Reliance Coal & Coke Co. v. H. P. Brydon & Bro.

286 F. 827, 1 Ohio Law. Abs. 434, 1923 U.S. App. LEXIS 2764
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 9, 1923
DocketNo. 3721
StatusPublished
Cited by2 cases

This text of 286 F. 827 (Reliance Coal & Coke Co. v. H. P. Brydon & Bro.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Coal & Coke Co. v. H. P. Brydon & Bro., 286 F. 827, 1 Ohio Law. Abs. 434, 1923 U.S. App. LEXIS 2764 (6th Cir. 1923).

Opinion

KNAPPEN, Circuit Judge.

By instrument dated July 3, 1920, plaintiff in error (hereinafter called defendant) contracted with the Logan & Kanawha Coal Company (hereinafter called the Kanawha Company) to purchase approximately one car per day of certain mine run coal for a period of one year from July 1, 1920, at a price therein provided for, delivery to be made in equal monthly quantities. The contract contained this final clause:

“This coal is for the Baltimore Manufacturing Company, Baltimore, Md., and subject to inspection of the first few cars as to quality and preparation. 'The Reliance Coal Company has the privilege, in case of embargoes, or if for any other reason the Baltimore Manufacturing Compamy cannot take all this coal in question, to ship part of same on contract to any of the other Fleisehmann plants.”

The Baltimore Manufacturing Company was a Fleischmann plant. Shipments under this contract were regularly made to the Baltimore Company until about October 16, 1920, from which time and until October 29 (by reason of the shutting down of the Baltimore plant) deliveries were made at defendant’s direction to the Fleischmann plant at Langdon, D. C., and after that date until about December 11, 1920, by like direction, to the Fleischmann plant at Peekskill, N. Y., after which date further deliveries were, by defendant’s direction, temporarily suspended until further notice should be given by it. Such notice was never given. On April 12, 1921, defendant in error (hereinafter called plaintiff) began this suit to recover damages for the alleged refusal of defendant to accept further shipments, asserting itself to be the undisclosed principal of the Kanawha Company in the making of the contract; also alleging formal assignment to it of the contract by the Kanawha Company on March 9, 1921. Upon the trial defendant contended that the written contract should be interpreted as meaning that, if the Baltimore Company was unable to use the coal, the Kanawha Company was not bound to furnish it, except to some other Fleischmann plant, at the option of defendant, and that defendant was bound to take and pay for (in addition to such coal as the Baltimore Company took) only such as defendant should order shipped to some other Fleischmann plant; that defendant had not refused to perform the contract, but had only declined to accept further shipments until the Baltimore plant should reopen — this suit being begun before such reopening. The trial court rejected defendant’s construction of the contract, and left it to the jury to find, as upon facts necessary to recovery, whether the Kanawha Company was plaintiff’s agent in the making of the contract, whether plaintiff duly performed it so far as permitted by defendant, whether after the temporary suspension of shipments, on December 11, 1920, plaintiff offered to resume shipments, and whether defendant thereupon unequivocally gave plaintiff to understand that it was no longer to be bound by the contract. There were verdict and judgment for plaintiff.

In our opinion the court did not err in rejecting defendant’s construction of the contract, and in holding, as matter of law (and as [829]*829not a question for the jury), that the fact that the Baltimore Company could not use the coal, and that defendant did not or could not ship to the other Fleischmann plants, would not relieve defendant from its contract or excuse its failure to accept and pay for tire coal. The contract was wholly in writing. Its terms were plain and unambiguous. The circumstances of its execution and the negotiations prior thereto were not in substantial dispute. This written contract, including its final clause, which we have quoted, unequivocally imports an absolute liability on defendant to accept all the coal contracted for. Goddard v. Foster, 17 Wall. (84 U. S.) 123, 21 L. Ed. 589. The only option given defendant was to change the destination of shipments. Assuming, for the purposes of this opinion, that defendant would have had such an option without express provision therefor, its inclusion is not significant. Defendant may well have wished to preserve good relations with the seller, and to avoid disputes and misunderstandings possible to arise when market prices greatly advance.

True, on the day on which defendant returned, with its signature, to the Kanawha Company, the formal contract, which had previously been executed by the latter, defendant mailed to the Kanawha Company an order for a shipment of coal, which was received by the latter company on the same day it received the signed contract from defendant; this order containing among the printed conditions on its back the following:

“The Reliance Coal & Coke Company shall not be held liable for failure to accept coal under this agreement, if consignee specified orders shipments held or canceled because of strikes, accident, or other causes; but in that event, however, the Reliance Coal & Coke Company shall have the privilege of furnishing other billing for the uncompleted portion of the order, if tBey so elect.”

But this clause was not called to the attention of the Kanawha Company, and the testimony that it was neither assented to nor read by the Kanawha Company, and was never sent to plaintiff, is undisputed. Plainly this clause was no part of the original contract. It did not purport to be such. The most which can be said in defendant’s favor is that it is at variance with plaintiff’s interpretation of the written agreement; but the written contract itself must govern. It contains its own exclusive provision for suspension of shipment, which we quote in the margin.1

Moreover, the final clause of the contract which we have quoted is a typewritten addition thereto, the words, “This coal -is for tire Baltimore Manufacturing Company, Baltimore, Md., and subject to inspection of the first few cars as to quality and preparation,” being added by the Kanawha Company, and the words immediately following (also typewritten), and which we have italicized, being added by [830]*830defendant. Clearly, the addition printed upon the back of a general form order for shipment cannot prevail against the unequivocal terms of the original contract. Sturm v. Boker, 150 U. S. 312, 326 et seq., 14 Sup. Ct. 99, 37 L. Ed. 1093; Sturtevant Co. v. Fireproof Co., 216 N. Y. 199, 204, 110 N. E. 440, L. R. A. 1916D, 1069.

The verdict of the jury conclusively presumes a finding by it that' the Kanawha Company acted as agent for plaintiff in.making the contract in suit and had authority to do so. If there was substantial evidence tending to support the finding, it must stand. We are unable to agree with defendant that there was no such evidence,, On March 11, 1920, defendant asked plaintiff for quotations on fuel requirements for the Baltimore Company. There was testimony that plaintiff mailed defendant’s letter to the Kanawha Company, requesting it to get in touch with defendant in reference thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fairmount Glass Works v. Cub Fork Coal Co.
287 U.S. 474 (Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
286 F. 827, 1 Ohio Law. Abs. 434, 1923 U.S. App. LEXIS 2764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-coal-coke-co-v-h-p-brydon-bro-ca6-1923.