Remmert v. EDA Contractors, Inc.

32 Pa. D. & C.5th 225
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedJuly 19, 2013
DocketNo. 4226
StatusPublished

This text of 32 Pa. D. & C.5th 225 (Remmert v. EDA Contractors, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Remmert v. EDA Contractors, Inc., 32 Pa. D. & C.5th 225 (Pa. Super. Ct. 2013).

Opinion

RIZZO, J.,

The appellants, EDA Contractors, Inc. a/k/a EDA Roofing Corp. and William J. Diaz, from the court’s order and decision of February 23,2013

FACTS AND PROCEDURAL HISTORY

Appellee-plaintiffs Gerald and Kathy Remmert commenced this action on March 1,2011 against appellant-defendants EDA Contractors, Inc. a/k/a EDA Roofing Corp. (“EDA Contractors”) and William J. Diaz (“Diaz”) for injuries suffered by Gerald Remmert (“Remmert”) on the morning of March 27, 2009. when Diaz’s vehicle struck appellees’ vehicle (being driven by Remmert) at the intersection of East Somerset Street and Memphis Street in the Port Richmond section of Philadelphia.

On August 2, 2012, after a five-day trial, a jury found appellee Remmert fifty-one percent (51%) liable for the accident and the injuries he himself sustained, and appellants liable for the remaining forty-nine percent (49%), which therefore barred appellees1 from any recovery. On September 7, 2012, appellees moved for post-trial relief in the form of either a judgment notwithstanding the verdict, or a new trial, pursuant to Pennsylvania Rule of Civil Procedure 227.1. Several grounds were raised including; that the trial court erred in allowing the testimony of an accident reconstructionist, that the trial court erred in certain aspects of its charge to the jury, that the jury was improperly presented with [227]*227the issue of comparative negligence, that defense counsel made improper remarks during opening and closing arguments, and finally that damages were inadequate because of an inadequate verdict.

After reviewing said motion, the responses, the trial transcript, applicable law, and receiving oral argument, this court granted appellees’ motion for post-trial relief in the form of a new trial on February 23, 2013. On March 22,2013, appellants timely appealed said order granting a new trial, pursuant to Pa.R.A.P. 311 (a)(6).

The facts of the case are as follows:

This accident occurred at the intersection of Memphis Street and East Somerset Street in Philadelphia, Pennsylvania. Memphis Street runs perpendicular to East Somerset Street, forming a “T-shaped” intersection. When traveling on Memphis Street as it meets East Somerset Street, a driver must first observe a stop sign, and then turn either left or right onto East Somerset Street, which is a two-lane street. Traffic proceeding along East Somerset Street is not controlled by a stop sign, and cannot turn onto Memphis Street as it is a one-way street.

At trial, Remmert gave undisputed testimony that at the time of the incident he was traveling along East Somerset Street at a speed of approximately 15-20 miles per hour, approached Memphis Street, and observed a large parked truck “sticking out” and obstructing his view of oncoming traffic from Memphis Street. Because Remmert had the right-of-way, he did not stop or slow down his speed as he proceeded straight along East Somerset Street. At trial, Diaz, driver for EDA Contractors, testified that he drove along Memphis Street and as he approached the [228]*228intersection of Memphis Street and East Somerset Street, stopped at the stop sign, observed the same truck parked at the comer obstmcting his view of the oncoming traffic from East Somerset Street, and then “inched” out into the intersection.

It is undisputed that the vehicle driven by Diaz stmck Remmert’s vehicle after Diaz made a left turn onto East Somerset Street from Memphis Street. The front left bumper of the Chevrolet Silverado driven by Diaz contacted the passenger-side headlight area of Remmert’s Nissan Altima. Remmert testified that the impact cracked his engine in half, pushed the vehicle’s hood up to the windshield, and totaled his vehicle. The impact also jolted Remmert forward and against the side of the door. When questioned about the impact, Diaz stated that his truck “went...right over the top of [appellee’s car].” Photographs introduced into evidence by Diaz showed minor damage to the truck’s front bumper. Diaz also introduced the testimony of an accident reconstmction expert who corroborated the testimony of both parties.

