Retail Builders, Inc. v. Margaret Latham

CourtCourt of Appeals of Tennessee
DecidedDecember 22, 2005
DocketM2004-00771-COA-R3-CV
StatusPublished

This text of Retail Builders, Inc. v. Margaret Latham (Retail Builders, Inc. v. Margaret Latham) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Retail Builders, Inc. v. Margaret Latham, (Tenn. Ct. App. 2005).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE July 12, 2005 Session

RETAIL BUILDERS, INC. v. MARGARET LATHAM

An Appeal from the Circuit Court for Sumner County No. 20350-C C. L. Rogers, Judge

No. M2004-00771-COA-R3-CV - Filed December 22, 2005

This is a construction case. The plaintiff construction manager agreed to manage the construction of a restaurant for the defendant restaurant owner. Preliminary documents showed that the construction manager agreed to provide its services for a guaranteed maximum price. During construction, there were unanticipated problems that increased costs. After construction was completed, the construction manager sought payments from the restaurant owner over and above the guaranteed maximum price, but the restaurant owner refused to pay more. The construction manager filed this lawsuit against the restaurant owner, claiming that the parties did not enter into an enforceable contract, and that the restaurant owner should pay the construction manager the reasonable value of its services under a theory of quantum meruit. After a bench trial, the trial court held in favor of the restaurant owner, determining that the parties had entered into a binding fixed price contract. The construction manager now appeals. We affirm in part and reverse in part the trial court’s determination and remand for further proceedings consistent with this opinion.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court is Affirmed in Part, Reversed in Part, and Remanded

HOLLY M. KIRBY , J., delivered the opinion of the Court, in which W. FRANK CRAWFORD , P.J., W.S., and DAVID R. FARMER , J., joined.

Robert L. DeLaney, Nashville, Tennessee, for the appellant, Retail Builders, Inc.

Curtis M. Lincoln, Hendersonville, Tennessee, for the appellee, Margaret Latham.

OPINION

Plaintiff Retail Builders, Inc. (“RBI”), is a construction company that is in the business of building and renovating restaurants. Joseph Embury (“Embury”) is the president of RBI. In some instances, RBI works as a general contractor, participating in the actual construction. In other instances, RBI provides construction management, where RBI often does not participate in the construction, but rather coordinates and supervises the construction.

In 1998, Defendant/Appellee Margaret Latham (“Latham”) met with Embury to discuss Latham hiring RBI to manage the construction of a restaurant called “The Light House.” The construction project became known as “The Light House Restaurant Project” (“the Project”). Later, Embury delivered to Latham a standardized “AIA Document”1 entitled “Standard Form of Agreement Between Owner and Construction Manager,” 1991 Edition. It is undisputed that neither party signed the AIA document.2 The parties dispute, however, whether handwritten notes were added to the AIA document reflecting Latham’s agreement to pay RBI 10% of the actual cost of work performed by RBI during the construction of the Project with a “[g]uaranteed maximum price under Amendment 1 Article 1.”

Latham hired Charles Hasty (“Hasty”) as the engineer on the Project, and she hired Tom Anderson (“Architect Anderson”) as the architect. She contracted with both Hasty and Architect Anderson to pay them directly for their services. RBI had no obligation to pay for the services of either Hasty or Architect Anderson out of the construction funds it was to receive.

In approximately May 1998, Latham sought to finalize financing for the Project. To obtain the necessary loan, she needed a document to present to the First Independent Bank (“Bank”). Toward this end, on May 12, 1998, before plans for the Project were completed, the parties executed a one-page standardized document entitled “Amendment No. 1 To Agreement Between Owner and Construction Manager” (“Amendment”). The Amendment provided:

Pursuant to Paragraph 2.2 of the Agreement, dated May 12, 1998, Margaret Latham (Owner) and Retail Builders, Inc. (Construction Manager), for The Light House Restaurant Project (The Project), the Owner and Construction Manager establish a Guaranteed Maximum Price and Contract Time for Work as set forth below: 1. $650,000.00 (Six hundred and fifty thousand dollars) guaranteed maximum price. 2. 120 day contract time.

