Regier v. Nebraska Public Power District

199 N.W.2d 742, 189 Neb. 56, 1972 Neb. LEXIS 656
CourtNebraska Supreme Court
DecidedAugust 4, 1972
Docket38365, 38366
StatusPublished
Cited by16 cases

This text of 199 N.W.2d 742 (Regier v. Nebraska Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regier v. Nebraska Public Power District, 199 N.W.2d 742, 189 Neb. 56, 1972 Neb. LEXIS 656 (Neb. 1972).

Opinion

Boslaugh, J.

These are appeals in proceedings in eminent domain. They were consolidated for trial in the district court and for briefing and argument in this court.

The plaintiffs, Theodore Regier and Marjorie Regier, own and farm approximately 626 acres of land south and east of Aurora, Nebraska. In 1969, the defendant condemned easements across the plaintiffs’ property for the construction of a transmission line.

The appraisers appointed by the county judge fixed the damages at $29,500. The defendant appealed to the district court where the jury returned a verdict in the amount of $62,600. The defendant appeals.

The plaintiffs’ land consists of the southwest quarter of Section 22, the northeast quarter of Section 27, and the west half of Section 26, all in Township 10 North, Range 6 West of the 6th P.M., in Hamilton County, Nebraska. The land is fertile, level, irrigated land. It is well developed and improved for agricultural use. Its value before the taking was between $559,800 and $681,260.

The defendant, in its declarations of taking, divided the plaintiffs’ land into separate tracts. The petitions filed in the county court described Tract No. H-29 as the NE % SW %, and the NW % of 26-10-6. Tract No. H-30 was described as the NE % of 27-10-6. Separate awards were made by the appraisers and separate appeals were taken by the defendant to the district *58 court. In the district court the cases were consolidated for trial with the separate tracts considered as separate causes of action. Separate verdicts were returned on each cause of action and separate appeals taken to this court. The defendant now contends that the judgments should be reversed and the causes remanded for a new trial because the plaintiffs’ land was not considered as a single unit in the district court.

All of the land involved in these cases is owned by the plaintiffs, is contiguous, and is devoted to the same use. It should have been considered as one unit or parcel for the purpose of ascertaining the damages resulting from the taking of the easements. See Verzani v. State, 188 Neb. 162, 195 N. W. 2d 762. The assignments of error, however, cannot be sustained for several reasons.

The error resulted from the defendant’s election to divide the plaintiffs’ land into separate tracts in the declarations of taking. A party cannot be heard to complain of an error which he was instrumental in bringing about. Beveridge v. State, 183 Neb. 406, 160 N. W. 2d 229, The defendant had the benefit of separate appraisals which would have permitted a single appeal if it had been satisfied with one of the awards. It cannot now complain of the theory which it adopted in the petitions filed in the county court. Furthermore, the record shows there was no prejudice to the defendant. Error without prejudice is not ground for reversal.

The defendant filed motions for a change of venue which were overruled by the district court. The ruling on these motions is assigned as error. The motions alleged, in substance, that a fair and impartial trial could not be had in Hamilton County because bias, prejudice, bitterness, and hostility against the defendant would make it impossible to select fair and impartial jurors. Affidavits offered in support of the motions referred to a number of newspaper articles which were *59 critical of the defendant and the routing of the transmission line.

The defendant did not examine any of the prospective jurors in regard to the newspaper articles, and the voir dire examination of the jury panel did not show that a fair and impartial jury could not be obtained. No challenge for cause by the defendant was overruled, and at the close of the examination of the jury panel, it was passed for cause by the defendant. Under these circumstances, it is unnecessary to consider further the showing made in support of and in resistance to the motions. A party who fails to challenge the jurors for disqualification and passes the jurors for cause waives any objection to their selection. State v. Eggers, 175 Neb. 79, 120 N. W. 2d 541; State v. Harris, 184 Neb. 301, 167 N. W. 2d 386.

