24CA1541 RH Mining v Summit County 07-03-2025
COLORADO COURT OF APPEALS
Court of Appeals No. 24CA1541 Summit County District Court No. 23CV30070 Honorable Karen A. Romeo, Judge
RH Mining Claims, LLC,
Plaintiff-Appellant,
v.
Summit County Board of Adjustment,
Defendant-Appellee.
JUDGMENT AFFIRMED
Division IV Opinion by JUDGE MEIRINK Freyre and Gomez, JJ., concur
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced July 3, 2025
Ingenuity Law Colorado, Alexander Dorotik, Denver, Colorado, for Plaintiff- Appellant
Hamre, Rodriguez, Ostrander & Prescott, P.C., Donald M. Ostrander, Emily N. Ostrander, Englewood, Colorado; Jeffrey L. Huntley, County Attorney, Cameron Turpin, Assistant County Attorney, Breckenridge, Colorado, for Defendant- Appellee ¶1 Plaintiff, RH Mining Claims, LLC (RH Mining), appeals the
district court’s order regarding RH Mining’s complaint for judicial
review under C.R.C.P. 106(a)(4). The district court partially granted
the motion of defendant, Summit County Board of Adjustment (the
BOA), to strike RH Mining’s amended reply brief and affirmed
Resolution No. 2023-05, which concerns RH Mining’s property. We
affirm the district court’s order granting the motion to strike a
portion of RH Mining’s amended reply brief and affirming
Resolution No. 2023-05.
I. Background
A. Factual Background
¶2 The subdivision at issue comprises 4.01 acres of land and
consists of twelve lots zoned for industrial purposes. Lot 11 is at
issue here. The original plan for the subdivision included only ten
lots. In 1979, Summit County’s regional planning commission met
to discuss the subdivision project, which by then included Lot 11
and Lot 12. At this meeting, the former planning director explained
that the intent was “to develop parking on Lot 11 for Lots 7, 8, 9 &
10” and that “Lots 11 and 12 need the common area to be
stipulated on the plat.”
1 ¶3 As shown in the figure below, the proposed plat did not
identify a common open area, but it labeled Lot 11 as “Open,
Parking, Snowstack” and did not assign floor space to Lots 11 and
12.
Proposed Subdivision Plat Detail for Lot 11
¶4 The proposed plat included a dotted line with a ninety-degree
angle in the middle of Lot 11 that ran parallel to the lot’s outer
borders. This line ran through several other parcels in the
subdivision and was identified in the plat as the “Building Setback
Line.” In a “Detailed Submittal and Final Plat” for the subdivision
submitted in November 1979, the project description stated that
19.7% of the subdivision would be designated common open area
“to accommodate channel of French Creek, common parking and a
common leach field and storage area.”
2 ¶5 In January 1980, the developer and the chairman of the
Summit County Board of Commissioners (BOCC) signed an
“Improvements Agreement” to ensure phased construction of utility
improvements to support future development on Lots 1 through 10,
which would be known as “French Creek Center, Phase I.” The
Improvements Agreement did not mention Lot 11 or 12.
¶6 Later that year, the BOCC approved and recorded the final
subdivision plat, which is partially shown below. The final plat
largely resembled the proposed plat, but unlike the proposed plat,
the description underneath Lot 11’s acreage just read “Open,” and
“n/a” was written in the project data table cell for the floor space
allocated to Lots 11 and 12:
Final Subdivision Plat Detail for Lot 11
3 ¶7 Lot 11 remained undeveloped for forty years. In 2021, RH
Mining purchased it.
B. Procedural History
¶8 In September 2022, RH Mining applied to the Summit County
Planning Department (Planning Department) for a permit to install
a 900-square-foot portable storage unit on Lot 11. The Planning
Department denied the application because Lot 11 was platted as
an “open space parcel with no assigned density [and] [w]hen the lot
was platted, it was created as an open space parcel per the French
Creek Center Sub Plat.” Because it was a platted open space parcel
with no density assigned, the Planning Department concluded that
“no structure can be built on the site.”
