Reichhold, Inc. v. United States Metals Refining Co.

655 F. Supp. 2d 400, 2009 U.S. Dist. LEXIS 52471, 2009 WL 1806668
CourtDistrict Court, D. New Jersey
DecidedJune 22, 2009
DocketCiv. 03-453(DRD)
StatusPublished
Cited by8 cases

This text of 655 F. Supp. 2d 400 (Reichhold, Inc. v. United States Metals Refining Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reichhold, Inc. v. United States Metals Refining Co., 655 F. Supp. 2d 400, 2009 U.S. Dist. LEXIS 52471, 2009 WL 1806668 (D.N.J. 2009).

Opinion

OPINION

DEBEVOISE, Senior District Judge.

CONTENTS

I. Background..............................................................404

II. The Parties’ Contentions...................................................408

III. Preliminary Rulings.......................................................410

A. Treatment Increased Costs............................................410

B. Inclusion of Investigation Costs.........................................411

C. Aerial Deposition Evidence ............................................412

D. Admissibility of Evidence Establishing Costs.............................416

IV. Negotiation of the of the Cleanup Plan with N JDEP...........................423

V. New Environmental Obligations ............................................426
A. General .............................................................426

*404 B. Site-Wide Analytical Delineation .......................................427

C. CVOCs..............................................................431
D. Capping the Staflex Parcel.............................................432
E. BTL Cap............................................................433
F. BTL Baseline Ecological Evaluation.....................................433
G. Delta Costs..........................................................433
VI. Source of Contamination...................................................434
A. General .............................................................434
B. Site-Wide Analytical Delineation .......................................436
C. Staflex Parcel Cap....................................................438
D. BTL Cap............................................................440
E. BTL Baseline Ecological Evaluation.....................................443
VII. Discussion...............................................................444
VIII. Conclusion...............................................................449

Plaintiff, Reichhold, Inc. (“Reichhold”), commenced this action on January 31, 2003, requesting legal and declaratory relief against United States Metals Refining Company (“USMRC”) pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601-9675, as amended by the Superfund Amendments and Reauthorization Act of 1986, Pub. L. 99-499, 100 Stat. 1613 (1986); and the New Jersey Spill Compensation and Control Act (the “Spill Act”), N.J. Stat. Ann. §§ 58:10-23.11 to 23.11(2). Reichhold later filed an amended complaint, adding CyprusAMAX Minerals Company and related entities as defendants 1

Reichhold seeks damages from USMRC for its past and future costs to address and remediate metals and chlorinated volatile organic compounds (“CVOCs”) contamination at the approximately 40-acre property formerly owned by Reichhold in Carteret, New Jersey (the “Site”). Reichhold also seeks a declaratory judgment for future investigation and remediation costs both on the Site and adjacent areas in and around the Arthur Kill that Reichhold has been directed by the New Jersey Department of Environmental Protection (“NJDEP”) to investigate and address.

During the period January 22 to March 4, 2009, the case was tried without a jury. This opinion constitutes the court’s findings of fact and conclusions of law.

I. Background

USMRC was incorporated as the Delmar Cooper Refining Company in November, 1903. The name was changed to USMRC in November, 1906. Between 1901 and 1986, USMRC conducted metals refining operations on property out of which the Site was carved when USMRC sold it to Reichhold in June, 1960. (See accompanying map of Site — Appendix A.)

USMRC performed primarily three operations on its property adjacent to the Site: (1) smelting and refining copper-bearing materials, including high and low grade scrap, (2) production of standard and unconventional coppers, and (3) smelting and refining of scrap materials bearing precious metals. More than 500,000 tons of scrap per year were typically charged to *405 the smelter. A variety of materials containing metal components were processed at the USMRC facility to recover copper and precious metals, including telephone and electronic scrap, automotive parts, electric motors and insulated wires.

USMRC’s smelting operations produced slag as a residual. The slag was transported from the cupola by rail car or by truck to slag storage areas including, in particular, a large slag pile on the BTL Parcel. (See Appendix A.)

In 1930 USMRC constructed a lead plant on what became the Reichhold Site. It began operations in 1931 and was used to refine lead and tin. The USMRC lead plant was dismantled in or before 1952. The lead plant was housed in the building which will be referred to as Building 401.

By letter dated November 13, 1950, USMRC agreed to sell approximately 400,-000 cubic yards of granulated slag to the Villa Contracting Company. That company intended to use this slag in connection with its contract with the New Jersey Turnpike Authority. Slag was placed on the Staflex Parcel (See Appendix A) to form a base for a haul road over which slag was trucked to the Turnpike.

In 1956 Anchor Abrasives Co. commenced producing slag grit. Slag, which USMRC sold to Anchor Abrasives, was run through screens to eliminate fine and large particles to create a product of uniform size. The product was bagged and sold for sandblasting. These screens were operated on top of the slag pile on the BTL Parcel.

In 1960, USMRC sold the 40-acre portion of its property in Carteret constituting the Site to Reichhold pursuant to a Purchase Agreement dated June 27, 1960 (the “Purchase Agreement”). The Site included a southern parcel (the “BTL Parcel”) located between the Arthur Kill and a parcel of land owned by the Central Railroad Co. of New Jersey (the “Jersey Central Railroad”), and another parcel located north of the railroad property (the “Staflex Parcel”). The Staflex Parcel consisted of a Northwest Field and a Southwest Field, to which reference is made in some of the relevant documents in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Camiolo, P. v. Erie Insurance Exchange
Superior Court of Pennsylvania, 2019
N.J. Dep't of Envtl. Prot. v. Exxon Mobil Corp.
183 A.3d 289 (New Jersey Superior Court App Division, 2015)
New Jersey Dep't of Envtl. Prot. v. Atlantic Richfield Co.
33 F. Supp. 3d 259 (S.D. New York, 2014)
Morristown Associates v. Grant Oil Co.
74 A.3d 968 (New Jersey Superior Court App Division, 2013)
ASHLEY II OF CHARLESTON, LLC v. PCS Nitrogen, Inc.
791 F. Supp. 2d 431 (D. South Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
655 F. Supp. 2d 400, 2009 U.S. Dist. LEXIS 52471, 2009 WL 1806668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reichhold-inc-v-united-states-metals-refining-co-njd-2009.