Rees v. BP America Production Co.

2009 OK CIV APP 37, 211 P.3d 910, 2008 Okla. Civ. App. LEXIS 125, 2008 WL 6085442
CourtCourt of Civil Appeals of Oklahoma
DecidedFebruary 22, 2008
Docket105,012. Released for Publication by Order of the Court of Civil Appeals of Oklahoma, Division No. 1
StatusPublished
Cited by1 cases

This text of 2009 OK CIV APP 37 (Rees v. BP America Production Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rees v. BP America Production Co., 2009 OK CIV APP 37, 211 P.3d 910, 2008 Okla. Civ. App. LEXIS 125, 2008 WL 6085442 (Okla. Ct. App. 2008).

Opinion

CAROL M. HANSEN, Judge.

11 Plaintiff/Appellant, Paul Rees, seeks review of the trial court's order dismissing Rees' class action claim against Defendant/Appellee, BP America Production Co. (BP), and allowing Rees' individual action to proceed. We affirm because Rees' class action claim is precluded by the denial of class certification in a previous case in which Rees was an unnamed member of the proposed class.

1 2 Rees sued BP, alleging he owned interests entitling him to receive royalty payments from BP on gas BP produced from properties located in LeFlore County and included in the Red Oak-Norris Field. He alleged BP underpaid royalties by wrongfully charging marketing fees and costs of making the gas marketable, including costs for gathering, treatment, compression, and dehydration, to royalty owners. Rees sought to bring the case as a class action on behalf of himself and "all similarly situated persons and entities who have received royalty payments from [BP] on Gas Substances produced from the Red Oak-Norris Field."

13 BP moved to dismiss based on prior actions pending or in the alternative to stay the case or transfer venue to Pittsburg County. Two other cases were pending against BP for underpaid royalties: Watts v. Amoco Production Company (now BP), Case No. C-2001-78 filed in Pittsburg County, and Chockley v. BP America Production Company, Case No. CJ-2002-84 filed in Beaver County. In Watts, the plaintiffs sought to represent a class consisting of "royalty owners in oil and gas drilling and spacing units established by the Oklahoma Corporation *911 Commission in Pittsburg, Latimer, Haskell, Leflore, Coal, Sequoyah, and Atoka Counties, Oklahoma to which [BP] distributes royalty, and for which [BP] has sold production to its affiliates and/or deducted post-production costs or marketing-related fees from the royalties paid." In Chockley, the plaintiffs defined the class as those who "own or have owned oil, gas and other minerals underlying tracts of land in Oklahoma which are subject to various oil and gas leases and/or pooling order of the Oklahoma Corporation Commission pursuant to which BP is/was a working. interest owner in oil and gas wells, and /or operated oil and gas wells within units which encompass such minerals."

{4 In Watts, the trial court denied class certification and the plaintiffs appealed. Over Rees' objection, the trial court in this case granted a stay pending completion of the Watts appeal. In an unpublished opinion in Watts v. Amoco Production Co., Case No. 90,404 (Sept. 14, 2004), the Oklahoma Court of Civil Appeals affirmed denial of class certification, stating,

We think it sufficient to note that (1) gas produced by the wells in question was marketable at the wellhead, (2) the costs incurred between the wellhead and the pipeline tailgate to prepare the gas for introduction into the pipeline are post-production costs, and (8) the propriety of deducting those costs involves an individualized inquiry of the factors discussed in Mittelstaedt v. Santa Fe Minerals, Inc., 1998 OK 7, 954 P.2d 1203, making this issue unsuitable for class action disposition. The need for individualized inquiry is further evident by the need to examine each of thousands of sales in deciding whether [BP] received the best market price for the gas vis-&-vis the costs incurred to prepare the gas for introduction into the pipeline.

The Oklahoma Supreme Court denied certio-rari.

1 5 After mandate issued in Watts, the trial court in this case granted BP's motion to dismiss Rees' class action claim. Citing In re Bridgestone/Firestone, Inc., Tires Products Liability Litigation, 333 F.3d 763 (7th Cir.2003), the trial court applied the principle of issue preclusion in ruling Rees, as an unnamed member of the proposed class in Watts, was bound by the decision in Watis denying class action certification. Rees appeals from this interlocutory order. 1

T6 Concurrently with filing its appellate answer brief, BP moved to dismiss Rees' appeal for lack of standing, asserting it had determined Rees did not own a royalty interest in the Red Oak-Norris Field and therefore was not a member of the proposed class. Rees' petition alleges he owns such an interest. We must presume this allegation is true for the purpose of reviewing a ruling on a motion to dismiss. Bettis v. Brown, 1991 OK CIV APP 98, 819 P.2d 1381, 1382. Accordingly, BP's motion to dismiss this appeal is denied.

T7 Rees contends the trial court erred in applying issue preclusion to an unnamed member of a class denied certification. He argues (1) an order denying class certification lacks the finality necessary to invoke issue preclusion, (2) an unnamed member of a proposed class denied certification is not a party to that litigation, and (8) the decision in Watts was not a decision on the same issues because Rees' claims are only a subset of those in Watts and Chockley. Rees also contends the trial court's preclusion of his class claims violates the due process rights of the absent members of the proposed Waits class, the trial court did not consider the ramifications of narrower classes, and its holding undermines public policy considerations by severely limiting the availability of the class action procedure.

1 8 In re Bridgestone/Firestone, Inc., Tires Products Liability IAitigation (Firestone), 333 F.3d 763 (7th Cir.2003), was sqccessiVe to the Seventh Cireuit Court of Appeal's previous decision that a federal district court abused its discretion in certifying nationwide classes covering multiple models of Ford vehicles and Firestone tires sold between 1990 *912 and 2001. After plaintiffs began filing class suits in various state courts, Ford and Firestone asked the federal district court to enforce the Seventh Circuit's decision by enjoining all class actions against them. The district court denied the motion and Ford and Firestone appealed.

T 9 The Court stated its determination that a nationwide class action was an unproductive investment of judicial time did not forbid a state tribunal from making the effort, and its opinion contemplated that state courts would certify narrower classes. However, it recognized the filing of multiple suits suggested the plaintiffs' lawyers had adopted a strategy of filing in as many courts as necessary until a nationwide class was certified, thereby rendering insignificant all the no-certification decisions of other courts. The Court then applied the principle of issue preclusion, stating its decision that no nationwide class was tenable, although not a final judgment, was sufficiently firm to be accorded preclusive effect. It reasoned that "unnamed class members have the status of parties for many- purposes and are bound by the decision whether or not the court otherwise would have had personal jurisdiction over them." Id. at 768. The Court conditioned the binding effect of a decision on absent class members upon the named representatives and their lawyers having furnished adequate representation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. US Bank National Association
260 P.3d 711 (Court of Appeals of Oregon, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2009 OK CIV APP 37, 211 P.3d 910, 2008 Okla. Civ. App. LEXIS 125, 2008 WL 6085442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rees-v-bp-america-production-co-oklacivapp-2008.