¶9 RH Mining claimed that the denial improperly labeled Lot 11
as “open space” when the parcel was just labeled “open,” so the
Planning Department reconsidered its permit denial. It denied the
permit application again, but on different grounds and stated the
following:
It has been determined that the plat for Lot 11, French Creek Center Sub would not allow for any structures to be built on this lot regardless of whether the structure in question would count as floor area for the purposes of density.
4 During the platting of this lot, it was discussed that this lot may be able to be used as a common parking area for the other lots in Lot 11 but otherwise should remain open, per the plat for the French Creek Center Sub.
¶ 10 RH Mining appealed this denial to the BOA, which held a
hearing on the matter. Following the hearing, the BOA
unanimously voted to affirm the Planning Department’s decision for
the following reasons: (1) staff interpreted “open” to mean “free from
structures”; (2) the developer did not allocate any floor space to Lots
11 and 12; (3) the combined acreage of Lots 11 and 12 was 19.7%
of the total acreage of the subdivision, which was the same
percentage of land within the subdivision allocated as common
open area; and (4) the developer did not list Lots 11 and 12 as
intended for development in Phase I of the Improvements
Agreement.
¶ 11 The BOA then adopted Resolution No. 2023-05, which made
two findings:
1. The use of the word “open” and the lack of allocated floor
area on the plat, combined with the description in the
materials from the preliminary and final platting process
that Lot 11 would be used for parking and snow storage,
5 supported the Code Administrator’s determination that
no structures should be allowed on the property.
2. There is a process in the Summit County Land Use and
Development Code (Code) by which the applicant could
request additional density and/or uses for the property,
and the BOA appeal process is not a substitute for the
proper procedure.
¶ 12 RH Mining filed a complaint for judicial review of the BOA’s
decision under C.R.C.P. 106(a)(4). RH Mining contended that the
words “open” and “n/a” signaled that “at the time of the [plat’s]
approval, it was unclear how Lot 11 would be developed in the
future and thus remained ‘open,’” and therefore the plat does not
prohibit structures or density on Lot 11. RH Mining did not discuss
the Building Setback Line.
¶ 13 In its opening brief, RH Mining asserted: (1) that the BOA
applied an incorrect framework by not referencing the Code when
interpreting the plat; (2) that the BOA abused its discretion by
failing to resolve any ambiguity in the plat; and (3) that because the
plat was ambiguous, the BOA was required to adjudicate the
application consistent with the Code. Again, it did not raise the
6 issue of the Building Setback Line. The BOA’s answer brief also did
not raise arguments relating to the Building Setback Line The
Free access — add to your briefcase to read the full text and ask questions with AI
24CA1541 RH Mining v Summit County 07-03-2025
COLORADO COURT OF APPEALS
Court of Appeals No. 24CA1541 Summit County District Court No. 23CV30070 Honorable Karen A. Romeo, Judge
RH Mining Claims, LLC,
Plaintiff-Appellant,
v.
Summit County Board of Adjustment,
Defendant-Appellee.
JUDGMENT AFFIRMED
Division IV Opinion by JUDGE MEIRINK Freyre and Gomez, JJ., concur
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced July 3, 2025
Ingenuity Law Colorado, Alexander Dorotik, Denver, Colorado, for Plaintiff- Appellant
Hamre, Rodriguez, Ostrander & Prescott, P.C., Donald M. Ostrander, Emily N. Ostrander, Englewood, Colorado; Jeffrey L. Huntley, County Attorney, Cameron Turpin, Assistant County Attorney, Breckenridge, Colorado, for Defendant- Appellee ¶1 Plaintiff, RH Mining Claims, LLC (RH Mining), appeals the
district court’s order regarding RH Mining’s complaint for judicial
review under C.R.C.P. 106(a)(4). The district court partially granted
the motion of defendant, Summit County Board of Adjustment (the
BOA), to strike RH Mining’s amended reply brief and affirmed
Resolution No. 2023-05, which concerns RH Mining’s property. We
affirm the district court’s order granting the motion to strike a
portion of RH Mining’s amended reply brief and affirming
Resolution No. 2023-05.
