Reinforced Concrete Pipe Co. v. Boyes

147 N.W. 577, 180 Mich. 609, 1914 Mich. LEXIS 939
CourtMichigan Supreme Court
DecidedJune 1, 1914
DocketDocket No. 144
StatusPublished
Cited by15 cases

This text of 147 N.W. 577 (Reinforced Concrete Pipe Co. v. Boyes) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reinforced Concrete Pipe Co. v. Boyes, 147 N.W. 577, 180 Mich. 609, 1914 Mich. LEXIS 939 (Mich. 1914).

Opinion

Kuhn, J.

The plaintiff, a corporation with its business offices located at Jackson, Mich., is engaged in the manufacture, under a patented process, of sewer pipe known as reinforced concrete pipe. The defendant Boyes, who resides in Grand Rapids, Mich., is engaged principally as a contractor in street and sewer work in that city. In the summer of 1909 he was successful in obtaining the contracts for the construction of sewers on two of its streets. After bidding on these jobs, and before receiving the contracts, knowing of the business of the plaintiff, he called at its offices in Jackson to get prices on the amount of pipe needed. After some negotiation, and after the contracts were awarded defendant Boyes, the following contract was entered into between the parties:

“This article of agreement, made and entered into this 4th day of September, A. D. 1909, by and between the Reinforced Concrete Pipe Company, of Jackson, Michigan, party of the second part, witnesseth: That the said party of the first part, for the consideration hereinafter named, does hereby promise, covenant, and agree to manufacture for the said party of the second part, approximately:
“18x20 to be manufactured or not as directed by D. W. Boyes.
“782 lin. ft. 18 in. inside diam. reinforced concrete pipe, at 65c. per lin. ft.
[611]*611“296 lin. ft. 21 in. inside diam. reinforced concrete pipe, at 75c. per lin. ft.
• “852 lin. ft. 24 in. inside diam. reinforced concrete pipe, at 95c. per lin. ft.
“564 lin. ft. 27 in. inside diam. reinforced concrete pipe, at $1.10 per lin. ft..
“266 lin. ft. 30 in. inside diam. reinforced concrete pipe, at $1.35 per lin. ft.
“332 lin. ft. 33 in. inside diam. reinforced concrete pipe, at $1.50 per lin. ft.
“The said pipe is to be manufactured for said second party at the city of Grand Rapids, Michigan, along the line of sewer construction of said city, where free water may be obtained, at such places as are convenient and practicable for the manufacture thereof, and where permission may be had from the city of Grand Rapids' for the manufacture of said pipe; said places of manufacture being the place of acceptance and delivery.
“Said party of the first part further agrees to manufacture the pipe in a good workmanlike manner, using a mixture of one part Portland cement and five parts sandy gravel, and reinforce the same, using the American Steel & Wire Company’s wire reinforcement in the body of the pipe,' with the interlocking joint, as per the specifications of the reinforced concrete pipe, copy of. which is hereto attached.
“It is understood and agreed that in the manufacture of said pipe the said party of the first part shall provide such openings for house and catch basin connections as are shown by the plans of the city engineer, or the engineer in charge of said sewer construction, without extra charge, the number and sizes of such openings to be furnished by the party of the second part at the commencement of the manufacture of said pipe.
“It is further agreed and understood that the manufacture of the pipe shall be under the inspection of the city engineer or the engineer in charge of the work.
“The said party of the first part further agrees to furnish a suitable derrick and saddle for the handling and lowering of said pipe into the trench, without extra charge to the party of the second part, excepting, however, the' freight to and from Jackson to [612]*612Grand Rapids, Michigan, shall be paid by the party of the second part.
“The said D. W. Boyes, party of the second part, does hereby promise and agree to and with the said party of the first part that he will accept of and receive the said pipe, when so manufactured, at the said places above mentioned, and pay to the party of the first part the prices per lineal foot as stipulated above.
“The said party of the second part further agrees to settle and pay to the said party of the first part, on the 10th day of each and every month during the time the said pipe is being so manufactured, for all pipe manufactured by said party of the first part during the previous month, that is to say, on the 10th day of each and every month after the commencement of the manufacture of the pipe, the said party of the second part shall pay to the said party of the first part for all pipe manufactured by the said party of the first part during the preceding month, and at the completion of the manufacture of said pipe the party of the second part agrees to settle in full and pay the balance due for all pipe manufactured by said party of the first part for this contract. Pipe to be paid for as estimated by the city engineer.
“In witness whereof, the said parties have set their hands and seals the day and date first above written.
“This contract is executed in duplicate.
“The Reinforced Concrete Pipe Company,
“By E. F. Lowery, Prest.”
“D. W. Boyes.”

