Reiter v. Kuhlman

228 N.W.2d 830, 59 Mich. App. 54, 1975 Mich. App. LEXIS 1316
CourtMichigan Court of Appeals
DecidedFebruary 24, 1975
DocketDocket 18345
StatusPublished
Cited by3 cases

This text of 228 N.W.2d 830 (Reiter v. Kuhlman) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reiter v. Kuhlman, 228 N.W.2d 830, 59 Mich. App. 54, 1975 Mich. App. LEXIS 1316 (Mich. Ct. App. 1975).

Opinion

R. M. Maher, J.

Plaintiff-subcontractor brought suit in the circuit court, alleging fraudulent appropriation of contract funds under MCLA 570.151 et seq.; MSA 26.331 et seq., the building contract fund act. 1 Summary judgment was granted plaintiff and defendant appeals.

*56 The complaint states that on or about July 13, 1971, plaintiff undertook, at the request of another subcontractor, Milton J. Kuhlman, to install a paved parking lot. Plaintiff completed work on July 29, 1971. Milton Kuhlman died shortly thereafter and his son, Richard Kuhlman, defendant herein, fraudulently collected $11,300 on the construction contract and fraudulently withheld these funds contrary to the building contract fund act.

Defendant, in his answer, admitted that Milton J. Kuhlman died shortly after the work was completed but moved to strike the allegations of fraud. By way of affirmative defenses, defendant stated that he was, at all times, acting for and on behalf of the estate of his father. Defendant claimed that, as administrator, he placed all monies collected on behalf of the estate into an account in his name and that the provisions of MCLA 570.151 et seq.; MSA 26.331 et seq., did not apply.

Plaintiff moved for summary judgment. He stated that Milton J. Kuhlman, deceased, had collected $5,000 on the construction contract on July 14, 1971, one day after plaintiff had commenced work and then died 5 days later. Plaintiff further asserted that he completed the contract on July 29, 1971 and that Richard Kuhlman, the administrator of his father’s estate, requested and received payment of $11,300, in his individual capacity, on August 2, 1971. Plaintiff therefore contended that both the deceased and defendant were trustees for his benefit under MCLA 570.151 *57 et seq.; MSA 26.331 et seq., in the amount of $5,687 plus interest but had fraudulently withheld payment.

Summary judgment was granted plaintiff after defendant failed to either file any opposition to the motion or appear for argument thereon. Counsel for defendant, however, explained his absence to the satisfaction of the trial court and the judge treated defendant’s motion to set aside summary judgment as a motion for rehearing on the summary judgment. Then, on the strength of the Supreme Court’s holding in B F Farnell Co v Monahan, 377 Mich 552; 141 NW2d 58 (1966), the trial court affirmed its prior ruling, stating that the monies collected by Richard Kuhlman on the construction contract had never become a part of Milton J. Kuhlman’s estate but were held in trust for the benefit of the subcontractors.

On appeal, defendant does not contest that his father collected the sum of $5,000 on the contract in question prior to his death and completion of the contract, and that he, as administrator of his father’s estate, saw to it that the contract was completed and collected the sum of $11,300 in payment on that contract.

The building contract fund act was enacted to provide a more effective remedy for private project subcontractors against their principal contractors. See General Insurance Co of America v Lamar Corp, 482 F2d 856 (CA 6, 1973). Although the act is penal in nature, the Supreme Court in B F Farnell Co v Monahan, supra, at 555, held that the building contract fund act created a civil remedy:

"When a statute provides a beneficial right but no civil remedy for its securance, the common law on its own hook provides a remedy, thus fulfilling law’s pledge of no wrong without a remedy.” (Citations omitted.)

*58 In Farnell, defendant-contractor received payment for work performed under a private construction contract and filed a voluntary petition in bankruptcy while still in possession of those funds but before payment of all subcontractors. Defendant delivered the contractual payment to the trustee in bankruptcy and was subsequently discharged. Plaintiff-materialman brought suit under the building contract fund act, alleging that the receipt of those funds and their delivery to the trustee in bankruptcy constituted a fraudulent appropriation. Defendant in Farnell obtained summary judgment of no cause from the trial court. The Supreme Court reversed, stating that if plaintiff could prove the allegations contained in its complaint, then the funds that were turned over to the trustee in bankruptcy were never defendant’s "property” within the meaning of § 70 of the bankruptcy act:

"It is clear that a contractor or subcontractor, by delivering to his trustee in bankruptcy what he himself holds as trustee under the [building contract fund act], cannot thereby defeat the common-law remedy this Court has provided in favor of those who under the act are aggrieved by his statutory violation. Whether defendant’s act of turning the funds over to his trustee did or did not place such funds beyond the reach of plaintiff is beside the point. Plaintiff had the remedy it seeks to pursue, as against the defendant, when the latter retained or used the funds as charged in its complaint. That remedy was not destroyed, either by defendant’s voluntary petition in bankruptcy or by his voluntary payment to the trustee in bankruptcy of that which was not his.” B F Farnell Co v Monahan, supra, at 557-558.

We find Farnell to be closely analogous to the case at bar. Here, the deceased, Milton J. Kuhl *59 man, collected the sum of $5,000 as primary subcontractor on an unfinished building contract in which plaintiff was a secondary subcontractor under him. The deceased held this amount in trust for the benefit of plaintiff and other secondary subcontractors, laborers or materialmen under MCLA 570.151 et seq.; MSA 26.331 et seq. When defendant, whether as administrator of Milton J. Kuhlman’s estate or in his individual capacity, collected the sum of $11,300 in payment for completing the contract, he thereby received this amount as a "subcontractor” within the meaning of the building contract fund act. Funds for building construction purposes, received by a subcontractor as a trustee under MCLA 570.151 et seq.; MSA 26.331 et seq., do not become part of his estate when he dies nor do they become a part of his estate because such funds are paid to the administrator of his estate.

Section 1 of the building contract fund act establishes the trust fund. Section 2 defines the statutory fraud and provides a penalty. Section 3 states what shall constitute evidence of intent to defraud. Plaintiff, in his complaint, alleges fraudulent appropriation of building contract funds by defendant in this case. Plaintiff has the remedy he seeks to pursue.

Nevertheless, did the trial court err in concluding that summary judgment was proper because of the absence of a genuine issue as to any material fact? GCR 1963, 117.2(3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
228 N.W.2d 830, 59 Mich. App. 54, 1975 Mich. App. LEXIS 1316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reiter-v-kuhlman-michctapp-1975.