[Cite as Reyes v. Kiwewa, 2024-Ohio-4524.]
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO
BUTLER COUNTY
JOSE REYES, : CASE NOS. CA2023-08-096 Appellee, : CA2023-09-099
: OPINION - vs - 9/16/2024 :
WILLY KIWEWA, :
Appellant. :
CIVIL APPEAL FROM BUTLER COUNTY AREA III COURT Case No. CVI2201250
Jose Reyes, pro se.
Willy Kiwewa, pro se.
BYRNE, P.J.
{¶ 1} Willy Kiwewa appeals from a decision of the Butler County Area III Court
which granted a small claims judgment in favor of Jose Reyes. For the reasons described
below, we affirm.
I. Factual and Procedural Background
{¶ 2} In December 2022, Reyes filed a small claims complaint against Kiwewa in Butler CA2023-08-096 CA2023-09-099
the Butler County Area III court. Reyes alleged that Kiwewa hired him to complete four
projects in Kiwewa's home and that he and Kiwewa had entered into an agreement on
pricing for labor and specific materials. Reyes alleged that during the project, a dispute
arose and Kiwewa refused him access to the home to complete the project. Reyes
claimed that Kiwewa owed him $2,208.36 for the balance of labor, materials, travel time,
and for a ladder that Kiwewa refused to allow him to retrieve. Kiwewa filed a
"counterclaim," in which he asserted that he only owed Reyes $350.
{¶ 3} The matter proceeded to a hearing before a magistrate in February 2023.
Kiwewa supplied a copy of the transcript of that hearing to this court. However, he did
not supply a transcript of the magistrate's hearing to the trial court after submitting his
objections to the magistrate's decision. For reasons that we will discuss later in this
opinion, we have not considered the transcript in deciding this appeal.
A. The Magistrate's Decision
{¶ 4} The magistrate, in his decision, found that in February 2022, Reyes and
Kiwewa entered into an agreement for remodeling projects at Kiwewa's home, which
included electric, plumbing, and lighting projects. The cost for Reyes' "work" (presumably
labor) was $8,450 and Kiwewa was to pay for the materials.
{¶ 5} The magistrate found that Reyes performed most of the agreed work and
Kiwewa made most of the payments to Reyes on the contract. However, the relationship
"broke down" after the parties disagreed over,
who was to pay for certain additional material, whether the parties had retained accurate records of how much had been paid and what was still owed, and whether Reyes should be paid for work that he had not yet completed after he was told by Kiwewa not to come back to his house.
{¶ 6} The magistrate noted that Reyes claimed that Kiwewa told him not to come
-2- Butler CA2023-08-096 CA2023-09-099
back to the home though Reyes was willing to finish the job. Kiwewa disputed this,
asserting that Reyes refused to finish the work unless he was paid the balance of what
he claimed he was owed. Kiwewa testified that he hired another person to finish the work
for $900.
{¶ 7} The magistrate also noted that at trial, Reyes claimed that he was owed the
balance on the contract price, which was $1,728.38. Also during trial, Reyes abandoned
his claim for compensation for the ladder.
{¶ 8} Kiwewa agreed that he would have owed Reyes $1,723.38 had Reyes
finished the work. But Kiwewa thought he was justified in not wanting Reyes to finish the
work until the issue of reimbursement for certain materials was resolved.
{¶ 9} The magistrate found that Kiwewa agreed to pay Reyes $8,450 and that
Kiwewa had paid $7,200, leaving a difference of $1,250. Kiwewa had to pay someone
else $900 to finish the contracted work. The magistrate noted that the difference between
$1,250 and $900 ($350) was the amount Kiwewa believed he owed Reyes.
{¶ 10} The magistrate found that from the evidence presented, it was "difficult" to
determine whether Kiwewa was justified in refusing to allow Reyes to finish the work.
