Reilly-Benton Co. v. Gurtler, Hebert & Co.

212 So. 2d 514, 1968 La. App. LEXIS 4895
CourtLouisiana Court of Appeal
DecidedJuly 1, 1968
DocketNo. 3091
StatusPublished
Cited by1 cases

This text of 212 So. 2d 514 (Reilly-Benton Co. v. Gurtler, Hebert & Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reilly-Benton Co. v. Gurtler, Hebert & Co., 212 So. 2d 514, 1968 La. App. LEXIS 4895 (La. Ct. App. 1968).

Opinion

JOHNSON, Judge.

The plaintiff, Reilly-Benton Company, Inc., filed this civil action to collect the unpaid portion of the price of a construction subcontract with the defendant, Gur-tler, Hebert & Company, Inc., the prime contractor for the construction of an addition to the plant of Armstrong Tire & Rubber Company, at Natchez, Mississippi. The Civil District Court for the Parish of Orleans rendered judgment in favor of plaintiff. The defendant has appealed.

In the building to be constructed the general contract between the owner and the defendant requires the erection of major equipment called a “hot-dip” unit consisting of several large rectangular heaters, three tall towers about 90 feet in height and one shorter tower, and a network of ducts connecting the various component parts of the unit. The work scope of the prime contract included three main types of insulation in various parts of the equipment, briefly described, as follows: 1. “Blankets,” which are long strips of insulation, some of which are three inches and some four inches thick to be fastened to the sheet metal hot ducts with metal pins welded to the duct surface over which blankets there was to be applied one-half inch cement coating; 2. “Bats” and panels,” which were compressed insulation material prefabricated with sheet metal to encompass the heaters and towers; 3. “Loose wool” insulation to fill the joints and seams of the panels. Also there was insulation of the roof of the plant addition.

The plaintiff is an insulation specialist. The plaintiff asked to bid on insulation on this job and plaintiff’s Mr. Taylor and Mr. Watters met with defendant’s Mr. Black to discuss the matter. Mr. Black placed on the large conference table some 110 to 125 separate drawings and plans for the entire construction and installations. In examining some of the drawings at that time, Mr. Taylor and Mr. Watters noticed some reference to the various types of insulation and asked about them. Mr. Black explained that the only scope of work plaintiff was to bid on was the blanket insulation on the hot ducts and he advised plaintiff that the panel type insulation was to be prefabricated and installed with the sheet metal. Mr. Black selected and delivered to Mr. Taylor and Mr. Watters 12 separate drawings which he said would show all of the blanket insulation of the hot ducts which plaintiff was to bid on and plaintiff was not to be concerned with cold ducts, panel or bat applications. Nothing was said about the loose wool packing of the joints or seams of the panels.

Mr. Taylor and Mr. Watters took the 12 drawings with them and from them prepared plaintiff’s first proposal to do the blanket insulations, which they submitted on October 12, 1961, for the price of $14,-056.00. It so happens that plaintiff manufactures and sells various types of insulation and that the general contract requires the defendant to buy the insulation materi[516]*516al from C. A. Litzler Company, Inc.; that Litzler in turn placed its order with the plaintiff to purchase all of the insulation material called for by the general contract. This enabled plaintiff to make a profit in the sale of the materials to Litzler Company. Haying heard nothing from defendants in response to its first proposal, plaintiff decided to revise its proposal to defendant by reducing its price for the installation of the blanket insulation. On December 5, 1961, plaintiff submitted a second proposal for the same installation work contained in the first proposal but at a reduced price of $12,200.00. The pertinent portions of the proposal are as follows:

“We wish to thank you for the courtesies extended, and confirm our quotation verbally of this date for all labor, equipment, tools, scaffolding, supervision and accessory materials required to apply insulating materials furnished by C. A. Litzler on the above subject project in accordance with drawings by C. A. Litzler, Inc. Drawings pertaining to this work are as follows: Drawing No. EA 1953, 1952, 1924, 1923, 1920, 1916, 1907, 1900, 1899, and 1896; ER-519, and 517. It is understood under this proposal that blanket insulation and required insulating cement will be furnished to us at job site in storage free of cost to us.
“We are to furnish necessary weld pins, speed washers and equipment required to pin weld 12 gauge securement pins to the duct work as well as required lacing tie wire and/or staples. Insulation will be applied by impaling over se-curement welded pins and locked with speed washers impaled over the weld pins. Over this we will trowel approximately 1/2" of insulating cement in accordance with specifications noted on above drawings by manufacturer.
* *■ * * * *
“PRICE-Labor, equipment, scaffolding, supervision and accessores to apply insulation on hot ducts per above drawings complete-$12,-200.00” (Emphasis added).

It will be noted that this proposal is only for the installation of the blanket insulation on the hot ducts shown on the particular numbered 12 drawings which Mr. Black delivered to Mr. Taylor and Mr. Watters and that these 12 drawings do not show the application of the bats, panels, loose wool or roof insulation. It is also important to note that the book of specifications does not contain any description or requirements on the subject of insulation. Insulation is designated on the drawings. There are other drawings and documents which do outline the application of bats, panels, loose wool and roofing but Mr. Black limited plaintiff’s bid to the blanket insulation shown on the 12 drawings which he selected and which 12 drawings are designated by number in plaintiff’s proposal.

On December 12, 1961, the defendant prepared and sent to plaintiff the subcontract drawn on defendant’s own printed form, signed by Leonard B. Hebert, Jr., Executive Vice-President for Gurtler-He-bert Company, Inc. A cover letter, signed by Mr. Hebert, transmitting the subcontract, says:

“We transmit herewith Subcontract No. D-4282-3 in the amount of $12,200.-00 covering Insulation all as per your proposal and our acceptance thereof.”

Inserted in the printed form under the topic head: “Description of Work” by typewriter is the following stipulation:

“According to the contract plans and specifications the Armstrong Tire and Rubber Company is to furnish to Gur-tler, Hebert & Co., Inc., certain of the insulation materials. The materials which Armstrong Tire and Rubber Company furnishes us will be furnished to you free of cost, delivered in accordance with the terms and conditions of our contract. You are to take these materials and are to furnish whatever other materials required and perform with your labor and equipment all of the insu[517]*517lation work called for by the general contract, plans and specifications.”

Mr. Taylor, for the plaintiff, testified that upon the receipt of the subcontract he checked the scope of work by the drawings, which Mr. Black had furnished him, and his price, and finding them in agreement he signed the contract and returned the copies to defendant. After proceeding in the performance of the work, the defendant called upon plaintiff to do certain packing of loose wool in some joints; whereupon Mr. Taylor informed defendant that such work was not in plaintiff’s subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Starke Taylor & Sons, Inc. v. Riverside Plantation
301 So. 2d 676 (Louisiana Court of Appeal, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
212 So. 2d 514, 1968 La. App. LEXIS 4895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reilly-benton-co-v-gurtler-hebert-co-lactapp-1968.