Resnic v. Toleas

56 Mass. App. Dec. 54
CourtMassachusetts District Court, Appellate Division
DecidedJuly 17, 1975
DocketNo. 8309; No.: 1118
StatusPublished
Cited by1 cases

This text of 56 Mass. App. Dec. 54 (Resnic v. Toleas) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Resnic v. Toleas, 56 Mass. App. Dec. 54 (Mass. Ct. App. 1975).

Opinion

Flynn, J.

This is an action of contract to recover $500.00 plus extra expenses for the alleged breach of a written contract whereby the defendant was to furnish labor and materials on the house of the plaintiff. The answer is a general denial, statute of limitations, justification for termination, and excuse of performance. The plaintiff’s answer to defendant’s declaration in set-off is a general denial, payment, work not done in a good and workmanlike manner, work of no value and expenditure for other work and illegality and voidness of the contract.

The court found for the defendant.

At the trial there was evidence tending to show:

Three days prior to June 14, 1973, the defendant and two men worked on the plaintiff’s home, and on June 14, 1973, at the request of the plaintiff, the de[56]*56fendant signed a contract, drawn by the plaintiff for the entire painting of the plaintiff’s home for the sum of $875.00 and the plaintiff paid the defendant the sum of $500.00.

The contract in susbtance stated that the contract price was $875.00 and that the work would be completed by June 30, 1973. The contract did not contain any provision that it could be cancelled under the provisions of G. L. c. 93, §48, and was signed at the plaintiff’s home.

The defendant worked for 5 or 6 days after June 14, 1973. The plaintiff attempted to contact the defendant without success and on June 27, 1973, the plaintiff wrote to the defendant ordering him to remove his equipment and terminated the contract. The plaintiff had complained about bubbles in the paint work, paint on shrubs and the front steps. The defendant had informed the plaintiff that he would complete the work to his satisfaction prior to the time that the work was to be completed. The plaintiff would not allow the defendant to complete the work.

Plaintiff claims to be aggrieved by the trial justice’s ruling on his requests for rulings ##1, 2, 4, 5, and 6. These requests and the trial justice’s disposition thereof are as follows:

Plaintiff's Requests for Rulings

1. Upon all the evidence a finding for the plaintiff is warranted because the defendant did not comply with the terms of the agreement. Denied. I find that the plaintiff would not permit the defendant to complete the work agreed upon prior to the time when the work was to be completed.

2. The plaintiff was justified in terminating the contract if the work was not done in a good [57]*57and workmanlike manner. Denied. This request is for a finding of fact and not for a ruling of law.

4. When a party binds itself by contract to do work or to perform a service, he agrees by implication to do a workmanlike job and use reasonable and appropriate care and skill in doing it. George v. Colman, 333 Mass. 496. Allowed. But see my findings.

5. Contracts should be construed in accordance with justice and common sense and probable intention of the parties. Bover v. Chalifour, 334 Mass. 348. Allowed. But see my findings.

6. The plaintiff could cancel the contract and recover monies thereunder because of the defendant’s failure to comply with G.L. c. 93 §48.1 Denied. This statute does not apply; if it did apply plaintiff cawnot avail himself of the statute as he failed to comply with the terms of the statute by failure to give notice of cancellation not later than midnight of the third business day following execution to the agreement.

[58]*58The trial justice found the following facts:

"I find that the plaintiff and defendant entered into an agreement to be performed within the month of June 1973, that before the end of June, namely on June 26, 1973, the plaintiff terminated the contract by requesting defendant to take his equipment from the premises and would not allow the defendant to complete the work, that upon the plaintiff’s own testimony the defendant was willing to complete the work to the plaintiff’s satisfaction. I therefore, find that the plaintiff breached his agreement with the defendant.”

The trial justice has found that the plaintiff breached the contract by not allowing the defendant to complete his work and he has further found that the defendant was willing to complete the work to the plaintiff’s satisfaction.

The creditability of the various witnesses and the weight to be given to their testimony are matters for the trial justice, Dolham v. Peterson, 297 Mass. 479, 481 (1937), and his findings if supportable on any reasonable view of the evidence cannot be disturbed. Weiner v. Egleston Amusement Co., 293 Mass.

[59]*5983 (1935). Furthermore, the Appellate Court can not disturb the general finding of the trial court when it is supported by any reasonable view of the evidence and rational inferences of which it was susceptible. Barttro v. Watertown Square Theatre, 309 Mass. 223 (1941). Castano v. Leone, 278 Mass. 429-431 (1932). Moss v. Old Colony Trust Co., 246 Mass. 139-143 and citations (1923). Weiner v. Egleston Amusement Co., 293 Mass. 83-86 (1935). Here, an inference may be drawn from the trial justice’s special findings, together with his general finding for the defendant, that the defendant, had he been allowed to complete his work but for the plaintiff’s action, could have completed his work in a satisfactory manner prior to the end of June or within « reasonable time thereafter.

Plaintiff argues that since the work was to done to his satisfaction his observation of bubbles in the paint, the paint on the shrubs and on the front steps, was sufficient justification for cancellation. However, there was finding here by the trial justice that the work that had been done by the defendant when the plaintiff terminated the contract on June 26, 1973 had not been done in a workmanlike manner [60]*60or, if so, that could not have been corrected. Nor was there any specific finding that the work performed was not satisfactory by objective standards. Ordinarily, the standard of satisfaction is considered to be a reasonable person or objective standard. Restatement, Contracts 2nd, §254, If there is doubt as to whether a personal standard or an objective standard is to be used it will be considered an objective standard. Hawkins v. Graham, 149 Mass. 284 (1889).

Although the trial justice found that the defendant was willing to complete the work to the plaintiff’s satisfaction, there was no such requirement in the original contract. It would appear, therefore, that there was only an implied objective standard of satisfaction in the contract up until June 27th, when the defendant offered to complete the work to the plaintiff’s satisfaction. From the justice’s finding that it was the plaintiff who breached the contract, a rational inference may be drawn that the justice applied such an objective standard and that by implication he found the paint job to be satisfactory on June 27th or, at least, that it was not in such a condition that it could not have been completed by June 30th, to the plaintiff’s satisfaction, or within a reasonable time thereafter if time was not of the essence.

Plaintiff argues that time was of the essence. Yet, the trial justice made no finding that time was of the essence or that the contract would have to be satisfactorily completed by June 30th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hodgson v. Phillip
1991 Mass. App. Div. 67 (Mass. Dist. Ct., App. Div., 1991)

Cite This Page — Counsel Stack

Bluebook (online)
56 Mass. App. Dec. 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/resnic-v-toleas-massdistctapp-1975.