Reytec Construction Resources, Inc. v. Baptist Hospitals of Southeast Texas

Court of Appeals of Texas·Decided November 23, 2016·No. 09-15-00085-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-15-00085-CV

REYTEC CONSTRUCTION RESOURCES, INC., Appellant V.

BAPTIST HOSPITALS OF SOUTHEAST TEXAS, Appellee

On Appeal from the 60th District Court Jefferson County, Texas

Trial Cause No. B-193,365

MEMORANDUM OPINION

Reytec Construction Resources, Inc. (“Reytec”) appeals the trial court’s amended final judgment granting summary judgment in favor of Baptist Hospitals of Southeast Texas (the “Hospital”). Reytec presents four issues on appeal. Because we conclude that Reytec raised a genuine issue of material fact precluding summary judgment on the Hospital’s breach of contract claim, we reverse the trial court’s judgment and remand this cause for further proceedings.

I. Background

Reytec is in the underground utility and road-construction business. The City of Beaumont hired Reytec to perform a road-construction project, which entailed excavation, removal, and replacement of an old roadway and everything beneath the roadway, including the storm drainage system and waterlines. In connection with this project, Reytec entered into a Lease Agreement (the “Lease”) with the Hospital, whereby Reytec leased property (the “Property”) from the Hospital that was located near Reytec’s construction site to serve as a location for it to store its construction equipment. The Lease provided that Reytec could use the Property “solely for the purpose of a construction equipment storage and material laydown yard.” Relevant to the issues on appeal, Paragraph 12 of the Lease provides: “SURRENDER OF PREMISES. Upon the expiration of the term hereof, Tenant shall surrender the Premises in as good a state and condition as they were at the commencement of this Lease Agreement, reasonable use and wear and tear thereof and damages by the elements excepted.” The Lease was executed by David Parmer, the CEO of the Hospital and by Greg Reyes, Reytec’s owner and President.

In connection with the road-construction project, Reytec also required a place to deposit the materials it excavated, including concrete, dirt, and other

materials. During a preconstruction meeting with the Hospital, Reytec’s project manager and general superintendent, Thomas Gill, asked the Hospital if it wanted the dirt from the excavation of the road. At first the Hospital declined Gill’s offer, but later, Jessie Deville, the Administrative Director of Facilities for the Hospital, informed Gill that the Hospital did want the dirt to use in a future Hospital project. On March 22, 2010, Reytec and the Hospital entered into a “Dump Contract[.]”The relevant portion of the Dump Contract provides:

I acknowledge by my signature below that I accept delivery, possession, and responsibility for excavated material as is delivered to [the Property] by [Reytec] for the sum of $00.00 per load for a total of $00.00. I further acknowledge that [Reytec] is only obligated to stock-

pile material to allow for it to be mowed. Any surveying of property or land permits are the responsibility of the owner or representative of property where excavated material is to be delivered.

Deville signed the Dump Contract in his official capacity as the Hospital’s Administrative Director of Facilities.

There is evidence in the record to support that the Hospital gave Reytec access to the Property to start delivering excavated materials shortly after the Hospital entered into the Dump Contract with Reytec. But, approximately ten months later, on January 20, 2011, Deville asked Gill to remove the excavated materials from the Property. At that time, Gill reminded Deville that under the Dump Contract the excavated materials were the Hospital’s responsibility but gave

Deville an estimate on what Reytec would charge the Hospital to remove the materials.

The Lease term was scheduled to end February 28, 2011. The Hospital decided not to renew the Lease but agreed to a short lease extension to allow Reytec time to procure a new property. After securing a new property to serve as its laydown yard, Reytec began removing its construction equipment from the Property. On March 7, 2011, the Hospital’s attorney sent Reytec a letter threatening to “take immediate steps to have [Reytec] evicted” unless Reytec removed its equipment and the excavated materials from the Property. Reytec eventually removed all of its equipment but did not remove the excavated materials. After Reytec left the Property, Deville obtained quotes from two other companies to have the excavated materials removed. The Hospital secured the services of AAA Floodmasters and paid $100,000 to remove the excavated materials from the Property.

