This text of 80 S.W.2d 61 (Refunding Board of Arkansas v. Bailey) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Refunding Board of Arkansas v. Bailey, 80 S.W.2d 61, 190 Ark. 558, 1935 Ark. LEXIS 90 (Ark. 1935).

Opinion

Mehaffy, J.

The appellee, H. A. Bailey, a citizen, resident and taxpayer, brought this suit against the appellant, asking that the appellant be permanently restrained and enjoined from issuing any greater amount of refunding certificates to Street Improvement District No., 2 of Booneville, Arkansas, than $75,652.78.

The appellant states: 1 ‘ The question involved in this case is the amount of refunding certificates to which Street Improvement District No. 2 of Booneville, Arkansas, is entitled under Aj> 11 and 12 of act 11 of the Acts of 1934.” Both parties, in fact, agree that this is the only issue to be determined, by this court.

The complaint alleged that §§ 11 and 12 of act 11 of 1934 provide for the issuance' of refunding certificates of indebtedness to municipalities and street improvement districts in an amount equal to the outstanding and unpaid certificates under act No. 8 of 1928 and Nos. 85 and 248 of the Acts of 1931, which were issued to street improvement districts in cities and towns for.constructing continuations of State highways through cities and towns. It is alleged that on November 21, 1934, the Refunding Board passed a resolution respecting the issuance of refunding obligations in lieu of certificates of indebtedness. The resolution is made a part of the complaint. Improvement District No. 2 of Booneville, Arkansas, was organized for the sole purpose of improving streets which are continuations of State highways through the city of '.Booneville. Said improvement district issued bonds in the principal sum of $98,500, for which the district actually received in cash the sum of $89,920.65. The district proceeded to pave said streets under the supervision of the Highway Commission at a cost of $85,317.87, the improvement being completed in 1931. On January 26, 1931, the State Highway Commission issued to said improvement district, under act 8 of 1928, a certificate in the sum of $29,665 with interest at 4% pei’ centum from January 1, 1930. The Highway Commission decided that it would pay only for one-half the cost of a slab of concrete 36 feet wide through the municipality, regardless of the width of such concrete road through the municipality, and it refused to-participate in the cost of curbing and turnouts. The road through Booneville for which said certificates was issued, through the business section of the town, is more than 36 feet in width, and it has curbing throughout the entire length, except at street intersections, where turnouts were constructed. The turnouts are wholly on the street, which is a continuation of the State highway through said municipality, but said turnouts are built at right angle to the main slab, constituting the State highway, for the purpose of permitting traffic on intersecting streets to drive upon the concrete slab. Said turnouts at said intersections occupy that portion of the street which would be a continuation of the sidewalks paralleling the street that is a continuation of the State highway.

On August 1, 1932, the Highway 'Commission issued to said improvement district certificate No. 59 under act 248 of 1931 in the sum of $109,730.69, of which amount $67,823 was principal and $41,907.69 was interest. The certificate for $29,665 principal under said act No. 8 and $67,823 principal under act 248 make a total principal of $97,488 of certificates issued to said improvement district. The State has paid $4,488 of the principal sum, leaving a balance due of $93,000 principal and interest thereon to January 1, 1934, of $6,599.18, as certified to the Refunding Board by the director of the Highway Commission under said act No. 11.

It is alleged that the amount paid the contractor for improving said streets was $78,068.11; that the laboratory, engineering and attorney’s fees and other necessary and proper costs amount to $7,249.76, making a total of $85,319.87 for the construction o'f said State highway. It is also alleged that only 93.935 per cent, of the total area of the pavement by said district constitutes a continuance of said highway, because of the fact that at street intersections turnouts were built to the line of intersecting streets which were never, and are not now, State highways. The pavement upon the said turnouts and curb constitute 6.065 per cent, of the total area of the pavement by said improvement district No. 2. The cost of said improvement district No. 2 of Booneville, Arkansas, totals $93,000 of principal of certificates of indebtedness, on which there is interest due up to January 1, 1934, of $6,599.18, as certified to the Refunding Board. It is alleged that the Refunding 'Board is about 10 issue refunding certificates under the provisions of act 11 for the entire amount of principal of the outstanding certificates of indebtedness in the sum of $99,599.18. It is alleged that the Refunding Board does not have authority to issue certificates for any greater amount than the cost to the district, which is alleged to be $75,652.78. The refunding certificates about to be issued are general obligations of the State of Arkansas, and are negotiable and payable out of the general State highway fund, raised by taxation on motor vehicles, and asking that the board be restrained from issuing refunding certificates in excess of $75,652.78.

Appellants filed a demurrer which stated that the complaint does not state facts sufficient to entitle the plaintiff to the relief prayed for, or any relief whatsoever. The court overruled the demurrer, the appellant refused to plead further, elected to stand upon its demurrer, and the court thereupon granted the relief prayed for. The case is here on appeal.

Counsel have discussed at length the statutes providing for paying part of the cost of constructing highways through municipalities, beginning with act 184 of the Acts of 1927. Several acts were passed subsequent to the passage of this act. We have carefully considered them in connection with act 11 of 1934. The primary rule of construction of statutes is to ascertain and give effect to the intent of the law-makers.

Section 11 of act 11 of 1934 reads as follows: “In instances where municipalities or street improvement districts have improved streets through cities and towns, which streets are continuations of State highways, and said municipalities or districts were given aid or are entitled to aid by the issuance of certificates of indebtedness under act No. 248 of 1931, it shall be the duty of the State Highway Commission to ascertain and report to the Refunding Board by municipalities or districts the amount of said certificates, together with the interest unpaid thereon to January 1, 3934, and the amount of aid to which any of said municipalities or districts may be entitled in instances where certificates have not been issued to them which represents the actual cost of improving tlie streets which are not the actual continuation of a State highway. Any municipality or street improvement district entitled to aid under said act 248 for which no certificates have been issued shall apply to the State T-P e:hway Commission for aid within sixty days from the effective date of this act. or thereafter be forever barred from the benefits hereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No.
Arkansas Attorney General Reports, 1986
Cook v. Bevill
440 S.W.2d 570 (Supreme Court of Arkansas, 1969)
City of Little Rock v. Arkansas Corp. Commission
189 S.W.2d 382 (Supreme Court of Arkansas, 1945)
Barnsdall Refining Corp. v. Ford, Comm'r Revenues
109 S.W.2d 151 (Supreme Court of Arkansas, 1937)
Paving Improvement District No. 51 v. Refunding Board
88 S.W.2d 50 (Supreme Court of Arkansas, 1935)
Ledbetter v. Hall
87 S.W.2d 996 (Supreme Court of Arkansas, 1935)
Smith v. Refunding Board of Arkansas
83 S.W.2d 76 (Supreme Court of Arkansas, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
80 S.W.2d 61, 190 Ark. 558, 1935 Ark. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/refunding-board-of-arkansas-v-bailey-ark-1935.