However, the magistrate nonetheless found that Reyes remained willing to finish the work
and even made two unnecessary trips of 45 minutes each way to do so, and that it was
not Reyes' fault that Kiwewa chose to hire someone else to finish the work.
{¶ 11} On this basis, the magistrate found that Reyes was entitled to be paid
$1,250, the remaining balance on the contract price. However, the magistrate noted that
Reyes had introduced an exhibit demonstrating that he purchased $478.38 in certain
materials for the project and still possessed those materials. The magistrate found that
the cost of those materials was intended to be included in the $1,250 balance that Reyes
-3- Butler CA2023-08-096 CA2023-09-099
believed he was owed from Kiwewa. Accordingly, the magistrate deducted $478.38 from
the balance of $1,250 and found that Kiwewa owed Reyes $771.62 in damages. The
magistrate recommended judgment in favor of Reyes in that amount and dismissed
Reyes' counterclaim.
B. Objections and the Trial Court's Decision
{¶ 12} On March 9, 2023, Kiwewa objected to the magistrate's decision. In his
objections, Kiwewa argued that the contractual dispute was Reyes' fault. He claimed that
prior to the filing of the lawsuit, Reyes was demanding to be paid more than he was
entitled under the contract. Kiwewa also argued that the two "unnecessary" trips that
Reyes made to his property occurred before the conflict arose and involved some timing
issues with other contractors on the property.1 Finally, Kiwewa argued that he invited
Reyes to complete the work, and asked him to give him an estimate on the costs to finish
the work, but Reyes would not give him an estimate and instead told him not to contact
him in the future. Kiwewa claimed that he attempted to resolve the issue with Reyes but
Reyes would not compromise and then refused to finish the work.
{¶ 13} Also on March 9, 2023, Kiwewa filed a request for a transcript in support of
his objections. A notation on this filing indicates that someone (presumably the clerk)
notified Kiwewa that this form had not been "filled out" correctly and that Kiwewa had
stated he would correct the form the following Monday. The form appears to request the
transcript of a May 2023 hearing that had not yet occurred, which may have been the
issue causing the clerk to reject the form.
{¶ 14} Apparently Kiwewa did not correct the form as he indicated he would. But
1. Reyes asserted in his complaint that he was unable to timely complete some work because he was waiting on Kiwewa's other contractors to finish their portion of the project. -4- Butler CA2023-08-096 CA2023-09-099
two months later, on May 10, 2023, Kiwewa filed a second transcript request. This form
requested the preparation of the transcript of the February 2023 hearing before the
magistrate. However, there is a notation on the filing indicating a $400 charge to prepare
the transcript. The words "never contacted" and "No Transcript" appear after this
notation. The notation seemingly implies that Kiwewa never paid for the transcript.
Regardless of the meaning, no transcript was ever filed with the trial court.
{¶ 15} In July 2023, the trial court issued a decision overruling Kiwewa's objections
and adopting the magistrate's decision "because" Kiwewa had "failed to file a transcript
Free access — add to your briefcase to read the full text and ask questions with AI
[Cite as Reyes v. Kiwewa, 2024-Ohio-4524.]
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO
BUTLER COUNTY
JOSE REYES, : CASE NOS. CA2023-08-096 Appellee, : CA2023-09-099
: OPINION - vs - 9/16/2024 :
WILLY KIWEWA, :
Appellant. :
CIVIL APPEAL FROM BUTLER COUNTY AREA III COURT Case No. CVI2201250
Jose Reyes, pro se.
Willy Kiwewa, pro se.
BYRNE, P.J.
{¶ 1} Willy Kiwewa appeals from a decision of the Butler County Area III Court
which granted a small claims judgment in favor of Jose Reyes. For the reasons described
below, we affirm.
