Reserve, Ltd. v. Town of Longboat Key

933 F. Supp. 1040, 1996 U.S. Dist. LEXIS 9490, 1996 WL 384492
CourtDistrict Court, M.D. Florida
DecidedMay 22, 1996
Docket90-85-CIV-T-23B, 92-762-CIV-T-23B
StatusPublished
Cited by8 cases

This text of 933 F. Supp. 1040 (Reserve, Ltd. v. Town of Longboat Key) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reserve, Ltd. v. Town of Longboat Key, 933 F. Supp. 1040, 1996 U.S. Dist. LEXIS 9490, 1996 WL 384492 (M.D. Fla. 1996).

Opinion

ORDER

MERRYDAY, District Judge.

After six years of litigation, the defendants once again present motions for summary judgment (Docs. 184 and 142). The initial summary judgment motion was resolved by Judge Morton , (sitting by designation) and ultimately addressed by the Eleventh Circuit Court of Appeals. The Reserve, Ltd. v. Town of Longboat Key, 17 F.3d 1374 (11th Cir.1994), ce rt. denied, — U.S. -, 115 S.Ct. 729, 130 L.Ed.2d 633 (1995). Judge Morton’s partial summary judgment favors the Town of Longboat Key (“Longboat Key”) by dismissing Counts I through IV. 1 The Eleventh *1042 Circuit’s decision affirms the judgment as to Count I, vacates the judgment as to Counts II, III, and IV, and remands the case for further proceedings. The following partial restatement of the facts assumed by that decision provides the background for this order:

Reserve sought to construct a spa complex in Longboat Key. In 1986, Longboat Key approved the first of several site plans for the complex. Thereafter, Reserve acquired eight acres in Longboat Key upon which to build the proposed complex. Reserve obtained a building permit from Longboat Key to construct fifty-seven condominium units and a spa (“permit”). At the time, section 160.40(A) of the Longboat Key Code provided that a permit would be revoked if, after construction commenced, no “substantial work” was accomplished in any thirty day period. Reserve contends that it spent approximately $6 million in acquiring acreage, designing the complex, demolishing pre-existing buildings on the site, site work, and construction costs. Throughout the 1980’s, Reserve’s principal, Dr. Murray Klauber (“Dr. Klauber”), was involved in numerous disputes with Longboat Key over matters unrelated to' the spa project. In addition, Dr. Klauber was active in politics in Longboat Key in the 1980’s. Beginning as early as 1984, Dr. Klauber opposed the candidacy of several members of the Longboat- Key Commission. By 1988, Dr. Klauber’s relationship with Longboat Key was, at best, strained. On May 10, 1988, Longboat Key notified Reserve that “substantial work” had not been completed on the spa complex within the last thirty-four days and warned that Reserve’s permit would be revoked if “substantial work” was not accomplished by June 5,1988. Reserve contacted Longboat Key in order to determine what would constitute “substantial work.” Longboat Key informed Reserve that the. completion of five pile caps would be considered “substantial work.” Although work was begun on five pile caps, not a single pile cap was completed between May 10, 1988 and June 5, 1988. On June 6, 1988, Longboat Key revoked Reserve’s permit for failure to complete “substantial work” on the spa complex within a thirty day period. At the time the permit was revoked, workmen were constructing a pile cap.
Reserve, through Klauber and its attorneys, informally approached Longboat Key officials on several occasions in an endeav- or to have its permit restored. Those officials refused to reinstate Reserve’s permit. In addition, the Longboat Key Commission called on the letter of credit Reserve posted as a site restoration bond. Ultimately, Reserve restored the site and discontinued its efforts to build the spa complex.

The Reserve, Ltd., 17 F.3d at 1375-76 (citations and footnotes omitted).

In their supporting memoranda, the defendants now lodge the following arguments:

(a) Count I is barred by the doctrine of res judicata; (b) Counts II through VIII are not ripe and the futility exception does not apply; (c) the alleged Town actions in Counts II, III, IV, VI, VII, VIII and X were not arbitrary and capricious under the deferential standard of review established by this Court, which requires only that the Town’s actions be rationally related to the general welfare; furthermore, the Reserve does not have a protectable [sic] property interest under the new substantive due process test enunciated in McKinney v. Pate, 20 F.3d 1550 (11th Cir.1994); (d) the complaint contains no factual basis for wrongdoing by the individually named defendants; (e) the Commissioners acting in their official capacities are entitled to absolute immunity; (f) individual defendants in their official capacities are also protected by qualified immunity; (g) Count XI fails to allege sufficient facts to entitle Reserve to relief, and is barred by the rule against split causes of action; (h) taking claims in Counts VI and IX are not ripe because Reserve has not sought the just, compensation remedies available *1043 in state court; and (i) equal protection violations alleged in Counts III and VII fail for the same reasons as Reserve’s substantive due process claims.

Docs. 134 and 143.

The plaintiffs reluctantly concede that res judicata defeats Count I of the plaintiffs’ 1992 action. The Eleventh Circuit’s ruling in the 1990 action precludes any further litigation of either the “void for vagueness” issue or the plaintiffs’ challenge to the validity of Longboat Key’s permit revocation ordinance. The additional plaintiffs included in the 1992 action are bound by the earlier decision. Accordingly, the defendants’ motions are granted as to Count I.

Despite the Eleventh Circuit’s ruling in The Reserve, Ltd., the defendants’ motions are also granted as to Counts II and IV, the substantive due process claims based on Longboat Key’s revocation of Reserve’s building permit. 2 Subsequent to the appellate decision in this case, the Eleventh Circuit issued an en banc opinion in an unrelated case that informs the resolution of this inquiry. See McKinney v. Pate, 20 F.3d 1550 (11th Cir.1994) (en banc), cert. denied, - U.S. -, 115 S.Ct. 898, 130 L.Ed.2d 783 (1995). 3

- Attempting to correct our circuit’s jurisprudence regarding the Fourteenth Amendment’s Due Process Clause, McKinney holds that Section 1983 substantive due process claims arising from non-legislative deprivations of state-created property interests are no longer cognizable. 4 Contrary to the plaintiffs’ suggestion, the effect of McKinney extends beyond employment disputes. 5 See, e.g., Boatman v. Town of Oakland, 76 F.3d 341 (11th Cir.1996) (applying McKinney to a case, resulting from a. municipality’s refusal to issue a certificate of occupancy to a property owner); Morley’s Auto Body, Inc. v. Hunter, 70 F.3d 1209, 1217 n. 5 (11th Cir.1995) (noting that, under McKinney,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chakra 5 v. City of Miami Beach
254 So. 3d 1056 (District Court of Appeal of Florida, 2018)
Eisenberg v. City of Miami Beach
54 F. Supp. 3d 1312 (S.D. Florida, 2014)
City of Pompano Beach v. Yardarm Restaurant, Inc.
834 So. 2d 861 (District Court of Appeal of Florida, 2002)
Henniger v. Pinellas County
7 F. Supp. 2d 1334 (M.D. Florida, 1998)
Collins & Co., Inc. v. City of Jacksonville
38 F. Supp. 2d 1338 (M.D. Florida, 1998)
Jacobi v. City of Miami Beach
678 So. 2d 1365 (District Court of Appeal of Florida, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
933 F. Supp. 1040, 1996 U.S. Dist. LEXIS 9490, 1996 WL 384492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reserve-ltd-v-town-of-longboat-key-flmd-1996.