The defendant contends that the verdicts were excessive. This is the principal issue presented by the appeals.

The verdicts in these cases included both permanent and temporary damages caused by the taking of the easements. The taking occurred on May 28, 1969. Construction of the transmission line began in April. 1970. The defendant’s contractor moved heavy equipment onto the land causing compaction and disturbance of the soil in the easement area. There was also a problem with trash left by the contractor which interfered with farming operations. The plaintiffs estimated the temporary damages at $10,000. A witness for the defendant estimated the temporary damages at $3,000. Since the verdicts were general, the amount allowed by the jury for temporary damages cannot be determined.

The easements taken are 150 feet wide and cross the plaintiffs’ property on a diagonal line from northwest to southeast. The combined area of the easements is approximately 19 acres. The centerline of the easement area across Section 27 intersects the west boundary of the northeast quarter 1,060 feet south of the north line *60 of the section. The centerline intersects the line between Sections 27 and 26, 703 feet north of the half-section line. The centerline intersects the east boundary of the west half of Section 26, 168 feet south of the half-section line. No part of the southwest quarter of Section 22 is included in the easement area.

The trial court considered the west half of Section 26 to be the area affected by easement across Tract H-29, and the northeast quarter of Section 27 and the southwest quarter of Section 22 to be the area affected by the easement across Tract H-30. It was a question of fact as to whether there was remainder damage to the southwest quarter of Section 22 and that part of the southwest quarter of Section 26 omitted from the description of Tract H-29 in the petitions filed in the county court. The evidence was in conflict and the question was for the jury.

The plaintiffs’ land is irrigated from 6 wells and 3 reuse pits. One of the wells on Tract H-30 is located within the easement area. Since the date of the taking, the plaintiffs have drilled an additional well near the center of the southwest quarter of Section 26 and have installed a center pivot irrigation system there. Much of the evidence relates to center pivot irrigation systems, their desirability and efficiency; whether the land was adaptable to irrigation by center pivot systems; and the effect the easements had upon the market value of the land because parts of it now cannot be irrigated by center pivot systems. The evidence was in conflict and presented questions for the jury.

The transmission line presently constructed across the plaintiffs’ land is a 345,000 volt line with 6 conductors and 2 shield wires. There are 7 “K” frame, 2-pole structures on the land which are 750 to 900 feet apart. The poles of each structure are spaced 26 feet apart. There are no guy wires or down-guys on the structures at this time but the evidence shows some of the structures are no longer perpendicular.

*61

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Czech v. Allen
318 Neb. 904 (Nebraska Supreme Court, 2025)
State v. Clark
315 Neb. 736 (Nebraska Supreme Court, 2024)
Howard v. State Farm Mutual Automobile Insurance
496 N.W.2d 862 (Nebraska Supreme Court, 1993)
Bittner v. Miller
410 N.W.2d 478 (Nebraska Supreme Court, 1987)
State v. Bonaparte
384 N.W.2d 304 (Nebraska Supreme Court, 1986)
Emery v. Mangiameli
359 N.W.2d 83 (Nebraska Supreme Court, 1984)
Schroll v. Fulton
328 N.W.2d 780 (Nebraska Supreme Court, 1983)
Kenyon v. Larsen
286 N.W.2d 759 (Nebraska Supreme Court, 1980)
Foreman & Clark of Nebraska, Inc. v. City of Omaha
280 N.W.2d 892 (Nebraska Supreme Court, 1979)
Reicheneker v. Seward
277 N.W.2d 539 (Nebraska Supreme Court, 1979)
Nebraska Electric Generation & Transmission Coop., Inc. v. Tinant
241 N.W.2d 134 (South Dakota Supreme Court, 1976)
State v. Myers
209 N.W.2d 345 (Nebraska Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.W.2d 742, 189 Neb. 56, 1972 Neb. LEXIS 656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regier-v-nebraska-public-power-district-neb-1972.