I. Factual and Procedural Background
{¶ 2} In December 2022, Reyes filed a small claims complaint against Kiwewa in Butler CA2023-08-096 CA2023-09-099
the Butler County Area III court. Reyes alleged that Kiwewa hired him to complete four
projects in Kiwewa's home and that he and Kiwewa had entered into an agreement on
pricing for labor and specific materials. Reyes alleged that during the project, a dispute
arose and Kiwewa refused him access to the home to complete the project. Reyes
claimed that Kiwewa owed him $2,208.36 for the balance of labor, materials, travel time,
and for a ladder that Kiwewa refused to allow him to retrieve. Kiwewa filed a
"counterclaim," in which he asserted that he only owed Reyes $350.
{¶ 3} The matter proceeded to a hearing before a magistrate in February 2023.
Kiwewa supplied a copy of the transcript of that hearing to this court. However, he did
not supply a transcript of the magistrate's hearing to the trial court after submitting his
objections to the magistrate's decision. For reasons that we will discuss later in this
opinion, we have not considered the transcript in deciding this appeal.
A. The Magistrate's Decision
{¶ 4} The magistrate, in his decision, found that in February 2022, Reyes and
Kiwewa entered into an agreement for remodeling projects at Kiwewa's home, which
included electric, plumbing, and lighting projects. The cost for Reyes' "work" (presumably
labor) was $8,450 and Kiwewa was to pay for the materials.
{¶ 5} The magistrate found that Reyes performed most of the agreed work and
Kiwewa made most of the payments to Reyes on the contract. However, the relationship
"broke down" after the parties disagreed over,
who was to pay for certain additional material, whether the parties had retained accurate records of how much had been paid and what was still owed, and whether Reyes should be paid for work that he had not yet completed after he was told by Kiwewa not to come back to his house.
{¶ 6} The magistrate noted that Reyes claimed that Kiwewa told him not to come
-2- Butler CA2023-08-096 CA2023-09-099
back to the home though Reyes was willing to finish the job. Kiwewa disputed this,
asserting that Reyes refused to finish the work unless he was paid the balance of what
he claimed he was owed. Kiwewa testified that he hired another person to finish the work
for $900.
{¶ 7} The magistrate also noted that at trial, Reyes claimed that he was owed the
balance on the contract price, which was $1,728.38. Also during trial, Reyes abandoned
his claim for compensation for the ladder.
{¶ 8} Kiwewa agreed that he would have owed Reyes $1,723.38 had Reyes
finished the work. But Kiwewa thought he was justified in not wanting Reyes to finish the
work until the issue of reimbursement for certain materials was resolved.
{¶ 9} The magistrate found that Kiwewa agreed to pay Reyes $8,450 and that
Kiwewa had paid $7,200, leaving a difference of $1,250. Kiwewa had to pay someone
else $900 to finish the contracted work. The magistrate noted that the difference between
$1,250 and $900 ($350) was the amount Kiwewa believed he owed Reyes.
{¶ 10} The magistrate found that from the evidence presented, it was "difficult" to
determine whether Kiwewa was justified in refusing to allow Reyes to finish the work.
However, the magistrate nonetheless found that Reyes remained willing to finish the work
and even made two unnecessary trips of 45 minutes each way to do so, and that it was
not Reyes' fault that Kiwewa chose to hire someone else to finish the work.
{¶ 11} On this basis, the magistrate found that Reyes was entitled to be paid
$1,250, the remaining balance on the contract price. However, the magistrate noted that
Reyes had introduced an exhibit demonstrating that he purchased $478.38 in certain
materials for the project and still possessed those materials. The magistrate found that
the cost of those materials was intended to be included in the $1,250 balance that Reyes
-3- Butler CA2023-08-096 CA2023-09-099
believed he was owed from Kiwewa. Accordingly, the magistrate deducted $478.38 from
the balance of $1,250 and found that Kiwewa owed Reyes $771.62 in damages. The
magistrate recommended judgment in favor of Reyes in that amount and dismissed
Reyes' counterclaim.
