Regency Midland Construction, Inc. v. Legendary Structures Inc.

CourtCalifornia Court of Appeal
DecidedNovember 7, 2019
DocketB292602
StatusPublished

This text of Regency Midland Construction, Inc. v. Legendary Structures Inc. (Regency Midland Construction, Inc. v. Legendary Structures Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regency Midland Construction, Inc. v. Legendary Structures Inc., (Cal. Ct. App. 2019).

Opinion

Filed 11/7/19 CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION EIGHT

REGENCY MIDLAND B292602 CONSTRUCTION, INC., (Los Angeles County Super. Ct. Plaintiff and Respondent, No. BC629322)

v.

LEGENDARY STRUCTURES INC.,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of Los Angeles County, Howard Halm, Judge. Affirmed. The Soni Law Firm, M. Danton Richardson, Leo E. Lundberg, Michael A. Long for Defendant and Appellant. Law Office of Parham Hendifar, Parham Hendifar, Michael Diaz for Plaintiff and Respondent. __________________________ A general contractor named Regency Midland Construction, Inc. hired subcontractor Legendary Structures, Inc. to do the concrete work for a new apartment building. Legendary quit halfway through. Regency and Legendary sued each other. Their dispute turns on the “retention” clause in the contract. The trial court properly granted summary judgment for Regency and dismissed Legendary’s cross-claims. We affirm. First is background. The deal was for about $2 million of concrete work for a new 71-unit apartment building. After Legendary quit, Regency got ANM Construction to finish the concrete job. Regency and Legendary fell to feuding about who owed whom what. The fight was about retention. Regency withheld money from Legendary, citing the retention clause. Before Legendary quit, Regency had paid Legendary about $1 million for its work. That sum was 90% of Legendary’s billings because the contract allowed Regency to withhold 10% of the amount due Legendary as security to ensure Legendary properly completed the job. Regency withheld from Legendary about $125,000, which we call the retention sum. Regency insisted on keeping that sum. Legendary demanded it. That is the main dispute. The trial court granted Regency’s motion for summary judgment, thus allowing Regency to keep the retention sum. Legendary appeals, saying the contract language entitles it to the sum. Our review of this summary judgment ruling is independent. (Conroy v. Regents of University of California (2009) 45 Cal.4th 1244, 1249.) Summary judgment is not disfavored, but rather a good way to test the merits without the burdens of trial. (Perry v. Bakewell Hawthorne, LLC (2017) 2

2 Cal.5th 536, 542.) The usual rules governing this procedure apply. (See, e.g., Code Civ. Proc., § 437c, subds. (c) & (p)(2).) This summary judgment appeal is purely a duel over contract interpretation, with no disputed issues of fact. The key sentence in the contract between Regency and Legendary specified “Ten percent (10%) of Subcontractor’s contract amount shall be withheld and will be released 35 days after completion of subcontractors work.” This 10% withholding created the retention sum. Felix Frankfurter reputedly said the three rules of statutory interpretation are to read the statute, read the statute, and read the statute. The same wise counsel applies to interpreting every text. So we read read read the contract, which we now describe. The contract is two pages, with a two page attachment. It begins by listing the date as “AUGUST/13/2015.” (The oddity of this usage will later assume significance.) The contract lists the lending bank and other preliminary information for the construction project. It then announces the agreement is between Regency “hereafter called ‘CONTRACTOR’” and Legendary “hereafter called ‘SUBCONTRACTOR’ . . . .” It specifies the concrete work for Legendary to perform. Next it states the total sum of $2,165,000 for the whole project is “TO BE PAID EACH MOTH [sic] ACCORDING TO THE PROGRESS OF THE WORK ACCORDING TO THE BANKS [sic] SCHEDULE.” We pause to emphasize that these preliminary lines of text contain odd stylistic usages and spelling and punctuation errors, some of which we have just noted. There also is a varying and apparently random pattern of capitalization, with some words in

