NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
25-P-3
RESI, LLC
vs.
CONSERVATION COMMISSION OF WAREHAM.
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
The plaintiff, RESI, LLC, appeals from a Superior Court
judgment dismissing its certiorari complaint and allowing a
judgment on the pleadings in favor of the defendant, the
Conservation Commission of Wareham (commission). The plaintiff
argues that in denying it permission to build a pier, the
commission did not in fact rely on the town's wetland protective
bylaw (bylaw), and alternatively that the commission's decision
was arbitrary and capricious and unsupported by substantial
evidence. We affirm.
Background. In August 2022, the plaintiff filed with the
commission a notice of intent seeking approval to construct a
pier (including a float system, two boat lifts, and a ramp) to service the potential residents of a seven lot subdivision in
Wareham (project site or pier). The commission referred the
matter for comment to the Department of Marine Fisheries (DMF)
and the town's shellfish constable. The DMF responded that the
project site "lies adjacent to mapped shellfish habitat for
northern quahog . . . , bay scallop . . . , and soft-shell
clam," and in June 2022 quahogs were found within the project
site. The shellfish constable responded that the project site
was within an area that is used year round for both commercial
and recreational shellfishing. Nineteen town residents signed a
letter objecting to issuance of the permit, pointing out, among
other things, that the project site was in or near a protected
shellfish area and the plaintiff had failed to specify "the
proposed number, type and style of the proposed watercraft to be
used at the site," art. I, § XVI(C)(6) of the bylaw. After a
public hearing, the commission denied the plaintiff's
application, relying in its decision on art. I, §§ III, VII(2),
and XVI(C)(9) of the bylaw.1
The plaintiff filed this action for certiorari, arguing
that the commission's decision did not adequately explain how
1 The commission's decision cited art. I, § "VI(2)" of the bylaw. The plaintiff infers, and we concur, that was a typographical error for bylaw § VII(2). In addition, the definition of "significant shellfish habitat" relied upon by the commission appears in art. I, § III (not § VII).
2 the bylaw applied to these facts and was arbitrary, capricious,
unsupported by the evidence, and contrary to law. From the
Department of Environmental Protection (DEP), the plaintiff
sought a superseding order of conditions pursuant to the
Wetlands Protection Act (act), G. L. c. 131, § 40, nineteenth
par., and 310 Code Mass. Regs. § 10.05(7)(c) (2014). On April
7, 2023, the DEP issued a superseding order of conditions
opining that "the project as proposed . . . adequately protects
the interests of the . . . [a]ct. However, the project will
need to obtain approval under the local Wareham bylaw prior to
commencing work."
The parties filed cross motions for judgment on the
pleadings. The judge concluded that the commission relied on
sections of the bylaw that empower it to consider the cumulative
effects of the project on shellfish and shellfish habitat, which
the judge interpreted to permit it to consider the effects on
the area adjacent to the pier, particularly because the
plaintiff had failed to provide information about the proposed
number and size of boats that would use the pier. Judgment
entered, and the plaintiff appealed.
Discussion. We review de novo the allowance of a motion
for judgment on the pleadings. See Boston v. Conservation
Comm'n of Quincy, 490 Mass. 342, 345 (2022) (Boston). A civil
action for certiorari pursuant to G. L. c. 249, § 4, "is the
3 appropriate means of review" for the plaintiff to seek judicial
review of the commission's decision. Boston, supra at 344,
quoting Friedman v. Conservation Comm'n of Edgartown, 62 Mass.
App. Ct. 539, 542 (2004). Even so, we keep in mind that
certiorari "is a limited procedure reserved for correction of
substantial errors of law apparent on the record created before
a judicial or quasi judicial tribunal" (quotation and citation
omitted). Cumberland Farms, Inc. v. Board of Health of
Braintree, 495 Mass. 225, 231 (2025). "[W]here a conservation
commission 'rests its determination on provisions of a local
bylaw that are more protective than the act[,] . . . a
superseding order of conditions issued by the DEP cannot preempt
the conservation commission's bylaw-based determination.'"
Boston, supra at 345, quoting Oyster Creek Preservation, Inc. v.
Conservation Comm'n of Harwich, 449 Mass. 859, 865 (2007). In
relying on a more stringent local bylaw, a local conservation
commission must "explain how the bylaw . . . applies to the
facts presented." Boston, supra at 346. It is not enough to
"simply refer[] to" the bylaw; the commission must show "that it
actually relied on [the bylaw and] how it did so . . . ." Id.,
quoting Oyster Creek Preservation, Inc., supra at 866 n.12.