B. Objections and the Trial Court's Decision
{¶ 12} On March 9, 2023, Kiwewa objected to the magistrate's decision. In his
objections, Kiwewa argued that the contractual dispute was Reyes' fault. He claimed that
prior to the filing of the lawsuit, Reyes was demanding to be paid more than he was
entitled under the contract. Kiwewa also argued that the two "unnecessary" trips that
Reyes made to his property occurred before the conflict arose and involved some timing
issues with other contractors on the property.1 Finally, Kiwewa argued that he invited
Reyes to complete the work, and asked him to give him an estimate on the costs to finish
the work, but Reyes would not give him an estimate and instead told him not to contact
him in the future. Kiwewa claimed that he attempted to resolve the issue with Reyes but
Reyes would not compromise and then refused to finish the work.
{¶ 13} Also on March 9, 2023, Kiwewa filed a request for a transcript in support of
his objections. A notation on this filing indicates that someone (presumably the clerk)
notified Kiwewa that this form had not been "filled out" correctly and that Kiwewa had
stated he would correct the form the following Monday. The form appears to request the
transcript of a May 2023 hearing that had not yet occurred, which may have been the
issue causing the clerk to reject the form.
{¶ 14} Apparently Kiwewa did not correct the form as he indicated he would. But
1. Reyes asserted in his complaint that he was unable to timely complete some work because he was waiting on Kiwewa's other contractors to finish their portion of the project. -4- Butler CA2023-08-096 CA2023-09-099
two months later, on May 10, 2023, Kiwewa filed a second transcript request. This form
requested the preparation of the transcript of the February 2023 hearing before the
magistrate. However, there is a notation on the filing indicating a $400 charge to prepare
the transcript. The words "never contacted" and "No Transcript" appear after this
notation. The notation seemingly implies that Kiwewa never paid for the transcript.
Regardless of the meaning, no transcript was ever filed with the trial court.
{¶ 15} In July 2023, the trial court issued a decision overruling Kiwewa's objections
and adopting the magistrate's decision "because" Kiwewa had "failed to file a transcript
of the proceedings" in support of his objections, "and because the magistrate's conclusion
[was] justified by his recitation of the facts." The trial court awarded judgment in favor of
Reyes in the amount of $771.62 plus court costs and interest and dismissed Reyes'
counterclaim.
{¶ 16} Kiwewa appealed, raising one assignment of error.
II. Law and Analysis
{¶ 17} Kiwewa's sole assignment of error states:
THE TRIAL COURT ERRED BY DENYING DEFENDANT'[S] OBJECTION FOR FAILING TO FILE A TRANSCRIPT OF THE PROCEEDINGS.
{¶ 18} Kiwewa's assignment of error indicates that the trial court erred in adopting
the magistrate's decision because the trial court erroneously relied on Kiwewa's failure to
file a transcript of the hearing before the magistrate. However, other than referring to the
transcript in his assignment of error, Kiwewa does not present any argument concerning
this issue in his appellate brief. Instead, Kiwewa's brief reiterates the arguments
contained in his objections to the magistrate's decision. However, Kiwewa supports these
arguments with reference to the transcript of the hearing before the magistrate, which,
-5- Butler CA2023-08-096 CA2023-09-099
again, he only filed for the first time in this appeal.
A. Expectations of Pro Se Litigants
{¶ 19} Before addressing Kiwewa's assignment of error, we pause to note that
Kiwewa represented himself pro se in the trial court as well as on appeal. "[P]ro se
litigants are expected, as attorneys are, to abide by the relevant rules of procedure and
substantive laws, regardless of their familiarity with the law." Fontain v. H&R Cincy
Properties, L.L.C., 2022-Ohio-1000, ¶ 26 (12th Dist.). "As a result, pro se litigants are
presumed to have knowledge of the law and correct legal procedures so that they remain
subject to the same rules and procedures to which represented litigants are bound."
