Repinski v. Clintonville Federal Savings & Loan Ass'n

181 N.W.2d 351, 49 Wis. 2d 53, 1970 Wisc. LEXIS 873
CourtWisconsin Supreme Court
DecidedDecember 1, 1970
Docket156
StatusPublished
Cited by12 cases

This text of 181 N.W.2d 351 (Repinski v. Clintonville Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Repinski v. Clintonville Federal Savings & Loan Ass'n, 181 N.W.2d 351, 49 Wis. 2d 53, 1970 Wisc. LEXIS 873 (Wis. 1970).

Opinion

Hallows, C. J.

When there is credible evidence which under any reasonable view fairly admits of an inference which is sufficient to support the jury’s finding, the trial court should not change the finding. Rodenkirch v. Johnson (1960), 9 Wis. 2d 245, 248, 101 N. W. 2d 83; Kinsman v. Panek (1968), 40 Wis. 2d 408, 414, 162 N. W. 2d 27. Consequently, we must review the evidence to determine whether it was error for the trial court to change the answer in the verdict.

In July, 1966, Clintonville and the Repinskis entered into an agreement for a mortgage loan for the construction of a new home in Outagamie county. The loan was for $17,300 at six and one-half percent interest and was payable in instalments over a period of twenty-five years. From this loan, $800 was used to pay the premium of the mortgage-life-insurance policy, but this insurance was not required by Clintonville for the making of the loan. The Repinskis deposited $5,086.50 with Clinton-ville to cover the balance of the cost of the new home and $5,000 of this was paid to the contractor during the early stages of construction.

In March, 1967, Clintonville inspected the new home and found it 97 percent completed. At this time Repin-skis were in dispute with the contractor over extras and Mr. Repinski instructed Clintonville not to make pay *56 ments to the contractor. Failure to make the payment resulted in the commencement of a lien-foreclosure action on July 21, 1967, by the contractor. During that month Repinskis were also having marital problems and Mr. Repinski left the home to live in Appleton. On July 14, 1967, he phoned Clintonville to inform it of his new address; Mr. McIntyre testified on behalf of Clinton-ville that during this conversation, Mr. Repinski requested the cancellation of the loan. Repinski in his testimony denied he made such a request.

It is undisputed McIntyre suggested to Repinski to cancel his mortgage-life-insurance policy and subsequently the mortgage-life-insurance policy was cancelled by Repinski and the return premium was paid to Clin-tonville. On September 25, 1967, a default judgment was entered in the foreclosure action and Clintonville’s first mortgage to the extent of $228.72 was recognized. Shortly thereafter Repinski made a settlement with the contractor. He also became reconciled with his wife. When requested to pay the contractor by Repinski, Clintonville refused to abide by its loan commitment. Repinskis then negotiated a new loan with another lender at a one fourth of a one percent higher rate of interest amounting to an increase of $846, and with additional costs of $550.

The evidence presented to the jury a disputed issue of whether Repinski cancelled the contract because of his difficulties with his wife and the contractor, or whether Clintonville took advantage of the situation to get out of its commitment because of the rising interest rates. Whether Repinski’s version of the phone call or that of Clintonville was to be believed depended upon the credibility of the witness and presented a question for the jury to decide. The inferences to draw from the other facts were likewise for the jury. The trial court drew inferences which supported the view espoused by *57 Clintonville. It believed the testimony of McIntyre that Repinski phoned him to cancel the loan, but the jury believed Repinski. The jury had a right to believe Repinski did not cancel the loan agreement; that the cancellation of the insurance was to save money to help pay for the extras; that Repinski wanted no money paid to the contractor so he would have some bargaining advantage and there was no intention to abandon the building project because of his marital difficulties. Whether this view is supported by the greater weight of the evidence is immaterial when the jury is the fact finder and the evidence is sufficient to meet the burden of proof. We think there were two reasonable views the evidence would support. When more than one reasonable view may be supported by credible evidence, the trial court must accept the view reached by the jury. Ernst v. Greenwald (1967), 35 Wis. 2d 763, 151 N. W. 2d 706. The trial court erred in finding as a matter of law that there could reasonably be only one view of the evidence and therefore the trial court committed error in changing the answer of the verdict. Millard v. North River Ins. Co. (1930), 201 Wis. 69, 228 N. W. 746; Auster v. Zaspel (1955), 270 Wis. 368, 71 N. W. 2d 417; Jost v. Dairyland Power Cooperative (1969), 45 Wis. 2d 164, 172 N. W. 2d 647.