I. Background
A. Factual Background
¶2 The subdivision at issue comprises 4.01 acres of land and
consists of twelve lots zoned for industrial purposes. Lot 11 is at
issue here. The original plan for the subdivision included only ten
lots. In 1979, Summit County’s regional planning commission met
to discuss the subdivision project, which by then included Lot 11
and Lot 12. At this meeting, the former planning director explained
that the intent was “to develop parking on Lot 11 for Lots 7, 8, 9 &
10” and that “Lots 11 and 12 need the common area to be
stipulated on the plat.”
1 ¶3 As shown in the figure below, the proposed plat did not
identify a common open area, but it labeled Lot 11 as “Open,
Parking, Snowstack” and did not assign floor space to Lots 11 and
12.
Proposed Subdivision Plat Detail for Lot 11
¶4 The proposed plat included a dotted line with a ninety-degree
angle in the middle of Lot 11 that ran parallel to the lot’s outer
borders. This line ran through several other parcels in the
subdivision and was identified in the plat as the “Building Setback
Line.” In a “Detailed Submittal and Final Plat” for the subdivision
submitted in November 1979, the project description stated that
19.7% of the subdivision would be designated common open area
“to accommodate channel of French Creek, common parking and a
common leach field and storage area.”
2 ¶5 In January 1980, the developer and the chairman of the
Summit County Board of Commissioners (BOCC) signed an
“Improvements Agreement” to ensure phased construction of utility
improvements to support future development on Lots 1 through 10,
which would be known as “French Creek Center, Phase I.” The
Improvements Agreement did not mention Lot 11 or 12.
¶6 Later that year, the BOCC approved and recorded the final
subdivision plat, which is partially shown below. The final plat
largely resembled the proposed plat, but unlike the proposed plat,
the description underneath Lot 11’s acreage just read “Open,” and
“n/a” was written in the project data table cell for the floor space
allocated to Lots 11 and 12:
Final Subdivision Plat Detail for Lot 11
3 ¶7 Lot 11 remained undeveloped for forty years. In 2021, RH
Mining purchased it.
B. Procedural History
¶8 In September 2022, RH Mining applied to the Summit County
Planning Department (Planning Department) for a permit to install
a 900-square-foot portable storage unit on Lot 11. The Planning
Department denied the application because Lot 11 was platted as
an “open space parcel with no assigned density [and] [w]hen the lot
was platted, it was created as an open space parcel per the French
Creek Center Sub Plat.” Because it was a platted open space parcel
with no density assigned, the Planning Department concluded that
“no structure can be built on the site.”
¶9 RH Mining claimed that the denial improperly labeled Lot 11
as “open space” when the parcel was just labeled “open,” so the
Planning Department reconsidered its permit denial. It denied the
permit application again, but on different grounds and stated the
following:
It has been determined that the plat for Lot 11, French Creek Center Sub would not allow for any structures to be built on this lot regardless of whether the structure in question would count as floor area for the purposes of density.
4 During the platting of this lot, it was discussed that this lot may be able to be used as a common parking area for the other lots in Lot 11 but otherwise should remain open, per the plat for the French Creek Center Sub.
¶ 10 RH Mining appealed this denial to the BOA, which held a
hearing on the matter. Following the hearing, the BOA
unanimously voted to affirm the Planning Department’s decision for
the following reasons: (1) staff interpreted “open” to mean “free from
structures”; (2) the developer did not allocate any floor space to Lots
11 and 12; (3) the combined acreage of Lots 11 and 12 was 19.7%
of the total acreage of the subdivision, which was the same
percentage of land within the subdivision allocated as common
open area; and (4) the developer did not list Lots 11 and 12 as
intended for development in Phase I of the Improvements
Agreement.
¶ 11 The BOA then adopted Resolution No. 2023-05, which made
two findings:
1. The use of the word “open” and the lack of allocated floor
area on the plat, combined with the description in the
materials from the preliminary and final platting process
that Lot 11 would be used for parking and snow storage,
5 supported the Code Administrator’s determination that
no structures should be allowed on the property.
2. There is a process in the Summit County Land Use and
Development Code (Code) by which the applicant could
request additional density and/or uses for the property,
and the BOA appeal process is not a substitute for the
proper procedure.
