Reyna v. City of Portland

District Court, D. Oregon·Decided March 24, 2025·No. 3:21-cv-01839·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF OREGON

LIANI REYNA, Ca se No. 3:21-cv-01839-AR Plaintiff, OPINION AND ORDER v.

CITY OF PORTLAND, a municipal corporation, Defendant. _____________________________________ ARMISTEAD, United States Magistrate Judge As relevant to this motion, Reyna brings two whistleblower retaliation claims against the City of Portland, under ORS § 659A.199 (Claim 1) and ORS § 659A.203 (Claim 2). (Second Am. Compl. (Compl.), ECF No. 28.) In December 2024, the City filed a combined motion for judgment on the pleadings and summary judgment. (ECF No. 92.) On both motions, the City sought to dismiss Claims 1 and 2 in their entirety. (Id. at 7-8, 25-26, 29-32; see also id. at 36

Page 1 – OPINION AND ORDER Reyna v. City of Portland, 3:21-cv-01839-AR (asking the court to “enter judgment in the City’s favor on the entirety of [Reyna’s] [operative complaint]”).) On March 7, 2024, the court granted the City summary judgment on Claims 1 and 2, except to the extent those claims were based on the theory that the City compelled Reyna to participate in an interview in May 2019 because she filed a tort claim notice in March 2019. (Opinion and Order, ECF No. 113.) Reyna now asks for reconsideration or clarification of the court’s Opinion and Order under Federal Rule of Civil Procedure 60(b).1 That Rule allows a court to relieve a party from an earlier order because of “mistake, inadvertence, surprise, or excusable neglect,” or “any other

reason that justifies relief.” FED. R. CIV. P. 60(b)(1), (6). She contends that she should be allowed to proceed on Claims 1 and 2 under a constructive discharge theory—that is, on the theory that the City’s retaliatory conduct forced her to retire early. For the reasons explained below, Reyna’s motion is DENIED. A. Notice of Need to Present Evidence Regarding Constructive Discharge Claim Reyna appears to contend in her motion for reconsideration that she was not on notice that she needed to provide evidence regarding constructive discharge to survive summary judgment as to that claim. (Pl.’s Mot. at 3, ECF No. 116 (quoting the City’s motion, and contending that the City did not make “an argument about sufficiency of constructive discharge”).) That argument is unavailing for two reasons.

1 Reyna brings her motion under both Rule 60 and Rule 59(e). The court agrees with the City that its earlier order (ECF No. 113) is not a final judgment and a motion under Rule 59(e) is therefore inappropriate. Page 2 – OPINION AND ORDER Reyna v. City of Portland, 3:21-cv-01839-AR First, the City moved for judgment against Reyna’s claims in their entirety, and argued that she had neither alleged sufficient facts nor could she provide sufficient evidence to support any claim under ORS § 659A.199 or ORS § 659A.203. Second, the court explicitly told Reyna that she must point to both her allegations and evidence supporting each claim in her response to the City’s combined dispositive motion. During the status conference on December 31, 2024, the court informed Reyna that, whether through the court’s own motion or in resolving the City’s combined dispositive motion, the court required clarification of Reyna’s claims before trial, because Reyna’s theories on each claim remained unclear. (ECF No. 97.) Reyna agreed that all parties would benefit from narrowing or

clarifying her claims before trial. The court told both parties during that status conference that its forthcoming order would outline issues to be addressed in the remaining briefing on the City’s dispositive motions. That order, issued on January 2, 2025, instructed Reyna: In the course of responding to the City’s motions, [Reyna] must identify for each claim the elements needed to prove them, tie those elements to specific factual allegations, and point to evidence supporting each claim and their elements (including showing that she can establish a prima facie case for each claim). (ECF No. 98 at 3 (emphasis added).) Later in the Order, the court instructed Reyna, regarding Claims 1 and 2, that she “must provide evidence showing that she engaged in the alleged protected activity, that she suffered the alleged qualifying adverse employment action, and that there was a causal link between the protected activity and the adverse employment action.” (Id. at 6.) In sum, Reyna was on notice that, if she sought to bring a constructive discharge claim as part of Claims 1 and 2, she needed to provide evidence supporting that theory. Page 3 – OPINION AND ORDER Reyna v. City of Portland, 3:21-cv-01839-AR 2. Merits of Reyna’s Constructive Discharge Claim Reyna contends that the record before the court on summary judgment supports her constructive discharge claim. She points to four categories of evidence: (1) investigations into Reyna’s personal life, (2) “stonewalling” of her complaints, (3) evidence showing that Reyna’s decision to move to Florida was distinct from her decision to retire, and (4) evidence of harassment by individual officers. Regarding the “long string of intrusive investigations into [Reyna’s] personal life” (Pl.’s Mot. at 4), Reyna acknowledges that the court has already considered the evidence regarding those investigations. Although she characterizes those investigations as “intrusive” and as

evidence of intolerable working conditions, she leaves out that two of the investigations into her personal life were initiated by her own complaints. And she fails to point to evidence suggesting that the City would have investigated any of the complaints differently absent her protected activities. She also contends that the City “stonewall[ed]” her complaints, pointing to (1) her testimony that, after the Citizen Review Committee (CRC) released its report in 2020, PPB should have, but failed to, complete an investigation related to that report within 10 days, and (2) her deposition statements that the City “stonewalled” her complaints against Fox and Moore. (Pl.’s Mot. at 4 (citing First Reyna Dep. at 77:13-81:08).) As to the investigation regarding the CRC report, she provides no convincing argument as to how that delay, which occurred after

Reyna had already retired, is evidence of “intolerable working conditions” during her employment. (Id.) As to her deposition testimony that the City “stonewalled” her complaints, those assertions are conclusory and unsupported by the record. And her assurance that she “can Page 4 – OPINION AND ORDER Reyna v. City of Portland, 3:21-cv-01839-AR provide testimony on stonewalled complaints” is insufficient to establish a genuine issue for trial. See FED. R. CIV. P. 56(c); Cafasso v. Gen. Dynamics C4 Sys., 637 F.3d 1047, 1061 (9th Cir. 2011) (“To survive summary judgment, a plaintiff must set forth non-speculative evidence of specific facts, not sweeping conclusory allegations.”). Reyna also appears to contend that the court’s earlier Opinion and Order conflated Reyna’s decision to retire with her decision to move to Florida. She states that “the Court recognized [Reyna] said her ex-wife ‘forced [her] to retire’ by moving to Florida,” but points out that Reyna’s decisions to retire and move to Florida “were distinct.” (Pl.’s Mot. at 4.) Even assuming that the two decisions (to retire and to move to Florida) were completely unrelated, that

Free access — add to your briefcase to read the full text and ask questions with AI

Reyna v. City of Portland, (D. Or. 2025).

Reyna v. City of Portland (Reyna v. City of Portland) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pennsylvania State Police v. Suders
542 U.S. 129 (Supreme Court, 2004)
Cafasso v. General Dynamics C4 Systems, Inc.
637 F.3d 1047 (Ninth Circuit, 2011)
McGanty v. Staudenraus
901 P.2d 841 (Oregon Supreme Court, 1995)