Havens v. Havens, 2022-Ohio-3103, ¶ 18 (12th Dist.). "In other words, '[p]ro se litigants
are not to be accorded greater rights and must accept the results of their own mistakes
and errors, including those related to correct legal procedure.'" Perelman v. Meade, 2021-
Ohio-4247, ¶ 22 (12th Dist.), quoting Cox v. Zimmerman, 2012-Ohio-226, ¶ 21 (12th
Dist.).
B. Failure to Support Objections with Transcript
{¶ 20} Civ.R. 53(D)(3)(b)(iii) provides that when a party objects to a factual finding
in a magistrate's decision, the objection "shall be supported by a transcript of all the
evidence submitted to the magistrate relevant to that finding or an affidavit of that
evidence if a transcript is not available." (Emphasis added.) We have previously
recognized the mandatory nature of this requirement. Levy v. Seiber, 2016-Ohio-68, ¶
17 (12th Dist.) ("A party's objection to a magistrate's factual finding must be supported
with a transcript or an affidavit of the evidence submitted to the magistrate."), citing Civ.R.
53(D)(3)(b)(iii).
{¶ 21} Civ.R. 53(D)(4)(d) provides that a trial court "shall" rule on objections to a
-6- Butler CA2023-08-096 CA2023-09-099
magistrate's decision that are timely filed. It further states that "In ruling on objections,
the court shall undertake an independent review as to the objected matters to ascertain
that the magistrate has properly determined the factual issues and appropriately applied
the law." Civ.R. 53(D)(4)(d). However, when an objecting party fails to timely file a
transcript or affidavit, "a trial court's independent review of the record is limited to an
examination of the magistrate's conclusions of law and recommendations in light of any
accompanying findings of fact." Levy at ¶ 18, citing Manninen v. Alvarez, 2014-Ohio-75,
¶ 21 (12th Dist.). Furthermore, when an objecting party fails to file a transcript or affidavit
of evidence with the trial court but filed the transcript with the appellate court, "the
appellate court is precluded from considering the transcript of the magistrate's hearing . .
. ." Id. citing State ex rel. Duncan v. Chippewa Twp. Trustees, 73 Ohio St.3d 728, 730
(1995); Singh v. Wadhwa, 2013-Ohio-3997, ¶ 20 (12th Dist.). In such a case, appellate
review "regarding factual issues is whether the trial court abused its discretion in applying
the law to the magistrate's factual findings." Id.
{¶ 22} As stated above, Kiwewa did not supply the trial court with a transcript of
the proceedings before the magistrate or an "affidavit of that evidence." But Kiwewa's
objections to the magistrate's decision as well as his reiterated arguments on appeal
challenge the factual findings of the magistrate and do not point to any legal errors. That
is, Kiwewa argues that the magistrate erred in finding that Reyes was willing and able to
complete his contracted work on the project and that Kiwewa wrongfully refused to allow
Reyes to complete the work. Kiwewa also argues that it was Reyes' improper calculation
of what was owed to him (and not Kiwewa's conduct), which led to the dispute.
{¶ 23} We find no error based upon our review. As stated above, Kiwewa only
presents factual arguments in this appeal, but we may not review such factual arguments
-7- Butler CA2023-08-096 CA2023-09-099
due to Kiwewa's failure to file with the trial court a transcript of the hearing before the
magistrate, or an affidavit of that evidence. Levy, 2016-Ohio-68 at ¶ 18. Otherwise, it
appears that the magistrate correctly applied the facts recited in the decision to the law.
The magistrate found that Reyes was contractually entitled to finish the project and thus
was entitled to the remainder of the contract price, minus costs for materials that Reyes
had included in the contract price and had not supplied to Kiwewa. Upon review, there is
nothing on the face of the magistrate's decision that would rise to the level of an abuse of
discretion. Id. We therefore overrule Kiwewa's sole assignment of error.
{¶ 24} Judgment affirmed.
HENDRICKSON and M. POWELL, JJ., concur.
-8-