The jury returned a verdict finding Remmert fifty-one percent (51%) causally negligent and the appellants forty-nine percent (49%) causally negligent, barring both appellees from all recovery. Within thirty days of the recording of the verdict, appellees filed a timely motion for post-trial relief requesting one of the following forms of relief: judgment notwithstanding the verdict, a new trial, or a new trial on the issue of damages only. In response, a briefing schedule was put forward for the filing of post-trial briefing by the parties, setting a date for oral argument of October 9, 2012.

[229]*229Both trial counsel and the court believed review of the trial transcript was essential to resolving the outstanding post-trial motion. Considerable delay in the provision of the trial transcript following oral argument on said motion resulted in several extensions afforded counsel for post-trial briefing. Each extension was requested by counsel and reviewed by this court as communication with counsel was on regular basis during this time. The unforeseen delay in the production of the trial transcript as well resulted in a delay of review and ultimate analysis by the court for decision after oral argument. Counsel knew of these delays and both expressed a need to review the trial transcript to support their own post-trial supplemental memoranda after oral argument. Both took said opportunity afforded them by the court to supplement their original post-trial filings.

On February 23, 2013, the court granted appellees’ request for relief in the form of a new trial. Due to consistent communications between the court and trial counsel regarding a delay in receipt of the trial transcript, it was anticipated by the court that counsel would await the court’s ruling. Defense counsel moved to enter judgment pursuant to Rule Rule 227.4(1 )(b), resulting in said Judgment pre-dating this court’s grant of relief on appelles’ post-trial motion for a new trial. Though entry of judgment was timely, it was done without (by courtesy) any prior notice to the court. The subsequent order of February 23,2013 entered by the court was in turn subject to challenge by the appellants and now forms the basis of the instant appeal.

Notwithstanding the unusual procedural chronology in the case, it is this court’s request that full appellate [230]*230review be given the bases upon which the lower court granted the aforesaid relief — such significant relief only being granted upon a thorough review of the transcript, applicable statutory law and case law.

ISSUES ON APPEAL2

In their post-trial motion, appellees raised several grounds for review: that the trial court erred in allowing the testimony of an accident reconstructionist and admission into evidence of photographs of the vehicle driven by Diaz, that the trial court erred in certain aspects of its charge to the jury, that the jury was improperly presented with the issue of comparative negligence, that defense counsel made improper remarks during opening and closing arguments, that the trial court erred in failing to overrule late objections by defense counsel to the trial testimony of Dr. James Brady, and that damages were inadequate because of an inadequate verdict. In their supplemental filing to their post-trial motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Murray
597 A.2d 111 (Superior Court of Pennsylvania, 1991)
Keller v. Re/Max Centre Realty
719 A.2d 369 (Superior Court of Pennsylvania, 1998)
Nudelman v. Gilbride
647 A.2d 233 (Superior Court of Pennsylvania, 1994)
Henery v. Shadle
661 A.2d 439 (Superior Court of Pennsylvania, 1995)
Thompson v. City of Philadelphia
493 A.2d 669 (Supreme Court of Pennsylvania, 1985)
Davis v. Mullen
773 A.2d 764 (Supreme Court of Pennsylvania, 2001)
Commonwealth v. Petroll
738 A.2d 993 (Supreme Court of Pennsylvania, 1999)
Peair v. Home Ass'n of Enola Legion No. 751
430 A.2d 665 (Superior Court of Pennsylvania, 1981)
Fish v. Gosnell
463 A.2d 1042 (Supreme Court of Pennsylvania, 1983)
Commonwealth v. Petroll
696 A.2d 817 (Superior Court of Pennsylvania, 1997)
McManamon v. Washko
906 A.2d 1259 (Superior Court of Pennsylvania, 2006)
Hallowell v. Wuestkamp
24 Pa. D. & C.4th 99 (Bucks County Court of Common Pleas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
32 Pa. D. & C.5th 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/remmert-v-eda-contractors-inc-pactcomplphilad-2013.