Regan v. Keyes

90 N.E. 847, 204 Mass. 294, 1910 Mass. LEXIS 915
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 7, 1910
StatusPublished
Cited by13 cases

This text of 90 N.E. 847 (Regan v. Keyes) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regan v. Keyes, 90 N.E. 847, 204 Mass. 294, 1910 Mass. LEXIS 915 (Mass. 1910).

Opinion

Losing, J.

We are of opinion that there has been a mistrial in this case.

Before October 14, 1901, the defendant in this action had tnade a general contract with the owner of a parcel of land on the corner of Lewis Street and Marginal Street in East Boston to erect on it a seven story warehouse in accordance with drawings and specifications by certain architects therein named.

By a contract dated October 14,1901, the plaintiff agreed to do all the work of excavation called for by the defendant’s contract with the landowner in accordance with the drawings and specifications of the architects as there set forth, which drawings and specifications were made part of the contract between the plaintiff and the defendant.

It is stated in the bill of exceptions that “ on or about November 30, 1902, and while the plaintiff was still carrying on the work of excavating, several 6 cave-ins ’ occurred and the side of the lot fronting on Lewis Street needed supporting in order to hold the sidewalk and to prevent injury to. the compressed air plant and the water and gas mains and sewer in the street.” We assume that November 30, 1901, not November 30,1902, is the date here intended. On December 20, 1901, it was agreed between the plaintiff and the defendant that the plaintiff should [299]*299stop work and that the defendant should complete the excavation at the plaintiff’s expense.

It is also stated in the bill of exceptions that “ at the date of the contract between the plaintiff and defendant,” there were in Lewis Street: (1) a compressing air plant used in the construction of the tunnel to East Boston under the harbor; (2) a large water main which supplied East Boston with its water supply; (3) a large trunk line sewer; and (4) gas mains. It is further stated in the bill of exceptions that the compressing air plant was a large one, consisting of buildings and machinery, and “ was of great weight and was liable to be seriously damaged by any ‘ cave-in ’ in the lot which was being excavated.”

The defendant’s evidence tended to show “ that it was impossible to carry on the work any further unless sheet piling was driven or a bulkhead was constructed immediately ” ; and “ that the engineer and architect in charge of the work, and also the engineers in charge of the tunnel construction, gave notice to the defendant that sheet piling should be driven or a bulkhead built at once, and threatened to secure an injunction against the prosecution of the defendant’s work unless the same was attended to; that the defendant requested the plaintiff to build the bulkhead, urging the immediate necessity therefor, and on the plaintiff’s refusal so to do, the defendant caused the bulkhead to be built at a cost of $457.” It appears from other parts of the bill of exceptions and from other papers before us that the cost of the bulkhead was $467, not $457.

The plaintiff testified that he understood that the bulkhead was put in “ so as to prevent, so that the delicate air compressing machinery would not be jarred, that furnished the air for the tunnel under the river, and if that should be jarred a large number of men would be in danger.”

At the trial the defendant asked for a ruling “ that the defendant should be allowed the cost of building the bulkhead on the Lewis Street front if the same was necessary to protect the street or sidewalk and prevent them from falling in, or if the same was necessary to protect the water mains or sewers or tunnel or compressed air plant in the street, or if the same was necessary in order to comply with the provisions contained in the specifications accompanying the contract between the [300]*300defendant Keyes and the National Dock and Warehouse Company.”

The presiding judge told the jury that the right of lateral support which one landowner owes to another is the support of the land in its natural condition, and that in the case at bar it was the plaintiff’s duty to take all reasonable and proper precautions to prevent injury to other people’s land or to the street in front of his lot.

At the close of the charge the learned counsel for the defendant took an exception to that portion of the charge which dealt with the duty of holding up the adjoining land without structures on it, and asked the judge to rule “that everything in that street in the way of work, tunnel, water main, should be held up, and that Keyes or Began was under a liability to hold those things in place, and, if the necessity of a bulkhead was reasonable in view of what was in the street in the way of public improvements, public necessities, he was obliged to hold them up by a bulkhead if a bulkhead was necessary.” This was refused and an exception was taken. An exception was also taken to the judge’s refusal to give the ruling asked for.

