Rembowski v. Rudolph Libbe, Inc.

2020 Ohio 2864, 154 N.E.3d 564
CourtOhio Court of Appeals
DecidedMay 8, 2020
DocketL-19-1091
StatusPublished
Cited by2 cases

This text of 2020 Ohio 2864 (Rembowski v. Rudolph Libbe, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rembowski v. Rudolph Libbe, Inc., 2020 Ohio 2864, 154 N.E.3d 564 (Ohio Ct. App. 2020).

Opinion

[Cite as Rembowski v. Rudolph Libbe, Inc., 2020-Ohio-2864.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT LUCAS COUNTY

Nicholas Rembowski Court of Appeals No. L-19-1091

Appellant Trial Court No. CI0201703251

v.

Rudolph/Libbe Inc., et al. DECISION AND JUDGMENT

Appellees Decided: May 8, 2020

*****

Kevin J. Boissoneault and Jonathan M. Ashton, for appellant.

Christopher W. St. Marie, Aaron S. Evenchik and Douglas J. Suter, for appellee Rudolph/Libbe Inc.

Justin D. Harris and Adam Borgman, for appellee Dunbar Mechanical, Inc.

SINGER, J. {¶ 1} Appellant, Nicholas Rembowski, appeals the April 10, 2019 judgment of the

Lucas County Court of Common Pleas which granted summary judgment to appellees

Dunbar Mechanical, Inc. and Rudolph/Libbe Inc. (“RLI”). Because appellees did not

owe a duty of care to appellant, we affirm the trial court’s judgment. Background

{¶ 2} On or about July 14, 2016, appellant began working at the Fiske/Lubriplate

facility in Toledo, Ohio. This facility makes food grade lubricants, greases, and oils. The

facility decided to upgrade its facilities and hired Dunbar as its general contractor to

oversee the project. The project included the creation of a mezzanine level of the facility

by pouring concrete, creating two new staircases, and installing six large kettles into the

new mezzanine level. To install the kettles, large holes and curbs were created in the

mezzanine as well. Large holes also had to be cut in the roof so that the kettles could be

flown in from a different site.

{¶ 3} Dunbar hired RLI as a subcontractor to pour the concrete for the mezzanine

level. RLI completed the mezzanine level and installed plywood coverings over the holes

for the kettles in early July 2016. Most of their employees then left the jobsite. Two RLI

workers remained on site to wrap up the job site. In order to reach the new mezzanine

level, RLI constructed two staircases that were about 100 feet away from one another and

separated by a large firewall.

{¶ 4} On July 18, 2016, in anticipation of the kettles arriving, Dunbar ordered RLI

to remove the hole coverings and to secure the mezzanine level. RLI completed the

removal of the hole coverings and secured the mezzanine level by placing red danger tape

on the staircases. This was the last day RLI employees were on the jobsite.

{¶ 5} Dunbar hired appellant’s employer GEM, Inc. to cut the large holes in the

roof and to install the curbs for the kettles. Appellant is an experienced ironworker with

2. years of experience. Appellant began working on the site on July 14, 2016, and worked

at the site for the next five days. Appellant’s work entailed working on the mezzanine

level and working above and below the roof to cut the required holes. Appellant was on

the job site when the coverings for the holes were removed. He was aware of the

uncovered holes prior to his injury.

{¶ 6} Dunbar instructed RLI to secure the mezzanine to ensure no one would be

injured by the uncovered holes. Dunbar’s project manager Dan Huguley stated in a

deposition he did not inform or supervise how RLI secured the mezzanine area. RLI

removed the hole covers and placed red danger tape on the staircases to ensure people

would not use the staircase to get to the mezzanine level. RLI’s employees then turned

the jobsite over to Dunbar and left the site. It was later discovered that the kettles would

be delivered a week later than expected, but Dunbar did not ask RLI to recover the holes

on the mezzanine level.

{¶ 7} On July 19, 2016, GEM completed its portion of the project and prepared to

leave the facility for another jobsite. Appellant’s foreman ordered another GEM

employee to retrieve tools from the mezzanine level. Appellant volunteered to go up to

the level to retrieve the tools instead of the other GEM employee. Appellant walked up

one of the staircases, ducked under the red danger tape, and did not utilize any fall

protection while near the kettle holes. While appellant was winding an extension cord, he

lost his balance and fell through one of the holes. Appellant suffered several broken

bones and other injuries from his fall.

3. {¶ 8} The parties argue about who placed the red tape and for what purpose.

Appellant states a GEM employee placed the red tape on the staircases to warn others

that the GEM workers were working above the mezzanine level for several days. He

testified that during his days on the site, he would go under the red tape or reattach the

red tape after going through it on one of the staircases. Appellees argue that RLI placed

the red tape at the direction of Dunbar to serve as “administrative control” to stop

workers from entering the mezzanine level while the holes were uncovered.

{¶ 9} There are also disputes as to when the red tape was placed on the staircase.

Appellant testified that the tape was placed in mid-July when GEM workers first began

cutting holes in the roof. Appellees state that the red tape was placed by RLI when they

removed the hole coverings to stop people from entering the mezzanine level.

{¶ 10} Several pictures demonstrated the red tape that was placed on the two

staircases. On the staircase that appellant accessed for his work, there was red tape, but it

was not securely attached and looked as though it was taken off and reattached several

time. This aligns with appellant’s testimony that GEM workers went through the red tape

as they completed their work on the project.

{¶ 11} The other staircase is almost encompassed in red tape and has a danger sign

on the red tape. It should be noted that additional red tape and the sign were added after

appellant fell. The red tape on this staircase does not appear as ragged or used as the

other staircase.

4. Arguments on Summary Judgment

{¶ 12} In its motion for summary judgment, Dunbar argues that it did not actively

participate in appellant’s work or employees, that Dunbar did not direct appellant on the

day of the fall, and that GEM’s employee ordered appellant to enter the mezzanine area

to quickly retrieve the tools from a dangerous area. In the alternative, Dunbar argues that

appellant assumed the risk when he entered a dangerous floor and through red danger

tape without taking any safety precautions.

{¶ 13} RLI argues that because RLI and GEM were both subcontractors with no

contractual relationship, RLI was only required to exercise ordinary care regarding GEM

and its workers because it did not actively participate in appellant’s work. RLI did not

owe a duty to appellant because RLI did not retain control over the workplace and left the

jobsite completely before appellant fell. In the alternative, RLI argues that even if it did

owe a duty to appellant, he was participating in an inherently dangerous activity and was

injured by an open and obvious hazard.

{¶ 14} In response, appellant argues that Dunbar and RLI owed him a duty of care

because they controlled a critical variable in appellant’s injury, the hole coverings.

Appellant also argues that Dunbar participated in and retained control of the jobsite

because it approved the use of the red tape before the RLI employees left.

{¶ 15} Appellant points to the red tape as a material dispute between the parties,

which he argues bars the granting of summary judgment. Appellant testified that one of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitzel v. Bryson/Tucker Elec., L.L.C.
2025 Ohio 2577 (Ohio Court of Appeals, 2025)
Kruthaup v. Schoen Builders, L.L.C.
2023 Ohio 2090 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 2864, 154 N.E.3d 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rembowski-v-rudolph-libbe-inc-ohioctapp-2020.