Repsol Renewables Development Company, LLC v. Trisura Insurance Company

CourtDistrict Court, D. New Mexico
DecidedJuly 25, 2024
Docket1:24-cv-00296
StatusUnknown

This text of Repsol Renewables Development Company, LLC v. Trisura Insurance Company (Repsol Renewables Development Company, LLC v. Trisura Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Repsol Renewables Development Company, LLC v. Trisura Insurance Company, (D.N.M. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO

REPSOL RENEWABLES DEVELOPMENT COMPANY, LLC, and JICARILLA SOLAR 1, LLC,

Plaintiffs,

v. Civ. Case No. 1:24-296 KRS/JMR

TRISURA INSURANCE COMPANY,

Defendant,

ORDER GRANTING MOTION TO STRIKE JURY DEMAND AND DENYING WITHOUT PREJUDICE MOTION TO STAY

THIS MATTER is before the Court on Defendant Trisura Insurance Company’s Motion to Strike Jury Demand and Motion to Stay This Action Pending Contractually-Required Mediation, (Doc. 6), filed April 1, 2024. Plaintiffs filed a response to the Motion on April 15, 2024 and Defendant filed a reply on April 29, 2024. (Docs. 15 and 19). Pursuant to 28 U.S.C. § 636(c), the parties consented to the undersigned to conduct dispositive proceedings in this matter and to enter a final judgment. (Docs. 16, 17, 18). Having considered the parties’ briefing, record of the case, and relevant law, the Court grants the Motion to Strike Jury Demand and denies without prejudice the Motion to Stay. This case arises from the construction of a photovoltaic solar power facility in Rio Arriba County, New Mexico. (Doc. 1-1) at 1-2. In February 2022, Plaintiffs contracted with Bridgelink Engineering (“Bridgelink”) for the design, engineering, procurement, and construction of the project in exchange for Plaintiffs’ payment to Bridgelink of $24,465,404.00. Id. As part of the contract between Plaintiffs and Bridgelink (hereinafter the “Project Contract”), Bridgelink was required to furnish a performance bond. Defendant issued the performance bond naming Bridgelink as contractor and Plaintiffs as bond owner/obligee. Id. at 2; 19-22 (hereinafter “Surety Bond”).1 Plaintiffs allege the Surety Bond obligates Defendant to guarantee performance of the Project Contract in the event of a default by Bridgelink. Id. at 7. Plaintiffs state they terminated the Performance Contract when Bridgelink defaulted, and Plaintiffs then made a demand to Defendant for completion of the Surety Bond. Id. at 2-3; 8-9.

Plaintiffs selected a new contractor (Overland Contracting, Inc.) to complete the remaining work under the Project Contract. Id. at 10. Plaintiffs had to retain additional suppliers and contractors to complete the Project, and they state their costs to complete the Project will exceed $51 million. Id. at 11-12. Plaintiffs allege that after a year of providing documentation to Defendant, on November 9, 2023 Defendant agreed to a partial settlement under which it made a payment of $11,539,213.79 to Plaintiffs without prejudice to Plaintiffs’ right to seek the remaining balance of the bond, i.e., $12,926,190.21. Id. at 12. Unable to settle the remaining balance of the bond, Plaintiffs bring the following claims against Defendant: Breach of Contract (for breach of the Surety Bond), Violation of the New Mexico Insurance Code, and Common Law Insurance Bad

Faith. Id. at 13-16. Defendant now moves to strike the jury demand made by Plaintiffs in their Complaint on the basis that the Project Contract between Plaintiffs and Bridgelink contains a jury trial waiver. Defendant also moves to stay this case pending completion of the mediation process set forth in the Project Contract.

1 The Project Contract was originally entered into by Plaintiff Jicarilla Solar and Bridgelink. In March 2022, Repsol Renewables acquired Jicarilla Solar, and the Project Contract and Surety Bond were amended to replace Repsol Renewables in place of Jicarilla Solar. See (Doc. 1-1) at 30; (Doc. 6) at 2, n.1. For purposes of this Memorandum Opinion and Order, the Court refers to Plaintiffs Jicarilla Solar and Repsol Renewables as “Plaintiffs,” except where specifically indicated. 1. Motion to Strike Jury Demand Defendant asks the Court to strike Plaintiffs’ jury demand because Plaintiffs waived their right to a jury trial in the Project Contract, the Project Contract is incorporated by reference into the Surety Bond, and Defendant “is entitled to stand upon the jury waiver incorporated into its Bond.” (Doc. 5) at 4-6. Plaintiffs respond that Defendant improperly conflates the Project