1. Commission's reliance on bylaw. The plaintiff argues
that the commission did not in fact rely on the bylaw, but
instead "simply interpret[ed] wetland protections differently
4 from [the DEP]," and thus the commission's decision is preempted
by the DEP's superseding order of conditions. We disagree. We
conclude that in its decision the commission relied on the
sections of the bylaw to which it cited, and which are more
stringent than the DEP regulations. Contrast Boston, 490 Mass.
at 347 (commission's decision "did not rely on the local
ordinance" but "cited . . . exclusively" to DEP regulations).
First, the commission relied on art. I, § XVI(C)(9) of the
bylaw (bylaw § XVI[C][9]), pertaining to coastal structures,
which provides: "Shellfish habitat evaluation. Piers shall not
be allowed to be constructed within significant shellfish
habitat as determined by the DMF and/or the Wareham Shellfish
Constable. The absence of shellfish may not mean that
productive shellfish habitat does not exist." Relying on that
section, the commission found that "[t]he installation of the
pier will result in the permanent loss of approximately 28 sq ft
of Significant Shellfish Habitat . . . ."
The plaintiff argues that the commission's finding that
there would be a loss of twenty-eight square feet of significant
shellfish habitat did not in fact rely on bylaw § XVI(C)(9), but
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
25-P-3
RESI, LLC
vs.
CONSERVATION COMMISSION OF WAREHAM.
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
The plaintiff, RESI, LLC, appeals from a Superior Court
judgment dismissing its certiorari complaint and allowing a
judgment on the pleadings in favor of the defendant, the
Conservation Commission of Wareham (commission). The plaintiff
argues that in denying it permission to build a pier, the
commission did not in fact rely on the town's wetland protective
bylaw (bylaw), and alternatively that the commission's decision
was arbitrary and capricious and unsupported by substantial
evidence. We affirm.
Background. In August 2022, the plaintiff filed with the
commission a notice of intent seeking approval to construct a
pier (including a float system, two boat lifts, and a ramp) to service the potential residents of a seven lot subdivision in
Wareham (project site or pier). The commission referred the
matter for comment to the Department of Marine Fisheries (DMF)
and the town's shellfish constable. The DMF responded that the
project site "lies adjacent to mapped shellfish habitat for
northern quahog . . . , bay scallop . . . , and soft-shell
clam," and in June 2022 quahogs were found within the project
site. The shellfish constable responded that the project site
was within an area that is used year round for both commercial
and recreational shellfishing. Nineteen town residents signed a
letter objecting to issuance of the permit, pointing out, among
other things, that the project site was in or near a protected
shellfish area and the plaintiff had failed to specify "the
proposed number, type and style of the proposed watercraft to be
used at the site," art. I, § XVI(C)(6) of the bylaw. After a
public hearing, the commission denied the plaintiff's
application, relying in its decision on art. I, §§ III, VII(2),
and XVI(C)(9) of the bylaw.1
The plaintiff filed this action for certiorari, arguing
that the commission's decision did not adequately explain how
1 The commission's decision cited art. I, § "VI(2)" of the bylaw. The plaintiff infers, and we concur, that was a typographical error for bylaw § VII(2). In addition, the definition of "significant shellfish habitat" relied upon by the commission appears in art. I, § III (not § VII).
2 the bylaw applied to these facts and was arbitrary, capricious,
unsupported by the evidence, and contrary to law. From the
Department of Environmental Protection (DEP), the plaintiff
sought a superseding order of conditions pursuant to the
Wetlands Protection Act (act), G. L. c. 131, § 40, nineteenth
par., and 310 Code Mass. Regs. § 10.05(7)(c) (2014). On April
7, 2023, the DEP issued a superseding order of conditions
opining that "the project as proposed . . . adequately protects
the interests of the . . . [a]ct. However, the project will
need to obtain approval under the local Wareham bylaw prior to
commencing work."
The parties filed cross motions for judgment on the
pleadings. The judge concluded that the commission relied on
sections of the bylaw that empower it to consider the cumulative
effects of the project on shellfish and shellfish habitat, which
the judge interpreted to permit it to consider the effects on
the area adjacent to the pier, particularly because the
plaintiff had failed to provide information about the proposed
number and size of boats that would use the pier. Judgment
entered, and the plaintiff appealed.
