Reilly v. Lee

16 N.Y.S. 313, 41 N.Y. St. Rep. 559, 61 Hun 627, 1891 N.Y. Misc. LEXIS 421
New York Supreme Court·Decided November 13, 1891·Published·Cited by 3 cases

Opinions

Van Brunt, P. J.

Although various causes of action were set out in the complaint, upon this appeal only the questions involved in the trial of the issues upon the first cause of action and the defendant’s counter-claim are brought up for review. The complaint alleges that the plaintiffs were co-partners in the firm of Reilly & O’Connor, and that in June, 1889, they entered into a contract with the defendant, whereby they agreed to execute, construct, and finish all the masonry work required to be done by the said defendant for the bridge to be constructed by the "Pennsylvania, Poughkeepsie & Boston Railroad Company across the Lehigh river at or near Slating-ton, Pa., for which the defendant agreed to make certain payments to them; that they entered upon the performance of this work, and carried out said contract in the manner and form in all respects as therein provided. The complaint further alleges that it was provided by the contract that when the work required to be done thereunder should have been completed, and the engineer in charge of the work have so certified, and made his estimate of the amount of work performed thereunder, the defendant should pay to the plaintiffs, within 20 days, the sum due to these plaintiffs under said contract. It was then alleged that the work had been fully performed and finished, and the engineer in charge of the work under said contract, more than 20 days before the commencement of the action, had certified that said work was completed, and had estimated the amount of the work done and money earned and due thereunder; that, according to the prices named in said contract, there was a certain sum due for the work done, of which a balance remains unpaid, which is sought to be recovered in said first cause of action. The defendant, by his answer, admitted the contract, denied its performance, and [314]*314denied that the engineer in charge of the work at any time truly or correctly certified that said work was completed, or had truly or correctly estimated the work done or the moneys earned or due thereunder, and alleged that, on the contrary thereof, the amount of work actually done and the money due or earned thereunder was much less than the amount which the pretended certificate the plaintiff obtained from some alleged engineer of the railroad company mentioned set forth, and was much less than the total amount claimed in the complaint", and was not in fact greater in amount or value than the sums of money which the defendant had already paid to the plaintiffs therefor. The plaintiffs, to maintain the issues upon their part, intro-, duced the contract between themselves and the defendant. This contract, so far as it is material for the consideration of the questions involved in this appeal, was as follows: “These articles of agreement, made this sixth day of June, 1889, by and between John E. Lee, of Paterson, N. J., party of the first part, and T. Wallace Reilly and O’Connor, party of the second part, witnesseth, that the second party, for and in consideration of the covenants, stipulations, and agreements hereinafter mentioned, promises and agrees to execute, construct, and finish in every respect, in the most substantial and workmanlike manner, and to the satisfaction and acceptance of the engineer or engineers in charge of the Pennsylvania, Poughkeepsie and Boston Railroad Company, all the masonry work required to be done by the first party for the bridge to be constructed by it across the Lehigh river, at or near Slatington, Pennsylvania.” The second paragraph of said contract is as follows: “>Second, The party of the first part shall have the right at any time, in case the force employed upon such work shall be considered by the engineer or engineers in charge of the railroad company as inadequate to complete any protion of the whole of said work within the time herein specified, to employ and put upon the work such additional force as he or they shall consider requisite.” The fifth and sixth paragraphs of said contract are as follows: “Fifth. It is mutually agreed between the parties hereto that, if the second party shall execute any part of such work defectively, then such defective work shall be rebuilt at the expense of the party of the second part upon receiving the order from the engineer or engineers in charge to that effect. Sixth. And the said first party (in consideration of the fulfillment and performance of all the stipulations contained in this contract, to be by said second party fulfilled and.performed, and whenever said work shall have been, in the opinion of the said engineer or engineers in charge, completely finished in every respect, and performed agreeably to the various stipulations and specifications in this agreement, and said engineer or engineers in charge shall have furnished to said first party a certificate to that effect, under his hand, together with his estimates of the quantity of the various kinds of work done by the second party under this agreement, which estimate shall be final and conclusive between the parties hereto) will pay to the second party, at the office of the Pennsylvania, Poughkeepsie and Boston Railroad Company, in the city of Hew York, within twenty days after said certificate and estimate shall have been furnished by the said engineer or engineers in charge, the sum which may be due under this contract, agreeably to such estimate.” Here follow the prices charged.

One of the plaintiffs then testified that 20 or 30 days after the work was finished he asked the defendant if he had his certificate, and that the defendant replied that he had received the final certificate and estimate for the Slatington bridge, and that that was the only one he had received. He said he had been doing a good deal of grading, and that he could not pay the plaintiffs finally on this work, but would give $2,000 on account, and would pay the balance very soon,—within a week or two, in that neighborhood, or as soon as he got his affairs in shape. He further testified that about the same time he received from the defendant a statement of account, which he produced, in the hand[315]*315writing of the defendant’s clerk, showing the amount of work done on the Slatington bridge, as certified to by the engineer. He further testified that they built the piers and did all the masonry work according to the specifications and under the personal direction of the engineer in charge of the work, Mr. John Schafer, of Newark, N. J., and that he was the engineer for the railroad company. The plaintiff further testified that a Mr. Primrose was the chief engineer of the Pennsylvania, Poughkeepsie & Boston Bailroad Company, and also offered in evidence final estimates approved by Mr. Primrose as chief engineer. It was claimed at the time of the introduction of this evidence, by the defendant’s counsel, that this was an estimate, and not a final certificate, as required by the contract. The plaintiffs also introduced in evidence a copy of the final estimate, approved by Mr. Schafer as engineer in charge, and delivered to the plaintiffs, which evidence was duly objected to by the defendant, and the exception taken to its admission. Mr. Schafer testified that at the time he put on the word “approved” the entire work as done had been approved by him, from time to time, during the construction. The defendant, at the close of the plaintiffs’ case, moved to dismiss the complaint as to the first cause of action upon the ground that it had not been proved as alleged, and that there was no evidence of a final certificate given by the engineer in charge of the Pennsylvania, Poughkeepsie &

Free access — add to your briefcase to read the full text and ask questions with AI

Reilly v. Lee, 16 N.Y.S. 313, 41 N.Y. St. Rep. 559, 61 Hun 627, 1891 N.Y. Misc. LEXIS 421 (N.Y. Super. Ct. 1891).

16 N.Y.S. 313 (Reilly v. Lee) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Braun v. Hothan
84 N.Y.S. 8 (Appellate Division of the Supreme Court of New York, 1903)
Banker v. Knibloe
23 N.Y.S. 1091 (New York Supreme Court, 1893)
Kinnear v. Powell
23 N.Y.S. 182 (Superior Court of New York, 1893)