Contract and the Surety Bond and that, “[a]lthough the bond acts as a security guaranteeing Bridgelink’s completion of its scope of work under the [Project] Contract, the two contracts are distinct.” (Doc. 15) at 2. Plaintiffs contend the contracts have different parties, serve different purposes, and impose different obligations, preconditions, limitations, and performance requirements, and the instant suit is not seeking to recover for breaches of the Project Contract. Id. at 2, 7-9. Plaintiffs further argue the Surety Bond’s incorporation of the Project Contract “does not incorporate all the contractual provisions of the [Project] Contract.” Id. at 6-7. Finally, Plaintiffs assert that Defendant cannot raise Bridgelink’s jury waiver because waiver is not a defense to liability. Id. at 10-11. In reply, Defendant maintains the jury waiver was

incorporated by the Surety Bond and that this litigation falls squarely within the broad scope of the jury waiver. (Doc. 19) at 2-8. “The right of trial by jury as declared by the Seventh Amendment to the Constitution—or as provided by a federal statute—is preserved to the parties inviolate.” Fed. R. Civ. P. 38. The right to a jury trial in the federal courts is governed by federal law. Telum, Inc. v. E.F. Hutton Credit Corp., 859 F.2d 835, 837 (10th Cir. 1988) (citing Simler v. Conner, 372 U.S. 221, 221-22 (1963) (per curiam)). Parties may contract to waive their right to a jury trial, and such waivers are neither illegal nor contrary to public policy if they are knowing and voluntary. Id.; see also Hulsey v. West, 966 F.2d 579, 581 (10th Cir. 1992); McCarthy v. Wynne, 126 F.2d 620, 623 (10th Cir. 1942), cert. denied, 317 U.S. 640 (1942). To determine if a jury waiver was knowing and voluntary, courts consider: “(1) whether there was a gross disparity in bargaining power between the parties; (2) the business or professional experience of the party opposing the waiver; (3) whether the opposing party had an opportunity to negotiate contract terms; and (4) whether the clause containing the waiver was inconspicuous.” Romero v. TitleMax of New Mexico, Inc., 2020

WL 5076081, at *1 (D.N.M.) (citation omitted). Here, the Project Contract entered into by Plaintiffs and Bridgelink contains a Jury Trial Waiver clause stating: “EACH PARTY WAIVES ITS RESPECTIVE RIGHT TO ANY JURY TRIAL WITH RESPECT TO ANY LITIGATION ARISING UNDER OR IN CONNECTION WITH THIS AGREEMENT.” (Doc. 6) at 11 (all capital letters in contract). The jury waiver is prominent, and Plaintiffs do not assert any disparity in bargaining power between the parties or lack of business or professional experience. Accordingly, the Court concludes that Plaintiffs agreed to the waiver knowingly and voluntarily. Regardless of the viability of the jury waiver between Plaintiffs and Bridgelink, Plaintiffs

argue the waiver was not incorporated into the Surety Bond and cannot be asserted by Defendant. (Doc. 15) at 6-11. The Surety Bond is a three-party contract between: (1) Plaintiffs as the Owner/Obligee; (2) Bridgelink as the Contractor; and (3) Defendant as the Surety. (Doc. 1-1) at 20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Simler v. Conner
372 U.S. 221 (Supreme Court, 1963)
Brown v. Coleman Company
220 F.3d 1180 (Tenth Circuit, 2000)
Barkan v. Dunkin' Donuts, Inc.
520 F. Supp. 2d 333 (D. Rhode Island, 2007)
McCarthy v. Wynne
126 F.2d 620 (Tenth Circuit, 1942)
Macias v. New Mexico Department of Labor
300 F.R.D. 529 (D. New Mexico, 2014)
Telum, Inc. v. E.F. Hutton Credit Corp.
859 F.2d 835 (Tenth Circuit, 1988)
Hulsey v. West
966 F.2d 579 (Tenth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Repsol Renewables Development Company, LLC v. Trisura Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/repsol-renewables-development-company-llc-v-trisura-insurance-company-nmd-2024.