The jury found for the plaintiff “in the sum of $623.80, with interest at six per cent from September 1, 1902, amounting to $238.60 ; total verdict $862.40.”

There is a preliminary question which must be disposed of.

A special question was submitted to the jury, namely : “ What expense, if any, for the bulkhead does the jury include in their verdict?” The record as to this is: “The jury answers: $467.oo/loo.”

^ The plaintiff has contended that since the only way in which the expense of the bulkhead could be included in the verdict was by deducting the expense of it from the sum otherwise found by the jury to be due to the plaintiff, the answer to this question must be taken to mean that the jury did deduct $467 from the sum otherwise found by them to be'due the plaintiff. If the cost of the bulkhead was in fact deducted from the sum otherwise due the plaintiff, the defendant cannot now complain that the charge of the presiding judge on that point was incorrect. And the plaintiff has insisted upon that point.

While it is hard to give any other meaning (than that con[301]*301tended for by the plaintiff) to the question and answer if they are examined critically, yet the question was a somewhat blind one to a jury, and an examination of the matters in dispute has convinced us that this case ought not to be disposed of on that ground. The plaintiff’s demand was for the contract price, $1,850 plus three extras, to wit: (1) Sand, amounting to $182.70 (under count 4) ; (2) back filling behind the bulkhead $76.63, and teams for hauling snow and ice (under count 6), amounting to $106.63; and (3) extra expense of hauling the earth excavated because he was not given the use of railroad tracks, $361.80, making a total of $2,501.13. The plaintiff allowed the defendant (1) a payment of $710, and (2) for completing the work $446.25, a total of $1,156.25, making his net claim $1,344.88. The auditor (1) allowed the defendant $38.25 more for completing the work than the plaintiff gave him credit for; (2) charged the plaintiff with $223.06 for part of the expense of erecting a derrick of which the plaintiff by agreement was to have the use in part; and (3) disallowed the $361.80 claimed by the plaintiff. These three items amounted to $623.11; de- ’ ducting that from $1,344.88 claimed by the plaintiff we have the amount allowed by the auditor $721.77. These were the items in dispute. We have been unable to persuade ourselves that the jury in finding a verdict for $623.80 deducted from the sum otherwise found to be due to the plaintiff $467 for the bulkhead.

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vappi & Co. Inc. v. Sullivan
120 N.E.2d 203 (Massachusetts Supreme Judicial Court, 1954)
P. A. Dolan Co. v. P. S. Thorsen Co.
86 N.E.2d 652 (Massachusetts Supreme Judicial Court, 1949)
Corcoran v. S. S. Kresge Co.
47 N.E.2d 257 (Massachusetts Supreme Judicial Court, 1943)
Leondires v. Pike
7 Mass. App. Div. 321 (Mass. Dist. Ct., App. Div., 1942)
Finnegan v. Checker Taxi Co.
14 N.E.2d 127 (Massachusetts Supreme Judicial Court, 1938)
Henshaw v. Brown
2 Mass. App. Div. 361 (Mass. Dist. Ct., App. Div., 1937)
Triulzi v. Costa
4 N.E.2d 617 (Massachusetts Supreme Judicial Court, 1936)
Gill v. Stretton
1 Mass. App. Div. 408 (Mass. Dist. Ct., App. Div., 1936)
Gallagher v. Wheeler
198 N.E. 891 (Massachusetts Supreme Judicial Court, 1935)
Eaton v. Walker
244 Mass. 23 (Massachusetts Supreme Judicial Court, 1923)
Nunn v. Brillhart
230 S.W. 862 (Court of Appeals of Texas, 1921)
Hickman v. Wellauer
171 N.W. 635 (Wisconsin Supreme Court, 1919)
Ulland v. Foss-Schneider Brew. Co.
28 Ohio C.C. Dec. 673 (Ohio Court of Appeals, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
90 N.E. 847, 204 Mass. 294, 1910 Mass. LEXIS 915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regan-v-keyes-mass-1910.