Reilly v. Mayor

22 Jones & S. 463, 7 N.Y. St. Rep. 61
CourtThe Superior Court of New York City
DecidedMay 8, 1887
StatusPublished

This text of 22 Jones & S. 463 (Reilly v. Mayor) is published on Counsel Stack Legal Research, covering The Superior Court of New York City primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reilly v. Mayor, 22 Jones & S. 463, 7 N.Y. St. Rep. 61 (N.Y. Super. Ct. 1887).

Opinions

By the Court.—Dugro, J.

Section 64 of chapter 410 of Laws of 1882 provides that all contracts shall be awarded to the lowest bidder. The lowest bidder for the work actually to be done is intended, and not the lowest bidder for an estimate of the work to be done.

The contractor Reilly was certainly not the lowest bidder for the work provided for by the contract in the matter before us; for in this case, only an estimate of the quantities of material to be removed was obtained, and these estimated quantities were relied upon as factors in determining the lowest bidder; the actual work to be done was no factor whatever in the dótermination.

Some of the bids for the estimated quantities of rock and earth, etc., were as follows :—

[469]*469Cubic y’d Cubic y’d

earth. rock. Curb. Flag. Total.

W. E. Dean,.............$0.25 $1.45 $0.78 $0.26 $20,672.12

M. H. Foley,............. 1.78 1.20 1.20 1.2Ó 12,848.32

John B. Devlin......... 70 1.25 55 22 20,782.00

R. J. Mills,............... 65 1.35 75 30 22,955.00

Wm. Phelan,____________ 40 1.60 65 26 23,131.00

John Slattery,..-_________ 68 1.75 65 26 26,891.00

Thomas E. Crimmins,.. 50 1.75 60 25 24,909.40

Wm. J. Reilly,.......... 1.69 .01 01 01 12,336.64

The amount of these bids attested by the actual quantities of rock, earth, etc., were :

W. E. Dean, $15,309.50 ; M. H. Foley, $27,121.47 ; John B. Devlin, $19,681.24; R. J. Mills, $21,311.85; Wm. Phelan, $18,220.37; John Slattery, $23,472.06 ; Thomas E. Crimmins, $20,045.85; Wm. J. Reilly, $25,255.23.

The lowest bidder, therefore, for the actual work to be done, was W. E. Dean. •'

There is no warrant in law for making estimated quantities of the respective classes of work to be done, factors in the determination of the question as to who the lowest bidder is for public work, the lowest bidder for the contract (not the presumed lowest bidder) is the bidder intended by the statute. Sec. 65 of chap. 410, Laws of 1882.

It is unnecessary to say that if the work were -all of one class, as the removal of earth, or of a mass as amass, no trouble would arise in determining the lowest bidder, but when it is proposed, as in the case at bar, to make one contract which shall provide for the removal of a mass made up of earth and rock, in unknown proportions, a difficulty arises. For then it is apparent that if the price fixed for the removal of earth be other than that fixed for the removal of rock, the only manner in which the question can be determined in the method adopted by ttie city officials in this case, is by a computation in which the respective prices for earth and rock removal, and the respective quantities of earth and rock [470]*470will be the factors. And if it is not possible to determine the proportions of the earth and rock no determination of the question can be made.

The method adopted in the case at bar of estimating the respective proportions of earth and rock, and making the amounts of these estimated quantities factors in the determination of the question, is manifestly no solution, it is a mere conjecture dependent for its verity upon whether the estimates be correct or not.

The lowest bidder for the actual work to be done is intended, and not the lowest bidder on the estimated quantity of work to be done. Appleby v. The Mayor, 15 How. Pr. 428.

“ The party aggrieved was employed in contravention of the policy and terms of the statute. He could not contract with the city except through its authorized agents, and he is chargeable in law with notice of the limitations of official authority imposed by general laws.” Donovan v. The Mayor, etc., 33 N. Y. 293; McDonald v. The Mayor, etc., 68 Ib. 23.

To make a contract for removing a mass containing unknown proportions of rock and earth, it is not necessary to resort to such a system as was adopted in the case at bar.

Many lawful methods of contracting for the wqrk suggest themselves to our minds in which the lowest bidder for the work actually to be done can be ascertained with certainty.

The object of the statutes and the ordinances was to invite real competition for work and to secure its performance for the lowest price which fair and real competition would produce. Matter of Ralph Marsh, 83 N. Y. 434.

The system adopted in the present case is neither sanctioned by law, nor warranted by necessity; it is permissive of pernicious and dangerous results, and could never have been intended to be authorized by law.

[471]*471We have now before this court a case wherein, under this system of accepting a lowest bidder for estimated quantities as the lowest bidder for a contract, one whose bid (by a computation based on estimated quantities of earth and rock and the bidders’ prices for their removal per cubic yard) was $15,526.28, and who by the application of his figures to the actual quantities, as they were ascertained on the completion of the work, received from the city $117,395.68, while the reasonable cost of doing the work was $26,541.79.

It will probably be claimed that, as the city stated its estimate of the respective quantities, and then called for estimates of price per cubic yard only for the various works to be done, with notice that it would not be bound as to quantities, no injustice could be done by an award—in other words, that all the bidders, knowing that the estimated quantities were to be factors only in ascertaining the lowest bidder, were aware that they must determine for themselves the actual qualities. Such reasoning is plausible but specious, «and cannot control this court. The estim«ated quantities were used as though they were the true quantities in the letting of the work, and the city was thereby made a party to a venturesome speculation far removed from the letter and the spirit of the Law. A bidder’s figures will of necessity be fixed by him with regard to the proportionate quantities of earth and rock, as he believes them to exist; and his selection of factors in the determination of the award will be such as will make his bid in amount as he desires, while the factors he selects may be such as will cause the city to pay the highest possible price for the variance between the quantities as estimated by the city and the quantities as they actually exist.

No authority was given by the act to the common council to adopt any ordinance or regulation which should in any way interfere with or prevent the ascertainment of the lowest bidder for the contract, that is, [472]*472for the actual quantity of any public work to be done, or which would leave the determination of such a lowest bidder to chance or conjecture.

Any system of letting contracts for public work is illegal which necessitates the determination of the “ lowest bidder” by conjecture, when it is possible to let a contract for the same work to “ a lowest bidder ” in whose selection no element of chance enters. The disposition of this question makes it unnecessary to consider the others, raised by the appeal.

The judgment should be reversed, and a new trial ordered, with costs to abide the event.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Williams v. . Dayton
55 N.Y. 367 (New York Court of Appeals, 1874)
Matter of the Petition of Ralph Marsh
83 N.Y. 431 (New York Court of Appeals, 1881)
Appleby v. Mayor of New-York
15 How. Pr. 428 (New York Supreme Court, 1858)

Cite This Page — Counsel Stack

Bluebook (online)
22 Jones & S. 463, 7 N.Y. St. Rep. 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reilly-v-mayor-nysuperctnyc-1887.