Article I of the Amendment contained provisos stating that “Contract Documents (plans) not completed,” and that the “Guaranteed maximum price [is] based on incomplete plans, meetings with Owner and allowances itemized on Exhibit B.” Exhibit B is a list of nineteen (19) items and the respective cost allowance for those items totaling $650,000. Exhibit B states that the estimates were based on an April 6, 1998 site plan/landscape plan developed by Hasty, on preliminary drawings done by Architect Anderson in April 1998, and on discussions with Latham. Included in the list of

1 “AIA” is the American Institute of Architects.

2 In earlier proceedings in this case, on August 27, 2001, the trial court had ruled that the arbitration clause in the AIA document was unenforceable, because there had been “no meeting of the minds, no signed contract, and no oral agreement for any binding arbitration.”

-2- items were $57,000 in profit and overhead for RBI and $21,000 for contingencies. The Amendment purports to amend an “Agreement” dated May 12, 1998; however, there is no signed “Agreement” in the record, only the unsigned AIA document. No other written instruments were signed by either party at any time before or during construction.

Based in part on the Amendment, Latham obtained a $900,000 loan from the Bank. The loan was comprised of two parts — $650,000 for construction, and $250,000 for “Design, Furniture, and Equipment.”3 Latham was responsible for administering the $250,000 portion of her loan. As is explained below, the Bank administered the $650,000 upon application for payment from RBI.

Architect Anderson’s first set of architectural plans were dated May 20, 1998. Those plans classified the restaurant as a Type 6 building, which can be composed of wood. However, the City of Hendersonville interpreted its building codes to require that the restaurant be a Type 5 building, which must be built with noncombustible materials. In light of this, the plans were modified to make the structure a Type 5 building. Though RBI would later claim that it takes longer to build a Type 5 building, no changes were made to the 120-day completion time set out in the Amendment.

In addition, during the excavation process, rock was discovered where the foundation of the building was to be laid. Therefore, to avoid having to blast the rock to make way for the foundation, the plans were modified to raise the structure a few feet.

On August 4, 1998, the building permit for the Project was issued, and construction commenced soon thereafter. RBI, as the construction manager, received the invoices for all labor and materials expended on the Project. RBI engaged all of the subcontractors and purchased the construction materials used on the Project. As indicated above, RBI periodically prepared documents entitled “Application and Certificate for Payment” (“application for payment”) and submitted these to Latham, the architect, and the Bank for approval and payment. Each application for payment recited that the “original contract sum” was $650,000. Each application for payment also listed the amount completed, the amount due, and the remaining balance on the contract. Attached to each application was a continuation sheet with a list of nineteen (19) items to be completed and the projected cost for each item that mirrored Exhibit B of the Amendment. In one column, the actual amount expended on each item was listed. In this way, the actual cost of the Project could be compared with the budgeted price as of the date of each application for payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
Swafford v. Harris
967 S.W.2d 319 (Tennessee Supreme Court, 1998)
Mitchell v. Archibald
971 S.W.2d 25 (Court of Appeals of Tennessee, 1998)
Strickland v. Cartwright
117 S.W.3d 766 (Court of Appeals of Tennessee, 2003)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Book-Mart of Florida, Inc. v. National Book Warehouse, Inc.
917 S.W.2d 691 (Court of Appeals of Tennessee, 1995)
APCO Amusement Co. v. Wilkins Family Restaurants of America, Inc.
673 S.W.2d 523 (Court of Appeals of Tennessee, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Retail Builders, Inc. v. Margaret Latham, Counsel Stack Legal Research, https://law.counselstack.com/opinion/retail-builders-inc-v-margaret-latham-tennctapp-2005.