Regency Centre Dev. v. Constr. Dimensions, Unpublished Decision (9-25-2003)

CourtOhio Court of Appeals
DecidedSeptember 25, 2003
DocketNo. 81171.
StatusUnpublished

This text of Regency Centre Dev. v. Constr. Dimensions, Unpublished Decision (9-25-2003) (Regency Centre Dev. v. Constr. Dimensions, Unpublished Decision (9-25-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regency Centre Dev. v. Constr. Dimensions, Unpublished Decision (9-25-2003), (Ohio Ct. App. 2003).

Opinions

JOURNAL ENTRY AND OPINION.
{¶ 1} Defendant-appellant/cross-appellee David E. Bartrum ("Bartrum") and plaintiff-appellee/cross-appellant Regency Centre Development Company, Ltd. ("Regency") appeal/cross-appeal from the judgment and opinion entered by the Cuyahoga County Court of Common Pleas after trial. For the reasons that follow, we affirm the decision of the trial court.

{¶ 2} The facts adduced at trial establish that Regency entered into two agreements with CDI General Contractors, Construction Dimensions, Inc. ("CDI").1 The parties stipulated at trial that Regency paid CDI $957,808.26 in connection with the two agreements; paying fully the February 3, 2000 agreement and withholding the sum of $131,652.60 on the remaining agreement. Testimony establishes that Regency withheld the final payment after receiving two applications for payment containing unexecuted Waivers of Lien forms. Regency's General Manager contacted CDI after June 2, 2000 and was advised that CDI was out of business and had no money to pay subcontractors.

{¶ 3} Thereafter, Regency terminated the agreements by letter dated June 30, 2000, and pursuant to Article 7(f) found in both agreements which provides in pertinent part: "* * * Owner may terminate the Contract by giving fourteen (14) days prior written notice to the General Contractor * * * if the General Contractor fails to perform the Work properly, or fails to make prompt payments to Sub-Contractors or for materials or labor * * *. In such event, Owner may terminate the employment of General Contractor and take possession of all or part of the Contractor's materials, tools, equipment and appliances, and complete the Work by such means as the Owner and General Contractor agree and charge the actual cost (reasonable and without management fees) thereof to the General Contractor, crediting or debiting his account as the case may be when the Work under this General Contractor is fully completed and accepted."

{¶ 4} The record contains evidence of six mechanics liens filed by various subcontractors on Regency's property. Regency also submitted a worksheet detailing alleged amounts owed to subcontractors unpaid by CDI. CDI disputes at least some of the subcontractors' claims for payment.

{¶ 5} Months before CDI went out of business, defendant David E. Bartrum, a 50% owner of CDI, determined to retire. Bartrum had served at times relevant as a director and officer of the company. On or around January 31, 2000, Bartrum resigned. It is undisputed that Bartrum deferred his wages for the years 1996 through 1998. While testimony conflicts as to the amount of wages CDI actually owed Mr. Bartrum for this time period, CDI issued payment to Bartrum in the amount of $81,000 on February 2, 2000, through four separate checks: one check for each year of deferred wage (1996-1998), and a fourth check earmarked for federal payroll taxes related thereto.

{¶ 6} Bartrum testified that prior to taking payment, he first determined that it would not render CDI insolvent. There is evidence that CDI had approximately $300,000 on February 2, 2000. Bartrum's described business partner also testified that he believed the company's assets exceeded its liabilities at that time. Bartrum further testified that he conferred with the company accountant and the office manager prior to taking payment. By May 2000, Bartrum laid off the CDI workforce due to lack of work. By approximately June 2000 CDI was out of business.

{¶ 7} Initially, CDI classified the $81,000 as wages, but later re-categorized it as a distribution. Consequently, the federal government issued a refund to CDI in the amount of $34,601.01 in September 2000. At that time, Bartrum cashed the refund check made payable to CDI, used $14,068.52 to cover payroll taxes for himself and employees of North Coast Computers, and deposited the balance of $20,532.49 into his own personal account.