¶ 12 RH Mining filed a complaint for judicial review of the BOA’s
decision under C.R.C.P. 106(a)(4). RH Mining contended that the
words “open” and “n/a” signaled that “at the time of the [plat’s]
approval, it was unclear how Lot 11 would be developed in the
future and thus remained ‘open,’” and therefore the plat does not
prohibit structures or density on Lot 11. RH Mining did not discuss
the Building Setback Line.
¶ 13 In its opening brief, RH Mining asserted: (1) that the BOA
applied an incorrect framework by not referencing the Code when
interpreting the plat; (2) that the BOA abused its discretion by
failing to resolve any ambiguity in the plat; and (3) that because the
plat was ambiguous, the BOA was required to adjudicate the
application consistent with the Code. Again, it did not raise the
6 issue of the Building Setback Line. The BOA’s answer brief also did
not raise arguments relating to the Building Setback Line The
district court granted RH Mining a seven-day extension to file its
reply brief, which was eventually timely filed.
¶ 14 Two days later, however, with no leave from the court or
conferral with the BOA, RH Mining filed an amended reply brief
containing arguments related to the Building Setback Line. The
BOA moved to strike the amended reply brief or, in the alternative,
for leave to file a surreply brief. RH Mining filed a response to the
motion, and the BOA filed its reply.
¶ 15 The district court granted the BOA’s motion to strike RH
Mining’s argument concerning the Building Setback Line,
concluding that it presented a new argument not raised in the
opening brief. The court also affirmed Resolution No. 2023-05 and
held (1) the plat unambiguously prohibits any structures from being
built on Lot 11; and (2) assuming that the plat was ambiguous,
extraneous evidence showed that the plat intended for no
structures to be built on Lot 11.
¶ 16 RH Mining appeals.
7 II. Discussion
¶ 17 RH Mining contends that the district court erred by (1) striking
all information concerning the Building Setback Line and
concluding that RH Mining waived this argument; (2) concluding
the plat unambiguously prohibited structures from being built on
Lot 11; and (3) concluding that extraneous evidence showed the
plat intended for no structures to be built on Lot 11.1 We disagree
with these contentions and address each in turn.
A. The District Court Did Not Err by Partially Granting the BOA’s Motion to Strike
¶ 18 RH Mining contends that the district court erroneously struck
part of RH Mining’s amended reply brief, which waived all
information pertaining to the Building Setback Line from the record
and precluded RH Mining from making an argument based on it.
We disagree.
1 RH Mining’s opening brief does not comply with C.A.R. 28(a)(7)(A),
which requires citation to the record and for the appellant to indicate whether the issues raised were preserved on appeal. We decline to impose sanctions under C.A.R. 38(a) but remind counsel of the obligation litigants have to comply with the rules. See Castillo v. Koppes-Conway, 148 P.3d 289, 291 (Colo. App. 2006) (recognizing that it is the litigant’s duty to locate and synthesize relevant facts and arguments, and this duty should not be given to the appellate court).
8 ¶ 19 “We review a district court’s decision to accept or reject a brief
for an abuse of discretion.” Migoya v. Wheeler, 2024 COA 124,
¶ 23. A district court abuses its discretion only “if its decision is
manifestly unreasonable, arbitrary, or unfair, or it misapplies the
law.” HMLL LLC v. MJM Holdings Ltd., 2024 COA 85, ¶ 17.
¶ 20 Generally, a court will not consider arguments raised for the
first time in a reply brief. See IBC Denver II, LLC v. City of Wheat
Ridge, 183 P.3d 714, 718 (Colo. App. 2008).
¶ 21 RH Mining maintains that by striking the Building Setback
Line argument in its amended reply brief, the district court
“deliberately ignored a portion of the record” when conducting its
judicial review. This is inaccurate. By partially granting the BOA’s
motion to strike, the district court did not “waive part of the record”;
rather it waived RH Mining’s ability to raise a Building Setback
Line-related argument for the first time in a reply brief.
