Reider v. P-48, Inc.

362 So. 2d 105, 1978 Fla. App. LEXIS 16589
CourtDistrict Court of Appeal of Florida
DecidedAugust 22, 1978
DocketNo. EE-142
StatusPublished
Cited by7 cases

This text of 362 So. 2d 105 (Reider v. P-48, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reider v. P-48, Inc., 362 So. 2d 105, 1978 Fla. App. LEXIS 16589 (Fla. Ct. App. 1978).

Opinion

PER CURIAM.

Appellants, Mr. and Mrs. Reider, brought this action in the trial court seeking return of certain deposit moneys paid toward the [107]*107purchase of two condominium units which were to be constructed by Appellee, P-48, Inc. and for recovery of expenses incurred by Appellants in improving the units in preparation for closing the transaction. Appellants also sought to have a vendees lien enforced against the property to secure such repayment. Appellee filed a counterclaim seeking damages incurred as a consequence of Appellants’ alleged refusal to close the sale of the units. The case was tried by the court, sitting without a jury. The court found that Appellants breached their contract to purchase the units by failing to close on the date specified by Appel-lee. The final judgment upheld the operation of the liquidated damages clause of the contract and ruled that Appellants recover nothing from Appellee. The court further ruled that in view of its holding that Appel-lee would be permitted to retain the deposit moneys under the liquidated damages clause, that Appellee should recover nothing from Appellants on its counterclaim.

We find that the evidence does not support the trial court’s finding that Appellants breached their contract by failing to close the purchase of the condominium units on the date specified by Appellee. We further find that even if Appellants had so breached said contract, Appellee was not in sufficiently “strict compliance” with its contract obligations as would entitle it to retain the deposit moneys.

In 1971 and 1972, Mr. and Mrs. Reider, Appellants, agreed to purchase two adjoining units (# 104 and # 105) in a condominium development known as the “Atlantis” being built by the seller, Appellee P-48, Inc. Appellants agreed to pay a purchase price of $39,800.00 for Unit # 105 and a purchase price of $18,200.00 for Unit # 104. Appellants paid a deposit of $7,900.00 towards the purchase price of Unit # 104.1 At the time of the said contracts, construction of the units had not yet commenced. The units were to be constructed in accordance with certain plans and specifications and construction was commenced in the fall of 1972. Substantial delay in the anticipated completion of the project was encountered by reason of difficulties which the Appellee had with its general contractor regarding correctness and quality of construction. In March, 1974, Appellee sent letters to the purchasers of the various units in the Atlantis, including Appellants, advising them that a certificate of occupancy on the Altantis had been obtained and that, although delays in completion had “been very frustrating to all of us” and that “even now there are items in some apartments and in the common areas to be completed”, Appellee wished to close the sale of the units immediately. In response, Appellants advised Appellee by letter dated March 20,1974, that while they did not wish to unnecessarily delay closing, there were a number of items in need of repair before they would agree to close. Subsequently, Appellee advised Appellants by letter dated May 30, 1974 that Appellee had “completed all of the repairs which it expects to make on Unit # 104-105” and stated that unless certain closing documents were executed by Appellants and checks tendered by June 4, 1974, Appellants would be considered in default and the units would be immediately listed for resale. By letter dated May 31, 1974, Appellants advised Appellee that they were prepared to close provided that certain designated construction defects were reme1 died. In the alternative, Appellants advised Appellee in that letter that they would agree to close if Appellee would agree to place $2,500.00 in an escrow account of Ap-pellee’s attorney to assure that the necessary repairs would be properly made, with provision that in the event that the repairs listed were not made within 30 days of closing, Appellants would be able to direct that the escrow funds be disbursed for the necessary repairs. Having received no response to their May 31, 1974 letter, Appellants again wrote to-Appellee on June 24, 1974, reiterating Appellants’ desire to close on the conditions set forth in the previous letter. Again, Appellee failed to respond to Appellants’ letter. Finally, on July 26, [108]*1081974, Appellants wrote to Appellee and demanded return of the deposit money. Ap-pellee failed to do so and Appellants instituted this action.

The trial judge found in his Findings of Fact that the subject units were ready for closing on May 1, 1974 and that Appellants defaulted in refusing to close at that time. Such finding is not supported by the evidence. In fact, Appellee tacitly concedes such since Appellee’s position on appeal appears to be that the units were ready for closing on June 4, the date by which Appel-lee demanded in its May 30 letter that Appellants return the necessary closing documents and checks. Appellee contends on appeal that Appellants were in default by reason of their failing to close by June 4.

We find that, in view of the condition of the subject premises on June 4,1974, Appellants had no duty to close the purchase on that date as demanded by Appellee. Accompanying Appellants’ above referred May 31, 1974 letter to Appellee was an itemized list of defects and deficiencies in these units which remained to be remedied. Included in such “punchlist” were several substantial items which the evidence showed were still unresolved on June 4. One of the problems centered around the condition of the sliding glass doors on the oceanfront side of the units. The doors did not meet specifications, and they rattled and whistled whenever there was an ocean breeze. This was a problem throughout the Atlantis. In fact, an obviously frustrated Appellee/Developer wrote to his general contractor on December 18, 1974:

“The Directors of the Atlantis Association are complaining strenuously about the delay. Their complaints are very much in order. When the wind blows from an eastward direction the noise from the sliding glass doors is very annoying and they should not be expected to endure this noise any longer.”

It was also shown that the sliding glass doors installed at the Atlantis did not meet structural load specifications. The doors failed a structural load test administered in September, 1974 and the defects in such doors were not remedied until mid 1975. Also, air conditioning ducting into certain areas of the units as called for in the plans and specifications was deleted by Appellee as a cost cutting measure resulting in insufficient cooling. The parking stall for Unit # 104 was not constructed in accordance with the minimum space requirement of the applicable city ordinances and presented a substantial problem in accommodating a standard size automobile. A closet was so reduced in size inadvertently by the carpenters as to make it virtually unusable. The wash basin in the dressing area to the master bedroom was improperly installed. It is clear from the evidence that these as well as several other deficiencies were as yet unresolved on June 4, 1974. In addition, there were a number of defects of a substantial nature in the condominium common areas which remained unresolved on that date. Moreover, the person who was Ap-pellee’s manager at the Atlantis in June, 1974, testified that units 104 and 105 were not ready for closing in the first week of June, 1974, that she would not have accepted them, that Mr. Reider was the only one who could not move into his unit, that Mr. Reider “was having more trouble than anyone” and that she sympathized with Mr. Reider because of the problems he was having.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hand v. GROW CONST., INC.
983 So. 2d 684 (District Court of Appeal of Florida, 2008)
Jones v. Warmack
967 So. 2d 400 (District Court of Appeal of Florida, 2007)
Alterman v. Martin-Busutil
716 So. 2d 849 (District Court of Appeal of Florida, 1998)
Avellone v. Mehta
544 So. 2d 1122 (District Court of Appeal of Florida, 1989)
Rodriguez v. Leonard
477 So. 2d 19 (District Court of Appeal of Florida, 1985)
Guerrera v. Eldred Construction Corp.
378 So. 2d 327 (District Court of Appeal of Florida, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
362 So. 2d 105, 1978 Fla. App. LEXIS 16589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reider-v-p-48-inc-fladistctapp-1978.