{¶ 8} On July 28, 2000, Regency commenced this action against CDI and Bartrum alleging breach of contract against CDI (Counts I and II), and violations of R.C. 1313.56-58, and R.C. 1336.01-12 against Bartrum (Counts III and IV). The two-day trial commenced on December 4, 2000. Thereafter, Regency filed a motion for default judgment against CDI on December 31, 2001, which Bartrum opposed and the trial court denied. On March 14, 2002, the trial court entered judgment in favor of Regency's claim of fraudulent transfer under R.C. 1336.04(A) as to Bartrum's negotiation of the treasury check issued to CDI in September 2000. In all other respects, the court entered judgment in favor of defendants CDI and Bartrum. Both Bartrum and Regency appeal from this judgment. For ease of discussion, we first address the cross-appeal of Regency and then those errors assigned by Bartrum.

{¶ 9} "CROSS ASSIGNMENT OF ERROR I. The trial court's judgment in favor of CDI against Regency is not sustained by the manifest weight of the evidence and is contrary to law."

{¶ 10} The standard of review provides that we may not reverse the trial court's decision as being against the manifest weight of the evidence if we find that the judgment is supported by some competent, credible evidence in the record. C.E. Morris Co. v. Foley ConstructionCo. (1978), 54 Ohio St.2d 279. We are likewise bound, in reviewing a bench trial, to presume that the findings of the trier of fact are correct. Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77,461 N.E.2d 1273. Regency contends that the evidence establishes that CDI breached the agreements by failing to pay the subcontractors. Regency refers to Articles 2, 4, 7(b) (f) of the agreements in support. The agreements do provide that Regency may terminate the agreements for CDI's failure to pay subcontractors (Article 7(f)) and charge the actual cost to CDI "crediting or debiting [its] account as the case may be."2 To that end, Regency was entitled to make direct payments to the unpaid subcontractors and to offset those amounts from the balance it owed CDI under the agreement. However, by the time of trial, the evidence established that Regency had $30,924 remaining from the balance it withheld under its agreement with CDI. In other words, Regency established that it paid out over $100,000 to subcontractors unpaid by CDI and that other subcontractors still remained unpaid at that point. It was further established that Regency successfully settled some of the subcontractor's claims for less than the full amount. Yet, in calculating its claimed damages against CDI, Regency assumed the validity of the full amounts allegedly owed to the remaining unpaid subcontractors.

{¶ 11} A party bringing a cause of action for breach of contract must demonstrate the following: (1) the existence of a binding contract or agreement; (2) that the non-breaching party performed its contractual obligations; (3) that the other party failed to fulfill its contractual obligations without legal excuse; and (4) that the non-breaching party suffered damages as a result of the breach. Garofalo v. Chicago TitleInsurance Co. (1995), 104 Ohio App.3d 95; McIntyre v. Thriftco, Inc. (May 17, 2001), Cuyahoga App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gustafson v. Buckley
121 N.E.2d 280 (Ohio Court of Appeals, 1953)
Gustafson v. Buckley
121 N.E.2d 280 (Ohio Court of Appeals, 1953)
Doner v. Snapp
649 N.E.2d 42 (Ohio Court of Appeals, 1994)
Streeton v. Roehm
81 N.E.2d 133 (Ohio Court of Appeals, 1948)
Garofalo v. Chicago Title Insurance
661 N.E.2d 218 (Ohio Court of Appeals, 1995)
Textron Financial Corp. v. Nationwide Mutual Insurance
684 N.E.2d 1261 (Ohio Court of Appeals, 1996)
Aristocrat Lakewood Nursing Home v. Mayne
729 N.E.2d 768 (Ohio Court of Appeals, 1999)
Sharp v. Shelby Mutual Ins.
239 N.E.2d 49 (Ohio Supreme Court, 1968)
Columbus Finance, Inc. v. Howard
327 N.E.2d 654 (Ohio Supreme Court, 1975)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
State ex rel. Wargo v. Price
381 N.E.2d 943 (Ohio Supreme Court, 1978)
Stockman v. Yanesh
428 N.E.2d 417 (Ohio Supreme Court, 1981)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
National Amusements, Inc. v. City of Springdale
558 N.E.2d 1178 (Ohio Supreme Court, 1990)
Grava v. Parkman Township
653 N.E.2d 226 (Ohio Supreme Court, 1995)
Davis v. Immediate Medical Services, Inc.
684 N.E.2d 292 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Regency Centre Dev. v. Constr. Dimensions, Unpublished Decision (9-25-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/regency-centre-dev-v-constr-dimensions-unpublished-decision-9-25-2003-ohioctapp-2003.