¶ 22 By waiting to raise the argument until it filed its amended (and
untimely) reply brief in the district court, RH Mining denied the
BOA the opportunity to consider and respond to that argument at
the administrative level and the district court level. See, e.g.,
Widder v. Durango Sch. Dist. No. 9-R, 85 P.3d 518, 526 (Colo. 2004)
9 (recognizing that judicial review under C.R.C.P. 106(a)(4)
“contemplates that the district court will review the record of the
proceedings conducted elsewhere” and “[will] not contemplate a new
evidentiary hearing at the district court level”); In re Marriage of
Drexler, 2013 COA 43, ¶ 27 (arguments raised for the first time in a
reply brief are not considered for appellate review).
¶ 23 We conclude that the court did not abuse its discretion by
partially granting the BOA’s motion to strike RH Mining’s amended
reply brief.
B. Review of the BOA’s Administrative Decision Under C.R.C.P. 106(a)(4)
¶ 24 RH Mining contends that the BOA erred by denying RH
Mining’s appeal and affirming the Planning Department’s
determination. Again, we disagree.
1. Standard of Review and Applicable Law
¶ 25 Our review under C.R.C.P. 106(a)(4) is limited to “a
determination of whether the [governmental] body or officer has
exceeded its jurisdiction or abused its discretion, based on the
evidence in the record before the defendant body or officer.”
C.R.C.P. 106(a)(4)(I). The appropriate consideration for an appellate
10 court is whether there is sufficient evidentiary support for the
decision reached by the administrative tribunal, not whether there
is adequate evidentiary support for the lower court’s decision. See
City of Colorado Springs v. Givan, 897 P.2d 753, 756 (Colo. 1995).
Therefore, an appellate court is in the same position as the district
court when reviewing a decision under Rule 106(a)(4). Ad Two, Inc.
v. City & Cnty. of Denver, 9 P.3d 373, 376 (Colo. 2000).
¶ 26 In conducting our review, we apply a deferential standard and
“we may not disturb the governmental body’s decision absent a
clear abuse of discretion.” Langer v. Bd. of Comm’rs, 2020 CO 31,
¶ 13. “A governmental entity abuses its discretion only when it
applies an erroneous legal standard or when no competent evidence
in the record supports its ultimate decision.” Id. We will only reach
this conclusion if the BOA’s decision was “so devoid of evidentiary
support” that the decision was arbitrary and capricious. Freedom
Colo. Info., Inc. v. El Paso Cnty. Sheriff’s Dep’t, 196 P.3d 892, 900
(Colo. 2008).
¶ 27 But when the decision involves the interpretation of recorded
instruments, we review it de novo. See Ad Two, 9 P.3d at 376; Pulte
Home Corp. v. Countryside Cmty. Ass’n, 2016 CO 64, ¶ 23. “In
11 doing so, we give words and phrases their common meanings and
will enforce such documents as written if their meaning is clear.”
Pulte, ¶ 23. We only consider extraneous evidence to prove intent
when the meaning of a term is unclear or ambiguous on its face.
Ad Two, 9 P.3d at 376. A term is ambiguous if it has more than
one reasonable interpretation. Id. Mere differences in opinion
between parties over how to interpret the instrument does not
create an ambiguity. Id.
2. Analysis
a. The Plat Unambiguously Prohibits Any Structures from Being Built on Lot 11
¶ 28 RH Mining contends that the terms of the plat were
ambiguous and that the plat was subject to multiple reasonable
interpretations. We disagree.
¶ 29 The plat identifies all twelve parcels, their perimeters, and
their respective acreage. Notably, Lots 1 through 10 do not contain
any words under their acreage, while Lots 11 and 12 do. Lot 11 is
labeled “open” and the words “leach field” and “snowstack” appear
on Lot 12. The plat also contains a project data table that identifies
each parcel, its area, and its floor space. Lots 1 through 10 are
12 assigned floor space, but Lots 11 and 12 have no floor space.
Instead, the term “n/a” is written in their floor space cell.
¶ 30 The plat does not define what the terms “open,” “floor space,”
or “n/a” mean, so we look to their plain meanings. See Sch. Dist.
No. 1 v. Denver Classroom Tchrs. Ass’n, 2019 CO 5, ¶ 13 (in
determining whether certain terms of an instrument are
ambiguous, “[w]e may consult with definitions in recognized
dictionaries to give undefined words their plain and generally
accepted meaning”).
