Reyes v. Kiwewa
Opinion
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO BUTLER COUNTY
JOSE REYES, :
CASE NOS. CA2023-08-096
Appellee, : CA2023-09-099
: OPINION
- vs - 9/16/2024 :
WILLY KIWEWA, :
Appellant. :
CIVIL APPEAL FROM BUTLER COUNTY AREA III COURT Case No. CVI2201250
Jose Reyes, pro se. Willy Kiwewa, pro se.
BYRNE, P.J.
{¶ 1} Willy Kiwewa appeals from a decision of the Butler County Area III Court which granted a small claims judgment in favor of Jose Reyes. For the reasons described below, we affirm.
I. Factual and Procedural Background
{¶ 2} In December 2022, Reyes filed a small claims complaint against Kiwewa in
CA2023-09-099
the Butler County Area III court. Reyes alleged that Kiwewa hired him to complete four projects in Kiwewa's home and that he and Kiwewa had entered into an agreement on pricing for labor and specific materials. Reyes alleged that during the project, a dispute arose and Kiwewa refused him access to the home to complete the project. Reyes claimed that Kiwewa owed him $2,208.36 for the balance of labor, materials, travel time, and for a ladder that Kiwewa refused to allow him to retrieve. Kiwewa filed a "counterclaim," in which he asserted that he only owed Reyes $350.
{¶ 3} The matter proceeded to a hearing before a magistrate in February 2023.
Kiwewa supplied a copy of the transcript of that hearing to this court. However, he did not supply a transcript of the magistrate's hearing to the trial court after submitting his objections to the magistrate's decision. For reasons that we will discuss later in this opinion, we have not considered the transcript in deciding this appeal.
A. The Magistrate's Decision
{¶ 4} The magistrate, in his decision, found that in February 2022, Reyes and Kiwewa entered into an agreement for remodeling projects at Kiwewa's home, which included electric, plumbing, and lighting projects. The cost for Reyes' "work" (presumably labor) was $8,450 and Kiwewa was to pay for the materials.
{¶ 5} The magistrate found that Reyes performed most of the agreed work and Kiwewa made most of the payments to Reyes on the contract. However, the relationship "broke down" after the parties disagreed over,
who was to pay for certain additional material, whether the parties had retained accurate records of how much had been paid and what was still owed, and whether Reyes should be paid for work that he had not yet completed after he was told by Kiwewa not to come back to his house.
{¶ 6} The magistrate noted that Reyes claimed that Kiwewa told him not to come
CA2023-09-099
back to the home though Reyes was willing to finish the job. Kiwewa disputed this, asserting that Reyes refused to finish the work unless he was paid the balance of what he claimed he was owed. Kiwewa testified that he hired another person to finish the work for $900.
{¶ 7} The magistrate also noted that at trial, Reyes claimed that he was owed the balance on the contract price, which was $1,728.38. Also during trial, Reyes abandoned his claim for compensation for the ladder.
{¶ 8} Kiwewa agreed that he would have owed Reyes $1,723.38 had Reyes finished the work. But Kiwewa thought he was justified in not wanting Reyes to finish the work until the issue of reimbursement for certain materials was resolved.
{¶ 9} The magistrate found that Kiwewa agreed to pay Reyes $8,450 and that Kiwewa had paid $7,200, leaving a difference of $1,250. Kiwewa had to pay someone else $900 to finish the contracted work. The magistrate noted that the difference between $1,250 and $900 ($350) was the amount Kiwewa believed he owed Reyes.
{¶ 10} The magistrate found that from the evidence presented, it was "difficult" to determine whether Kiwewa was justified in refusing to allow Reyes to finish the work. However, the magistrate nonetheless found that Reyes remained willing to finish the work and even made two unnecessary trips of 45 minutes each way to do so, and that it was not Reyes' fault that Kiwewa chose to hire someone else to finish the work.
{¶ 11} On this basis, the magistrate found that Reyes was entitled to be paid $1,250, the remaining balance on the contract price. However, the magistrate noted that Reyes had introduced an exhibit demonstrating that he purchased $478.38 in certain materials for the project and still possessed those materials. The magistrate found that the cost of those materials was intended to be included in the $1,250 balance that Reyes
CA2023-09-099
believed he was owed from Kiwewa. Accordingly, the magistrate deducted $478.38 from the balance of $1,250 and found that Kiwewa owed Reyes $771.62 in damages. The magistrate recommended judgment in favor of Reyes in that amount and dismissed Reyes' counterclaim.
B. Objections and the Trial Court's Decision
{¶ 12} On March 9, 2023, Kiwewa objected to the magistrate's decision. In his objections, Kiwewa argued that the contractual dispute was Reyes' fault. He claimed that prior to the filing of the lawsuit, Reyes was demanding to be paid more than he was entitled under the contract. Kiwewa also argued that the two "unnecessary" trips that Reyes made to his property occurred before the conflict arose and involved some timing issues with other contractors on the property.1 Finally, Kiwewa argued that he invited Reyes to complete the work, and asked him to give him an estimate on the costs to finish the work, but Reyes would not give him an estimate and instead told him not to contact him in the future. Kiwewa claimed that he attempted to resolve the issue with Reyes but Reyes would not compromise and then refused to finish the work.
{¶ 13} Also on March 9, 2023, Kiwewa filed a request for a transcript in support of his objections. A notation on this filing indicates that someone (presumably the clerk) notified Kiwewa that this form had not been "filled out" correctly and that Kiwewa had stated he would correct the form the following Monday. The form appears to request the transcript of a May 2023 hearing that had not yet occurred, which may have been the issue causing the clerk to reject the form.
{¶ 14} Apparently Kiwewa did not correct the form as he indicated he would. But
1. Reyes asserted in his complaint that he was unable to timely complete some work because he was waiting on Kiwewa's other contractors to finish their portion of the project.
CA2023-09-099
two months later, on May 10, 2023, Kiwewa filed a second transcript request. This form requested the preparation of the transcript of the February 2023 hearing before the magistrate. However, there is a notation on the filing indicating a $400 charge to prepare the transcript. The words "never contacted" and "No Transcript" appear after this notation. The notation seemingly implies that Kiwewa never paid for the transcript. Regardless of the meaning, no transcript was ever filed with the trial court.
{¶ 15} In July 2023, the trial court issued a decision overruling Kiwewa's objections and adopting the magistrate's decision "because" Kiwewa had "failed to file a transcript of the proceedings" in support of his objections, "and because the magistrate's conclusion [was] justified by his recitation of the facts." The trial court awarded judgment in favor of Reyes in the amount of $771.62 plus court costs and interest and dismissed Reyes' counterclaim.
{¶ 16} Kiwewa appealed, raising one assignment of error.
II. Law and Analysis
{¶ 17} Kiwewa's sole assignment of error states:
THE TRIAL COURT ERRED BY DENYING DEFENDANT'[S]
OBJECTION FOR FAILING TO FILE A TRANSCRIPT OF THE PROCEEDINGS.
Free access — add to your briefcase to read the full text and ask questions with AI
2024 Ohio 4524 (Reyes v. Kiwewa) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.