Refrigeration & Air Conditioning Institute v. Rine

75 N.E.2d 473, 80 Ohio App. 317, 36 Ohio Op. 19, 1946 Ohio App. LEXIS 520
CourtOhio Court of Appeals
DecidedNovember 7, 1946
Docket462
StatusPublished
Cited by11 cases

This text of 75 N.E.2d 473 (Refrigeration & Air Conditioning Institute v. Rine) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Refrigeration & Air Conditioning Institute v. Rine, 75 N.E.2d 473, 80 Ohio App. 317, 36 Ohio Op. 19, 1946 Ohio App. LEXIS 520 (Ohio Ct. App. 1946).

Opinion

*318 Sherick, P. J.

-This cause was first tried before a justice of the peace and plaintiff secured a judgment for $154. Defendant appealed to the Court of Common Pleas wherein the cause was retried without the intervention of a jury, resulting in a judgment for plaintiff for $5. From that judgment plaintiff appeals to this court on questions of law. >

The single question presented concerns the proper measure of damages recoverable by the seller upon the buyer’s breach of a contract partially performed. Are the damages measured by the contract price or the actual value of the services rendered and goods furnished, plus anticipated profits if they can be established with sufficient certainty?

Plaintiff’s petition alleges, in substance, a written contract for the furnishing of a correspondence course in refrigeration and air conditioning, the total cost of which was $172. Plaintiff -pleads part performance and its willingness to complete its contractual obligations. It avers that defendant breached the agreement after receiving some 39 lessons and refused to continue the course of study. It recites payment of $23. It prays for judgment in the sum of $149, the- balance of the contract price.

The answer denies generally and sets forth two affirmative defenses, i. e., failure of consideration and fraud in the inducement.

The reply is a general denial.

The Court of Common Pleas found that plaintiff had proved its contract; that defendant 'had failed to establish the truth of his two defenses; that plaintiff was entitled to recover; and that, inasmuch as plaintiff had failed to prove any actual damages, it could recover ño more than nominal damages, to wit, $5. Judgment was entered accordingly. Such, findings are definitely substantiated by the record.

The contract provides, among other things, that, *319 upon successful completion of the course of study and full payment of tuition, plaintiff will furnish an additional two weeks of intensive shop' and laboratory training at its institute in Chicago; and that “here the student will work under actual shop conditions on standard equipment furnished by the industry, unde r the direction of competent engineers and instructors.” Plaintiff further covenanted to furnish defendant, Rine, with bus transportation to and from Chicago. It promised him assistance in procuring employment in the field covered by the course of study. It further appears from correspondence in evidence that defendant had been given a student number, RA 11316. Of those matters we shall hereinafter have something further to say.

The measure of damages" in this type of cases is an open question in Ohio. We therefore turn to other jurisdictions for enlightenment. From the case of International Correspondence School, Inc., v. Crabtree, 162 Tenn., 70, 34 S. W. (2d), 447, 78 A. L. R., 330, and the annotation thereto in A. L. R., it appears that three schools of thought have developed. In Massachusetts the rule is that the school may recover the full contract price. In Nebraska it is held that the school can recover the full contract price, unless the student can lessen his liability by showing savings in the school’s expenses, brought about by its not having to perform the contract on its part. The third rule, adhered to in Michigan, is that a school can recover only for actual loss, the burden is upon the school to make proof thereof and failure to do so limits it to recovery of nothing more than nominal damages. We refrain from citation of authorities. They may be procured from the case and annotation hereinbefore referred to.

What ought to be the Ohio rule? To determine this question, we must examine this state’s theory of recov *320 ery of damages in breach of contract eases where the contract has been partially performed. It is generally accepted that he who seeks damages for a breach of contract bears the burden of proof, unless a statute otherwise dictates or knowledge is peculiarly within the possession of the other contracting party who must, in such case, bear the burden of producing it. Ohio has step by stqp veered to the rule that only actual damages are recoverable, unless the law permits a recovery of punitive damages. In practically all kinds of contract violations, Ohio has sought to compensate the injured party, not to reward him. Our courts have frowned upon the award of punitive damages, unless they are provided for by law. The courts have also forbidden juries to speculate, and have instructed them to award only such damages as will make the aggrieved party whole, that is, save him from pecuniary loss.

The plaintiff in the present action is selling service as well as the lessons which it furnishes and later grades. It goes even further than this and agrees that, when the course is completed and paid for, plaintiff will advance money for bus transportation and will give the student two weeks of shop instruction in a standard, equipped shop under experienced instructors. Without doubt those items are figured in arriving at the total contract price. They represent an actual anticipated cash outlay by the institute. The breach saved such contemplated expenditures. The contract figure is indivisible, and, unless plaintiff discloses the cost thereof, application of the Massachusetts rule, will' compensate it for a loss which it has not and never will sustain.

The defendant’s student number, 11316, reasonably suggests that the institute has or has had a goodly number of students taking its refrigeration and air conditioning course. At the contract price this would *321 represent a tidy sum of nearby two million dollars, if tbe full tuition sum were recoverable in every case. It is common knowledge that many contract to take correspondence school courses and that relatively few complete them. The record shows that three or four students, who were all the students contracting with plaintiff at the time in the Mt. Vernon area, have discontinued study. After course expenditures, • there would remain quite an appreciable sum in each student’s case. Again, it is a matter of common knowledge that the -original composition of correspondence school lessons and their printing in bulk are not matters of great expense; and when postage, correction of lessons, secretarial service, stationery and school administration costs are proportioned and added, the total cannot represent any considerable portion of the tuition fee of an individual student. Such facts and figures are within the exclusive knowledge of the school. Why ought it not be required to produce them?

In 13 Ohio Jurisprudence, 93, Section 27, it is stated, as to damages for breach of a contract partially performed :

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hostetler v. Cent. Farm & Garden, Inc.
2012 Ohio 507 (Ohio Court of Appeals, 2012)
JKL Components Corp. v. Insul-Reps, Inc.
596 N.E.2d 945 (Indiana Court of Appeals, 1992)
Bennett v. Fun & Fitness of Silver Hill, Inc.
434 A.2d 476 (District of Columbia Court of Appeals, 1981)
Tibbs v. National Homes Construction Corp.
369 N.E.2d 1218 (Ohio Court of Appeals, 1977)
State v. Crutcher
174 N.W.2d 449 (Supreme Court of Iowa, 1970)
Burnett v. Sebel
150 N.E.2d 304 (Ohio Court of Appeals, 1958)
Green v. Nelson
232 P.2d 776 (Utah Supreme Court, 1951)
Alexander Hamilton Institute, Inc. v. Jubelt
102 N.E.2d 741 (Ohio Court of Appeals, 1951)
Jones v. Middletown
96 N.E.2d 799 (Butler County Court of Common Pleas, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
75 N.E.2d 473, 80 Ohio App. 317, 36 Ohio Op. 19, 1946 Ohio App. LEXIS 520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/refrigeration-air-conditioning-institute-v-rine-ohioctapp-1946.