Reif v. First National Bank of the Black Hills

369 N.W.2d 123, 1985 S.D. LEXIS 295
CourtSouth Dakota Supreme Court
DecidedMay 29, 1985
DocketNo. 14663
StatusPublished

This text of 369 N.W.2d 123 (Reif v. First National Bank of the Black Hills) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reif v. First National Bank of the Black Hills, 369 N.W.2d 123, 1985 S.D. LEXIS 295 (S.D. 1985).

Opinion

FOSHEIM, Chief Justice.

William J. Reif (contractor) appeals from a judgment on a housing contract. We reverse and remand.

We refer to Reif v. Smith, 319 N.W.2d 815 (S.D.1982) (Reif I), for factual background which will be supplemented as necessary for disposition of the issues on this appeal.

In Reif I, we held that the plans and material list were inadequate, that owners could not waive a provision of the original contract requiring written change orders for some items and not for others, and that the contractors should receive compensation for all of the extras and the amount owing under the original contract. The owners were to receive a set-off only for that portion of the work performed according to the plans but in a defective manner. They were not to receive a set-off for work accomplished according to the plans or for work that remained unfinished because contractors were ordered off the job. We directed the trial court on remand to redetermine the amount allowed to contractors as extras, and the amount allowed to owners as a set-off against the amount claimed by contractors. The issues on appeal involve the amount of extras, amounts allowed as a set-off, and the work in exchange for rent arrangement between owner and a carpenter.

AMOUNT OF EXTRAS

The first issue stems from the trial court’s finding of fact No. VIII:

“Plaintiffs claim for extras in the amount of $6,561.81, which the plaintiffs have proven by evidence, should be reduced by $1,012.02, which is the total of invoices number 5911, 6197, 6428, 6490, and 6592, which were either items purchased or work performed by plaintiff William G. Reif, d/b/a Reif Construction, prior to the commencement of the work on the contract involved in this litigation.”
A review of the record indicates that the starting figure of $6,561.80 in Finding VIII is erroneous. That figure appears only on the contractor’s lien statement (plaintiff’s exhibit 12), and in Reif I, findings of fact and conclusions of law. It was originally considered the amount owing to the plaintiffs under the contract as final payment, not as the total amount for any extras. The total amount of claimed extras on the lien statement was $8,840.47.

The trial court reduced the erroneous $6,561.80 figure by what it determined was the total of invoices number 5911, 6197, 6428, 6490 and 6592 which appear in plaintiff’s Exhibit ll.1 None of these invoices, however, were ever claimed as extras. The only extras claimed were the invoices included in Exhibit 9. An incorrect disallowance accordingly resulted because the wrong starting figure was reduced by the wrong invoices.

Exhibit No. 9 constituted the entire extra material claimed to have been purchased from Island’s Building Center, listed on the lien statement. That total is $2,569.58.

The trial court originally found that the living room window for $200.00, the firebox for $345.60 and the fireplace door for $168.28, were extras. Nevertheless, finding of fact No. IX from the second trial concluded contractor failed to prove that all other items claimed as extras were separate and independent of the contract and plans; and therefore were not allowed as extras. This is contrary to our direction on remand that contractor should receive the contract price, plus compensation for the extras, labor and materials. See Reif, supra at 817.

[126]*126Contractor states he is claiming extras for everything, however, he does not list the $2,101.00 for outside material and labor, detailed on Exhibit B. The trial court made no finding on this item. Owner admitted he instructed contractor to complete the outside work as claimed in Exhibit B; however, he denies knowledge that he was going to be charged for the material. Because this matter was brought up in the second trial but is not briefed, it is uncertain whether contractor has abandoned its original outside material and labor claim for the $2,101.50: Boe v. Healy, 84 S.D. 155, 168 N.W.2d 710 (1969). This uncertainty should be settled.

It also appears from the second trial evidence, owner’s admissions and the original findings of fact that, contrary to the trial court’s current finding of fact No. XIII, the following items were proved as extra materials: (1) materials purchased outside the original agreement for $2,829.58; (2) labor at 120% of materials cost for $3,395.50; and, (3) materials purchased but not installed by contractor which would be the firebox and fireplace door for $513.89. This totals $6,738.97.

AMOUNTS ALLOWED AS SET-OFFS

After contractor was ordered off the job, owner arranged with a carpenter to make the repairs he deemed necessary. Contractor claims the trial court failed to follow the law of the case expressed in Reif /, supra. The trial court found that the plans were not defective; consequently, all repairs claimed by owners were a result of defective workmanship. This finding was made notwithstanding the testimony and other evidence submitted by the contractor indicating that some of the work claimed as a set off was actually 1) work performed according to the plans, 2) work that was left undone because contractors were ordered off the job, and 3) later additions and changes that were neither called for in the plans or discussed as extras. Contractor also submitted evidence that some of the work claimed was charged for, but not actually completed. Because each item is disputed, we will discuss them separately.2

Owner claimed that renailing3 was required, but admitted that the sheetrock was originally installed according to the plans. Contractor testified that he told owner to use studs to secure the sheetrock, but owner refused and ordered it done according to the plans. In Reif I, we held that owners were responsible for the inaccuracies in the construction plans and that owners should not have received an offset for additional work required due to inadequacy of the blue-print supplied by themselves.” Reif I, supra at 818.

Owner asked the carpenter to texture all of the walls and the kitchen ceiling. The texturing, at least in the kitchen, may have been required because owner added a soffit. Owner conceded that the soffit is not the responsibility of contractor; therefore, any texturing that was required because of that addition should not be the contractor’s responsibility.

The contractor testified that the center post for the handrail4 was not in the plans, and that the nailing in the basement was not needed. Witnesses also testified that approximately four days prior to the second trial they inspected the premise's. No additional blocking had been completed, even though owner submitted a charge for such work. A specific finding on these items should be made.

[127]*127The original plans called for a flat ceiling in the bedroom. Owner and contractor agreed to change the plans to require a cathedral ceiling.5 Contractor built the cathedral ceiling, but left a gap, which produced an insect problem; indicating that his work was defective. The trial court’s finding on this item was not erroneous.

Next, owner submitted a charge for painting.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gifford v. Bowling
200 N.W.2d 379 (South Dakota Supreme Court, 1972)
Apoian v. State
235 N.W.2d 641 (South Dakota Supreme Court, 1975)
Zahrowski v. Dahl
100 N.W.2d 802 (South Dakota Supreme Court, 1960)
Boe v. Healy
168 N.W.2d 710 (South Dakota Supreme Court, 1969)
Reif v. Smith
319 N.W.2d 815 (South Dakota Supreme Court, 1982)
Hutchinson County v. Bender
264 N.W. 816 (South Dakota Supreme Court, 1936)
Hillcrest Terrace Corp. v. City of Rapid City
23 N.W.2d 793 (South Dakota Supreme Court, 1946)
Steere & Ballah v. Gingery
110 N.W. 774 (South Dakota Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
369 N.W.2d 123, 1985 S.D. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reif-v-first-national-bank-of-the-black-hills-sd-1985.