The verdict submitted was confusing and we think the jury was misled in its finding Repinskis suffered no damages. The trial court did not reach this question in its opinion. The verdict inquires, “What sum of money will reasonably compensate the plaintiffs, David Repinski and Bonnie Repinski, his wife, as a result of such cancellation, with respect to: (a) Additional interest payable on the new loan? . . . (b) Cost in connection with obtaining new loan, consisting of recording fee, survey costs, title insurance, 1% loan charge, appraisal fee, credit report, MGIC Insurance, and title *58 examination?” This question was to be answered only if question number one was answered “No.” But a no answer to the first question would imply that Clinton-ville wrongly breached its loan commitment because Repinskis did not cancel it. However, question two refers to the “result of such cancellation” and this can only refer to the Repinskis’ cancellation. The question should have referred to Clintonville’s breach, not to Repinskis’ cancellation; or better, the two questions should have been on the same basis, i.e., did Clintonville breach its contract? Obviously, the jury was misled in answering question two because the evidence is undisputed and shows Repinskis did incur additional expense in acquiring the new loan. The answers are clearly contrary to the evidence and cannot stand.

An award of damages for breach of contract should compensate the injured party for losses necessarily flowing from the breach. Restatement, 1 Contracts, pp. 503, et seq., sec. 329; 5 Williston, Contracts (rev. ed.), p. 3762, sec. 1338; Dehnart v. Waukesha Brewing Co. (1963), 21 Wis. 2d 583, 124 N. W. 2d 664. When litigation is a natural and proximate result of the breach, recovery may be had as damages for attorney’s fees necessarily incurred in that litigation. Weinhagen v. Hayes (1922), 179 Wis. 62, 190 N. W. 1002. However, attorney’s fees incurred by the Repinskis in the lien-foreclosure action were not a result of Clintonville’s refusal to release the proceeds of the loan when requested in October. These fees became a liability when the judgment was entered and this was not due to Clin-tonville’s failure to perform. The evidence does not support Repinskis’ contention that their settlement with the contractor for $700 included the attorney’s fees and because they did not have the Clintonville proceeds, the deal fell through and they were required to pay the attorney’s fees.

*59 It is not disputed that interest rates on mortgage loans were increasing during 1967 and the increase in interest rate of the new loan amounted to $846.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apple, Inc. v. Motorola Mobility, Inc.
886 F. Supp. 2d 1061 (W.D. Wisconsin, 2012)
Kempfer v. Automated Finishing, Inc.
564 N.W.2d 692 (Wisconsin Supreme Court, 1997)
Walgreen Co. v. Sara Creek Property Co.
775 F. Supp. 1192 (E.D. Wisconsin, 1991)
Yost v. City of Council Bluffs
471 N.W.2d 836 (Supreme Court of Iowa, 1991)
Thorp Sales Corp. v. Gyuro Grading Co.
331 N.W.2d 342 (Wisconsin Supreme Court, 1983)
Metropolitan Transfer Station, Inc. v. Design Structures, Inc.
328 N.W.2d 532 (Court of Appeals of Iowa, 1982)
Bridgkort Racquet Club, Inc. v. University Bank
271 N.W.2d 165 (Court of Appeals of Wisconsin, 1978)
Toulon v. Nagle
226 N.W.2d 480 (Wisconsin Supreme Court, 1975)
Schmidt v. Mueller
193 N.W.2d 161 (Wisconsin Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
181 N.W.2d 351, 49 Wis. 2d 53, 1970 Wisc. LEXIS 873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/repinski-v-clintonville-federal-savings-loan-assn-wis-1970.