Discussion. We review de novo the allowance of a motion
for judgment on the pleadings. See Boston v. Conservation
Comm'n of Quincy, 490 Mass. 342, 345 (2022) (Boston). A civil
action for certiorari pursuant to G. L. c. 249, § 4, "is the
3 appropriate means of review" for the plaintiff to seek judicial
review of the commission's decision. Boston, supra at 344,
quoting Friedman v. Conservation Comm'n of Edgartown, 62 Mass.
App. Ct. 539, 542 (2004). Even so, we keep in mind that
certiorari "is a limited procedure reserved for correction of
substantial errors of law apparent on the record created before
a judicial or quasi judicial tribunal" (quotation and citation
omitted). Cumberland Farms, Inc. v. Board of Health of
Braintree, 495 Mass. 225, 231 (2025). "[W]here a conservation
commission 'rests its determination on provisions of a local
bylaw that are more protective than the act[,] . . . a
superseding order of conditions issued by the DEP cannot preempt
the conservation commission's bylaw-based determination.'"
Boston, supra at 345, quoting Oyster Creek Preservation, Inc. v.
Conservation Comm'n of Harwich, 449 Mass. 859, 865 (2007). In
relying on a more stringent local bylaw, a local conservation
commission must "explain how the bylaw . . . applies to the
facts presented." Boston, supra at 346. It is not enough to
"simply refer[] to" the bylaw; the commission must show "that it
actually relied on [the bylaw and] how it did so . . . ." Id.,
quoting Oyster Creek Preservation, Inc., supra at 866 n.12.
1. Commission's reliance on bylaw. The plaintiff argues
that the commission did not in fact rely on the bylaw, but
instead "simply interpret[ed] wetland protections differently
4 from [the DEP]," and thus the commission's decision is preempted
by the DEP's superseding order of conditions. We disagree. We
conclude that in its decision the commission relied on the
sections of the bylaw to which it cited, and which are more
stringent than the DEP regulations. Contrast Boston, 490 Mass.
at 347 (commission's decision "did not rely on the local
ordinance" but "cited . . . exclusively" to DEP regulations).
First, the commission relied on art. I, § XVI(C)(9) of the
bylaw (bylaw § XVI[C][9]), pertaining to coastal structures,
which provides: "Shellfish habitat evaluation. Piers shall not
be allowed to be constructed within significant shellfish
habitat as determined by the DMF and/or the Wareham Shellfish
Constable. The absence of shellfish may not mean that
productive shellfish habitat does not exist." Relying on that
section, the commission found that "[t]he installation of the
pier will result in the permanent loss of approximately 28 sq ft
of Significant Shellfish Habitat . . . ."
The plaintiff argues that the commission's finding that
there would be a loss of twenty-eight square feet of significant
shellfish habitat did not in fact rely on bylaw § XVI(C)(9), but
rather applied the less stringent DEP regulation, 310 Code Mass.
Regs. § 10.34(2) (2014), which pertains to "Land Containing
5 Shellfish."2 The plaintiff points out that bylaw § XVI(C)(9)
forbids building a pier "within significant shellfish habitat as
determined by the DMF" (emphasis added), but the DMF found that
the project site was only "adjacent to mapped shellfish habitat"
(emphasis added). Cf. Fafard v. Conservation Comm'n of Reading,
41 Mass. App. Ct. 565, 569-570 (1996) (by applying bylaw to
buffer zone to which it did not directly apply, town violated
principles of "uniformity of standards and enforcement").
However, the commission was also applying the second
sentence of bylaw § XVI(C)(9), which provides that "[t]he
absence of shellfish may not mean that productive shellfish
habitat does not exist." We read the commission's decision as
interpreting both sentences of bylaw § XVI(C)(9) to empower it
to deem the twenty-eight square foot area where the pier would
be built as a significant shellfish habitat because it was
adjacent to mapped shellfish habitat, quahogs had been found
within it, and the shellfish constable had reported that it was
used for commercial and recreational shellfishing. We give
2 Art. I, § III of the bylaw defines "significant shellfish habitat" to "include those areas of Lands Containing Shellfish designated and mapped as significant shellfish habitat for commercial or recreational use by the [DMF]." The DEP regulations define "Land Containing Shellfish" as "land under the ocean . . . when any such land contains shellfish," defined to include the species that the DMF found adjacent to the project site. 310 Code Mass. Regs. § 10.34(2).
6 deference to the commission's reasonable interpretation of its
bylaw. See Nelson v. Conservation Comm'n of Wayland, 90 Mass.
App. Ct. 133, 134 (2016).
