Rees v. Panhandle Eastern Pipe Line Co.

452 N.E.2d 405, 1983 Ind. App. LEXIS 3257
CourtIndiana Court of Appeals
DecidedAugust 15, 1983
Docket4-682A152
StatusPublished
Cited by9 cases

This text of 452 N.E.2d 405 (Rees v. Panhandle Eastern Pipe Line Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rees v. Panhandle Eastern Pipe Line Co., 452 N.E.2d 405, 1983 Ind. App. LEXIS 3257 (Ind. Ct. App. 1983).

Opinion

STATON, Judge.

The trial court awarded a default judgment to Panhandle Eastern Pipe Line Co. (Panhandle). It permanently enjoined Leland and Fannie Rees from interfering with Panhandle's easement rights to maintain its pipelines which traverse the Reeses' property. On appeal, the Reeses raise several issues surrounding their general contention that the grant of a permanent injunction was erroneous because the trial court did not decide whether Panhandle's actions constituted inverse condemnation:

(1) Did the trial court abuse its discretion by denying the Reese's motion for relief from judgment when they failed to appear at trial despite their actual notice of the trial date?
(2) Did the trial court err in determining that the easements were intended to be 66 feet wide?
(8) Did the trial court err in determining that the Reeses were not entitled to damages?

Affirmed. 1

Prior to this dispute, Panhandle had acquired easement rights to operate four natural gas pipelines over land owned by the Reeses. These easements allowed Panhandle to maintain the pipelines for the detection of gas leaks. Nevertheless, in 1975 Leland interfered with Panhandle's preparation to clear brush and trees from the pipelines. In early 1976, Panhandle obtained a preliminary injunction against the Reeses prohibiting further interference.

After unsuccessfully appealing the grant of the preliminary injunction, the Reeses filed a counterclaim for inverse condemnation. The trial court dismissed the counterclaim because the Reeses had not asked the court's permission to file it. On June 19, 1980, the trial court gave the Reeses fourteen days to file their counterclaim. Again, the Reeses unsuccessfully moved to file a counterclaim.

The Reeses failed to appear at trial on November 5, 1980 even though they had actual notice of the trial date. After hearing evidence from Panhandle, the trial court entered a default judgment permanently enjoining the Reeses from interfering with Panhandle's easement rights to maintain its pipelines, In addition, the trial court interpreted the reasonable width of each easement to be 66 feet.

Pursuant to Ind. Rules of Procedure, Trial Rule 60(B), the Reeses filed a motion to have the default judgment set aside, which *408 the trial court denied. The trial court also denied the Reeses' motion to correct errors which requested damages for inverse condemnation. -

I. (a).

Compulsory Counterclaims

The Reeses contend that the trial court erroneously denied their request to file a counterclaim. They assert that the trial court was required to allow them to file their counterclaim because it was a compulsory counterclaim under TR. 183(A) Although we agree with the Reeses that the trial court erred by not allowing some of their claims as compulsory counterclaims, the error is harmless because the Reeses inexcusably failed to appear and argue their claims at trial.

A counterclaim is a claim by a defendant which would defeat or diminish the plaintiff's claim. Tron v. Yohn (1896), 145 Ind. 272, 43 N.E. 437. Pursuant to TR. 18, counterclaims are either compulsory (required to be made) or permissive (at the option of the defendant or the court). Only the compulsory counterclaim is required to be filed because it is a matter which, if brought in a former controversy, would preclude repetitious litigation in a subsequent controversy. Middlekamp v. Hanewich (1977), 178 Ind.App. 571, 586, 364 N.E.2d 1024, 1034.

TR. 18(A) sets forth a three part test to determine whether a counterclaim is compulsory:

"Trial Rule 18

COUNTERCLAIM AND CROSS-CLAIM

"(A) Compulsory counterclaims. A pleading shall state as a counterclaim (1) any claim which at the time of serving the pleading the pleader has against any opposing party, (2) if it arises out of the transaction or occurrence that is the subject-matter of the opposing party's claim (3) and does not require for its adjudication the presence of third parties of whom the court cannot acquire jurisdiction...." (Emphasis added.)

Under the first part of the test, we must determine whether the Reeses' claim for damages was mature at the time they served their answer to Panhandle's complaint. Middlekamp, supra, 364 N.E.2d at 1035. The maturity of the Reeses' claims ranges from 1959 to 1978. Only the claims which had matured before they filed their first answer meet the first part of the test for compulsory counterclaims. The claims which matured after the Reeses filed their first answer are permissive counterclaims under TR. 18(BE). Whipple v. Dickey (1980), Ind.App., 401 N.E.2d 787, 792.

According to TR. 18(E), such counterclaims may be filed only with the trial court's permission:

"(E) Counterclaim maturing or acquired after pleading. A claim which either matured or was acquired by the pleader after serving his pleading may, with the permission of the court, be presented as a counterclaim by supplemental pleading. ..."

From a reading of the record, we cannot say that the trial court abused its discretion in denying the permissive counterclaims which had matured after the Reeses filed their first answer.

The trial court was required to allow those counterclaims which were mature when the Reeses filed their first answer only if they meet the second and third parts of the TR. 18(A) test for compulsory counterclaims. The second part of the test is whether the claims "arose out of the transaction or occurrence that is the subject-matter of the opposing parties claim...." TR. 18(A). Transaction has been defined as "a series of many occurrences which are logically related." Moore v. N.Y. Cotton Exchange (1926), 270 U.S. 593, 610, 46 S.Ct. 367, 371, 70 L.Ed. 750, 757, Middlekamp, supra, 364 N.E.2d at 1035. Therefore, if the claims, which were mature at the time the Reeses filed their first answer, are logically related to Panhandle's complaint for injunetion, the claims have met the second part of the test of compulsory counterclaims.

Two of the Reeses' three claims which were mature when they filed their *409 first answer meet the second part of the test. First, the Reeses claim that Panhandle's award of 66 feet wide easements exceeds the original easement grant entitling them to compensation. Second, they claim that the construction of Panhandle's fourth pipeline caused exposure and washout of two hills. Third, the Reeses claim damages from Panhandle's removal of their trees, shrubs, and raspberries along its easements.

The first and third claims are logically related to Panhandle's claim to maintain its pipelines because they concern to what extent Panhandle may maintain its pipelines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bacompt Systems, Inc. v. Ashworth
752 N.E.2d 140 (Indiana Court of Appeals, 2001)
Panhandle Eastern Pipe Line Co. v. Tishner
699 N.E.2d 731 (Indiana Court of Appeals, 1998)
Walsman v. McCullough
492 N.E.2d 1093 (Indiana Court of Appeals, 1986)
Crider v. State Exchange Bank of Culver
487 N.E.2d 1345 (Indiana Court of Appeals, 1986)
Metropolitan Real Estate Corp. v. Frey
480 N.E.2d 267 (Indiana Court of Appeals, 1985)
Indiana & Michigan Electric Co. v. Terre Haute Industries, Inc.
467 N.E.2d 37 (Indiana Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
452 N.E.2d 405, 1983 Ind. App. LEXIS 3257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rees-v-panhandle-eastern-pipe-line-co-indctapp-1983.