On October 17, 2012, the Hospital filed suit against Reytec, asserting claims for breach of contract based on the Lease. The Hospital amended its petition and asserted additional claims for breach of the Lease and also asserted an alternative claim for breach of contract based on the Dump Contract. The Hospital sought to recover the cost of removing the excavated materials from the Property, restoring

the Property to its pre-Lease condition, and claimed damages for diminished market value of the Property and the “loss of potential sale(s) of the [Property.]” The Hospital further sought attorney’s fees and its alleged costs associated with evicting Reytec from the Property.

Reytec filed a general denial of the Hospital’s allegations and asserted various affirmative defenses. Relevant to the issues on appeal, Reytec alleged that (1) the Hospital waived its right to assert its claims regarding the excavated materials through execution of the Dump Contract, (2) the Hospital released Reytec from all obligations or responsibilities concerning the excavated materials, and (3) the Dump Contract served as a modification of the Lease thereby relieving Reytec of any obligations and duties under the Lease regarding the excavated materials.

On November 14, 2014, the Hospital filed a second amended traditional and no-evidence motion for summary judgment. Therein, the Hospital sought summary judgment on its claims for breach of the Lease, breach of the Dump Contract, and Reytec’s affirmative defenses. On December 15, 2014, the trial court granted the Hospital’s motions for summary judgment in their entirety, and awarded the Hospital $100,000 in actual damages. The trial court also generally awarded the Hospital reasonable and necessary costs and attorney’s fees and pre-and post-

judgment interest. On February 19, 2015, the trial court amended its final judgment to include an award of $94,582.85 in attorney’s fees, $3,590.64 in taxable costs, and $10,833.33 in pre-judgment interest. The trial court also awarded the Hospital conditional appellate attorney’s fees, costs, and interest. Reytec appealed the trial court’s judgment.

II. Standard of Review

We review a trial court’s grant of a motion for summary judgment de novo.

Buck v. Palmer, 381 S.W.3d 525, 527 (Tex. 2012); Travelers Ins. Co. v. Joachim, 315 S.W.3d 860, 862 (Tex. 2010). A no-evidence motion for summary judgment under Rule 166a(i) must challenge at least one specific element of the opponent’s claim or defense on which the opponent will have the burden of proof at trial. Tex. R. Civ. P. 166a(i). The opponent must then present summary judgment evidence raising a genuine issue of material fact to support the challenged elements. Id. “The court must grant the motion unless the respondent produces summary judgment evidence raising a genuine issue of material fact” on the challenged elements. Id. A genuine issue of material fact is raised when the nonmovant produces more than a scintilla of evidence establishing the existence of the challenged element. Fort Worth Osteopathic Hosp., Inc. v. Reese, 148 S.W.3d 94, 99 (Tex. 2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Reytec Construction Resources, Inc. v. Baptist Hospitals of Southeast Texas, (Tex. Ct. App. 2016).

Reytec Construction Resources, Inc. v. Baptist Hospitals of Southeast Texas (Reytec Construction Resources, Inc. v. Baptist Hospitals of Southeast Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Fort Worth Osteopathic Hospital, Inc. v. Reese
148 S.W.3d 94 (Texas Supreme Court, 2004)
Little v. Texas Department of Criminal Justice
148 S.W.3d 374 (Texas Supreme Court, 2004)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Ulico Casualty Co. v. Allied Pilots Ass'n
262 S.W.3d 773 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Intec Systems, Inc. v. Lowrey
230 S.W.3d 913 (Court of Appeals of Texas, 2007)
Bank of Texas v. VR Electric, Inc.
276 S.W.3d 671 (Court of Appeals of Texas, 2008)
Case Corp. v. Hi-Class Business Systems of America, Inc.
184 S.W.3d 760 (Court of Appeals of Texas, 2006)
Brownlee v. Brownlee
665 S.W.2d 111 (Texas Supreme Court, 1984)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Martin v. Martin, Martin & Richards, Inc.
991 S.W.2d 1 (Court of Appeals of Texas, 1997)
FORECA, SA v. GRD Development Co., Inc.
758 S.W.2d 744 (Texas Supreme Court, 1988)
Arthur J. Gallagher & Co. v. Dieterich
270 S.W.3d 695 (Court of Appeals of Texas, 2008)
Anglo-Dutch Petroleum International, Inc. v. Haskell
193 S.W.3d 87 (Court of Appeals of Texas, 2006)
Pitman v. Lightfoot
937 S.W.2d 496 (Court of Appeals of Texas, 1996)