Second, the commission relied on art. I, bylaw § VII(2)
(bylaw § VII[2]), which empowers it to consider "unacceptable
significant or cumulative effects" on the resource area values
protected by the bylaw, which include shellfish, land containing
shellfish, and the recreational value of the area. The
commission quoted the following language of that section:
"The Commission is empowered to deny a permit for failure to meet the requirements of this bylaw; for failure to submit necessary information and plans requested by the Commission; . . . for failure to avoid or prevent unacceptable significant or cumulative effects upon the resource area values protected by this bylaw; and where no conditions are adequate to protect those values."
Bylaw § VII(2). In applying that section to the facts of this
case, the commission permissibly considered not only the effect
that the project would have on shellfish directly under the
pier, but also the "unacceptable significant or cumulative
effects" on the area adjacent to the pier.
Unlike the Quincy bylaw discussed in Boston, 490 Mass. at
348-349, and like the Attleboro bylaw discussed in Cave Corp. v.
Conservation Comm'n of Attleboro, 91 Mass. App. Ct. 767, 773
(2017), the bylaw at issue here specified the cumulative effects
the commission should consider. Indeed, art. I, bylaw § XVI(A)
(bylaw § XVI[A]) describes in detail how "[t]he construction[,]
7 maintenance[,] and use of docks and piers are likely to have a
significant or cumulative effect on the resource area values of
. . . shellfish [and] shellfish habitat . . . ." It explains
that "[t]urbulence and prop dredging generated by boat traffic
around docks and piers significantly increases turbidity levels
in surrounding waters," which impacts the oxygen level of the
water and redistributes sediment, "smothering existing
shellfish" and "hinder[ing] or prevent[ing] the effective
settlement of shellfish larvae." Though the commission did not
cite to bylaw § XVI(A), it did cite to and quote from
§ XVI(C)(9), as discussed above. In those circumstances, we
interpret the commission's reliance on both §§ VII(2) and
XVI(C)(9) in its decision as having been informed by the
introductory subsection, § XVI(A), explaining the "significant
or cumulative" effects that it could consider. Contrast Boston,
supra (Quincy ordinance did not specify cumulative effects
commission should consider).
Moreover, as noted by the objecting townspeople and the
report of the commission's agent who visited the project site,
bylaw § XVI(C)(6) required the plaintiff to provide the
commission with information about the proposed number and size
of boats that would use the pier. The plaintiff argues that the
commission did not cite to that subsection of the bylaw, and the
judge placed too much emphasis on the lack of information about
8 boats. We are not persuaded. Even if the judge's analysis did
differ from that of the commission, that would not affect our de
novo review of the commission's decision. See S. Volpe & Co. v.
Board of Appeals of Wareham, 4 Mass. App. Ct. 357, 359-360
(1976).
The commission found that "the unknown number of boats"
adjacent to the pier would "result in additional loss of access
to Shellfish Habitat and Shellfish directly." We read that
reference to the "unknown number of boats" as applying the
portion of bylaw § VII(2) quoted by the commission that
empowered it to deny a permit "for failure to submit necessary
information and plans." Contrary to the plaintiff's argument,
where the plaintiff provided no information regarding the number
or size of boats that would use the pier, it was not the
commission's responsibility to propose conditions that would
satisfy the bylaw.
We conclude that the DEP's superseding order of conditions
did not preempt the commission from enforcing the town's more
stringent bylaw. The superseding order of conditions focused on
the temporary impact that construction of the pier would have on
the specific footprint of the pier. In contrast, the
commission's decision focused on the ongoing impact that the
pier would have on the adjacent shellfish habitat, including the
impact of boats coming to and from the pier. Contrast Boston,
9 490 Mass. at 347 n.9 (commission's decisions "do not clearly
express a concern with future impacts").
2. Certiorari review under G. L. c. 249, § 4.
Alternatively, the plaintiff argues that the commission's
decision was arbitrary and capricious, and unsupported by
substantial evidence. "A decision is not arbitrary or
capricious unless there is no ground which reasonable people
might deem proper to support it"[;] [s]ubstantial evidence is
such evidence as a reasonable mind might accept as adequate to
support a conclusion," based on the entire record, including any
countervailing evidence (quotation and citations omitted).
Cumberland Farms, Inc., 495 Mass. at 231. For the reasons
discussed above, we conclude that the plaintiff has not shown
that the commission's decision was either arbitrary or
capricious, or that it was unsupported by substantial evidence.
We discern no substantial error of law apparent on the record
created before the commission. See id.
Judgment affirmed.
By the Court (Blake, C.J., Neyman & Grant, JJ.3),
Clerk
Entered: January 22, 2026.
3 The panelists are listed in order of seniority.