¶ 31 The word “open” has several definitions, including “having no
enclosing or confining barrier”; “completely free from concealment:
exposed to general view or knowledge”; “not restricted to a
particular group or category of participants”; and “presenting no
obstacle to passage or view: not enclosed, obstructed, or filled with
objects.” Merriam-Webster Dictionary, https://perma.cc/SK55-
6DNT.
¶ 32 “Floor space” is defined as “the area of the floor of a building
such as a shop, office, or factory.” Cambridge Dictionary,
https://perma.cc/ZJF5-SGMP.
13 ¶ 33 “N/a” is an abbreviation for several terms, including “not
applicable” and “not available.” Merriam-Webster Dictionary,
https://perma.cc/HH3H-2SRL.
¶ 34 Giving the words defined above their common meaning, we
conclude that “open” as used in the plat means “having no
enclosing or confining barrier” and “presenting no obstacle to
passage or view: not enclosed, obstructed, or filled with objects.”
This is consistent with the way that the floor space for Lots 11 and
12 was marked “n/a” to mean no square footage was allocated for a
building or structure on these two parcels. See, e.g., Premier Farm
Credit, PCA v. W-Cattle, LLC, 155 P.3d 504, 517 (Colo. App. 2006)
(recognizing that the written document’s “language must be
examined and construed in harmony with the plain and generally
accepted meaning of the words used, and reference must be made
to all the agreement’s provisions” (quoting Fibreglas Fabricators, Inc.
v. Kylberg, 799 P.2d 371, 374 (Colo. 1990))).
¶ 35 RH Mining argues that if there was no intent to allow
structures on Lot 11, it would be unnecessary for the plat to
include a Building Setback Line on Lot 11 and including a setback
renders the plat ambiguous. In support, RH Mining cites Section
14 3505.13 of the Code, which defines a setback as “an undeveloped
open area of fixed width within a parcel along the front, side or rear
property line which shall remain free of any development and no
building, structural improvement or paving is to be placed in any
required setback except as provided in Section 3505.13.F. and G.”
By including setbacks on Lot 11, RH Mining contends that
buildings are allowed on Lot 11 as long as they are not located
within the setbacks.
¶ 36 RH Mining’s contention is misplaced. All the parcels have
building setbacks — not just Lot 11. What distinguishes Lot 11 is
that, in addition to a setback, which is intended to be an
undeveloped area along the parcel’s perimeter, Lot 11 has the word
“open,” which we have already indicated means “presenting no
obstacle to passage or view.” Unlike Lots 1 through 10, which
permit structures to be erected — except within the setback areas
— no structures were intended for placement inside or outside of
Lot 11’s Building Setback Line. Thus, even applying the Code’s
definition of a setback, there is no ambiguity or conflict with the
conclusion that no buildings were intended on Lot 11.
15 b. Extraneous Evidence Supports the BOA’s Finding that the Plat Intended for No Structures to Be Built on Lot 11
¶ 37 Even if the plat is ambiguous, the following extraneous
evidence supports the BOA’s conclusion that no structures were
intended to be built on Lot 11:
• At the regional planning commission meeting in 1979,
the former planning director explained that “the concept
[wa]s to develop parking on Lot 11 for Lots 7, 8, 9, & 10.”
• The final proposed project description allocated 19.7% of
the subdivision as “common open area to accommodate
the channel of French Creek, common parking and a
common leach field and storage area.” The combined
acreage of Lots 11 and 12, which is calculated in the
project data table on the plat, totals 0.79 acres —
roughly 19.7% of the subdivision’s 4.01 acres. Nothing
in the record indicates that the Planning Department
changed this designation.
• The developer and BOCC chairman signed an
Improvements Agreement to construct utilities and
improvements on the subdivision. The agreement
16 included Lots 1 through 10 but did not mention Lot 11 or
¶ 38 Having considered this extraneous information, we conclude
that the BOA did not err in finding that no structures can be built
on Lot 11.
III. Disposition
¶ 39 Accordingly, we affirm the district court’s judgment granting
the BOA’s motion to strike the Building Setback Line argument
from RH Mining’s amended reply brief and affirming Resolution
No. 2023-05.
JUDGE FREYRE and JUDGE GOMEZ concur.