Attached to the contract was a copy of the standard specifications for the manufacture and composition of reinforced concrete pipe. Shortly after the execution of the contract plaintiff sent on to Grand Rapids the necessary moulds, tools, and machinery for manufacturing the pipe, which was begun on September 23d, under direction of a Mr. Curran, who was the foreman in charge of the gang of workmen on the job. After the work was completed, and when plaintiff insisted on payment according to the terms of the contract, the defendants claimed certain set-offs, amount[613]*613ing to about $200, composed of various items — for constructing some brick sewer, for bailing, for extra cement around pipes under railroad tracks, and for city inspection charges — all of which were outside the terms of the contract. This claim resulted in the present controversy. On the trial of the case the defendants admitted the full amount claimed by the plaintiff in its bill of particulars, and claimed the benefit of Circuit Court Rule 24c, in respect to the opening and closing in the taking of the testimony and the argument on the trial of the cause. This right of a set-off was based by the defendants on two propositions, viz.:

(1) That Mr. Curran was held out to defendant Boyes as an agent having authority to charge the plaintiff for the minor changes which were made.
(2) That the pipe to be manufactured and supplied by the plaintiff under the contract was not furnished to the defendant Boyes within a reasonable time, as a result of which he suffered losses.

At the close of defendants’ proofs, the trial judge directed a verdict for the plaintiff, and whether or not the two propositions above set forth, under the proofs in this case, raised questions of fact which should have been submitted to the jury is the question to be considered in reviewing the case here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P Antonio Lasala v. Blue Water Beagle Club
Michigan Court of Appeals, 2024
Vernisha Key v. Stonemor Michigan LLC
Michigan Court of Appeals, 2021
Daimler Chrysler Corp. v. Graves Sheet Metal
827 N.E.2d 607 (Indiana Court of Appeals, 2005)
S C Gray, Inc. v. Ford Motor Co.
286 N.W.2d 34 (Michigan Court of Appeals, 1979)
Cleary v. Henderson Bros.
185 N.W.2d 919 (Michigan Court of Appeals, 1971)
Levine v. Johnson
159 N.W.2d 165 (Michigan Court of Appeals, 1968)
Thornton Construction Co. Inc. v. MacKinac Aggregates Corp.
157 N.W.2d 456 (Michigan Court of Appeals, 1968)
Doggett v. King ex rel. Fidelity Phoenix Fire Ins.
34 A.2d 608 (District of Columbia Court of Appeals, 1943)
Wortman v. R. L. Coolsaet Construction Co.
9 N.W.2d 50 (Michigan Supreme Court, 1943)
Pierson v. Davidson
233 N.W. 329 (Michigan Supreme Court, 1930)
Brow v. Gibraltar Land Co.
229 N.W. 604 (Michigan Supreme Court, 1930)
Chamberlain v. the Amalgamated Sugar Co.
247 P. 12 (Idaho Supreme Court, 1926)
Eberlein v. Stockyards Mortgage & Trust Co.
204 N.W. 961 (Supreme Court of Minnesota, 1925)
Hulse v. Michigan Sugar Co.
152 N.W. 1048 (Michigan Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.W. 577, 180 Mich. 609, 1914 Mich. LEXIS 939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reinforced-concrete-pipe-co-v-boyes-mich-1914.