3 all capitals, some words with initial capitals, and some words with no capital letters. These points too later become significant. Now comes the vital sentence: the retention clause. This clause is one of the primary recitals of the contract. It is one sentence long. It includes strikeout wording, a typed substitute insertion that replaces the strikeout words, and two sets of handwritten initials in the margin to show approval of the wording change. Together with the strikeout words, the original retention clause reads: “Ten percent (10%) of Subcontractor’s contract amount shall be withheld and will be released 30 days after final completion of the building.” The typed insertion for the strikeout is this: “35 days after completion of subcontractors [sic] work.” We note the drafters’ omission: there is no possessive apostrophe, either singular or plural. We count this as a simple error. “Subcontracting work” would seem to be the phrase to use if one wanted to avoid an apostrophe. Below we return to the significance, or rather the insignificance, of this error. The pair of handwritten initials is next to this insertion. So the final and complete retention clause — striking the strikeout and inserting the insertion — reads like this, with our italics: “Ten percent (10%) of Subcontractor’s contract amount shall be withheld and will be released 35 days after completion of subcontractors work.” The central dispute boils down to the meaning of “subcontractors” in this sentence. There are many more words in the contract, including a so- called Article 13, but the retention clause is the key. The other words are either consistent or irrelevant.

4 We recite that key language (with our italics) once more, for coherence and emphasis: “Ten percent (10%) of Subcontractor’s contract amount shall be withheld and will be released 35 days after completion of subcontractors work.” Legendary’s argument is not crystalline but amounts to this: the italicized word “subcontractors” must mean any subcontractor, not just Legendary. Legendary itself did not complete the concrete subcontracting work, true, but the replacement subcontractor ANM did, so once ANM completed the work, Legendary should get the 10% Regency withheld from the payments for the work Legendary did before it abandoned the project. To do otherwise, Legendary protests, is “baseless and inequitable.” In sum, then, Legendary says subcontractor should be interpreted to mean any concrete subcontractor, not Legendary in particular. Regency’s position, by contrast, is subcontractor’s work means Legendary’s work specifically. Legendary’s work was the entire concrete job the contract specified — providing all the labor, materials, and equipment and ensuring the result was up to code and free of liens — which Legendary never completed. Thus Legendary is entitled to no further sums. The fact ANM substituted in to save the day does not matter, according to the language of the contract, says Regency. Regency is right and so was the trial court’s result. As a matter of literal interpretation, Regency wins. The contract defines “SUBCONTRACTOR” as “Legendary Structures, Inc.” Legendary’s attempt to expand this definition to include ANM violates the contractual language. There are two wrinkles, but they are inconsequential. The drafters made two textual errors. We repeat the key sentence

5 again, now with no italics: “Ten percent (10%) of Subcontractor’s contract amount shall be withheld and will be released 35 days after completion of subcontractors work.” First, as already noted, the drafters omitted the possessive apostrophe from the inserted word “subcontractors.” Second, the drafters did not place either “Subcontractor’s” or “subcontractors” in all capitals, as appeared earlier in the document, thus creating a triple inconsistency in the use of capital letters in this word. Legendary’s lawyers do not make anything of these drafting flaws, and neither do we.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butler-Rupp v. Lourdeaux
65 Cal. Rptr. 3d 242 (California Court of Appeal, 2007)
Falkowski v. Imation Corp.
33 Cal. Rptr. 3d 724 (California Court of Appeal, 2005)
Conroy v. Regents of University of California
203 P.3d 1127 (California Supreme Court, 2009)
Perry v. Bakewell Hawthorne, LLC
389 P.3d 1 (California Supreme Court, 2017)
Olive v. Gen. Nutrition Ctrs., Inc.
242 Cal. Rptr. 3d 15 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Regency Midland Construction, Inc. v. Legendary Structures Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/regency-midland-construction-inc-v-legendary-structures-inc-calctapp-2019.