Reliance Insurance v. Trane Co.

184 S.E.2d 817, 212 Va. 394, 1971 Va. LEXIS 354
CourtSupreme Court of Virginia
DecidedNovember 29, 1971
DocketRecord 7560
StatusPublished
Cited by4 cases

This text of 184 S.E.2d 817 (Reliance Insurance v. Trane Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance v. Trane Co., 184 S.E.2d 817, 212 Va. 394, 1971 Va. LEXIS 354 (Va. 1971).

Opinion

Per Curiam.

Reliance Insurance Company (Reliance) is here on a writ of error granted it to a judgment for $28,645.17 in favor of the plaintiff, The Trane Company, on a labor and materials bond given by M. L. Whit-low, Inc., (Whitlow) as principal and Reliance as surety.

The record shows that Whitlow entered into a contract with the School Board of the City of Alexandria for the construction of additions and alterations to one of its school buildings. Pursuant to the contract, and as required by Code § 11-23, as amended,. 1964 Repl. Vol., Whitlow obtained a labor and materials bond from Reliance, Subsequently, Whitlow entered into a contract with Bob Vranich, Inc., (Vranich) to perform the plumbing and heating work for the project. Plaintiff, pursuant to a contract with Vranich, supplied it with materials for th'e job and Vranich defaulted in the payment of the account.

*395 The bond on which plaintiff based its claim for recovery defines a claimant as “one having a direct contract with the principal or with a subcontractor of the principal * * *." (Emphasis added.)

Reliance concedes that plaintiff is covered under the provisions of the bond if it alone is considered. But it argues that the surety on a general contractor’s labor and materials payment bond required by the statute is vulnerable to a direct right of action by a materialman only if it is shown that the general contractor did not obtain a payment bond from the subcontractor, and since there was no evidence that Whitlow failed to obtain a bond from Vranich, the plaintiff did not prove its case.

The pertinent parts of Code § 11-23 provide: (1) for a payment bond from a prime contractor conditioned upon the payment to all persons having direct contractual relationship with the prime contractor; (2) for a payment bond from a subcontractor conditioned upon the payment to all persons having direct contractual relationship with the subcontractor; and (3) in the event the prime contractor fails to obtain a bond from the subcontractor, anyone having a direct relationship with the subcontractor may sue upon the prime contractor’s bond. -

We find nothing in the language of the statute which prohibits a bond executed by the prime contractor and his surety from providing broader coverage than that required by the provisions of the statute. Nor is there any provision in the statute requiring proof that a subcontractor’s bond was not given before a materialman can recover orí the primé contractor’s bond,

Hughes & Co. v. Robinson Corp., 211 Va. 4, 175 S.E.2d 413 (1970), relied upon by Reliance, has no application to the present case.

The provisions of the bond afforded coverage to the plaintiff, and Reliance is bound by its tenor. Hence the judgment is

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

APAC-Atlantic, Inc. v. General Insurance Co.
643 S.E.2d 483 (Supreme Court of Virginia, 2007)
Stromberg Sheet Metal Works, Inc. v. United States Fidelity & Guaranty Co.
71 Va. Cir. 122 (Fairfax County Circuit Court, 2006)
Hanson Pipe & Products, Inc. v. Falcon Construction Corp.
55 Va. Cir. 347 (Norfolk County Circuit Court, 2001)
Clark v. Bodycombe
221 S.E.2d 506 (Supreme Court of North Carolina, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
184 S.E.2d 817, 212 Va. 394, 1971 Va. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-insurance-v-trane-co-va-1971.