Reel Enterprises v. CITY OF LAW CROSSE

431 N.W.2d 743, 146 Wis. 2d 662, 1988 Wisc. App. LEXIS 801
CourtCourt of Appeals of Wisconsin
DecidedSeptember 29, 1988
Docket86-0746
StatusPublished
Cited by15 cases

This text of 431 N.W.2d 743 (Reel Enterprises v. CITY OF LAW CROSSE) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reel Enterprises v. CITY OF LAW CROSSE, 431 N.W.2d 743, 146 Wis. 2d 662, 1988 Wisc. App. LEXIS 801 (Wis. Ct. App. 1988).

Opinion

GARTZKE, P.J.

Reel Enterprises, its individual partners and Swanson Heavy Moving Company, Inc., appeal from a judgment dismissing their complaint for inverse condemnation against the City of La Crosse and the Department of Natural Resources. The theory of the complaint is that the DNR’s acts in pursuit of but before the adoption of a floodplain zoning ordinance for the city, pursuant to sec. 87.30, Stats., and *666 DNR’s other acts, "took” the plaintiffs’ properties for public use without compensation. 1

The circuit court concluded that since the zoning ordinance had not become legally effective, this suit had been prematurely commenced. It dismissed the complaint without prejudice to plaintiffs’ right to bring another suit if the ordinance became effective.

The dispositive issue is whether the complaint alleges acts by the city or the DNR which can be a temporary taking of property, requiring just compensation under sec. 32.10, Stats., and Wis. Const, art. I, sec. 13. We conclude that because all but one of the alleged acts are not legally enforceable restrictions on the use of any of the properties, none of those acts can be a taking. Because the complaint fails to allege that the remaining act deprived any of the plaintiffs of all or substantially all of the beneficial use of their properties, that act is not a taking. We therefore affirm the judgment dismissing the complaint.

The trial court properly treated defendants’ motion to dismiss as one for summary judgment. When defendants moved to dismiss the complaint, matters outside the pleadings were presented to and not excluded by the trial court. Under these circumstances the motion to dismiss must be treated as one for summary judgment. Sec. 802.06(3), Stats.

The only purpose of summary judgment methodology is to determine whether a genuine issue of material fact exists which requires a trial. If no factual issue exists and the moving party is entitled to judgment as a matter of law, then the trial court has *667 no discretion: it must grant the relief requested. Green Spring Farms v. Kersten, 136 Wis. 2d 304, 310, 401 N.W.2d 816, 820 (1987). The first step is to determine whether the complaint states a claim. If it does not, the methodology stops and the complaint must be dismissed.

As an appellate court, we apply the same methodology as the trial court. Appellate review is de novo. Wright v. Hasley, 86 Wis. 2d 572, 579, 273 N.W.2d 319, 322-23 (1979).

We read the complaint in light of pertinent floodplain legislation. If a municipality does not adopt a reasonable and effective floodplain zoning ordinance within one year after data adequate to formulate the ordinance is available, the DNR must determine the limits of a floodplain in the municipality and adopt an ordinance applicable to the municipality. 2 Sec. 87.30(l)(a), Stats. The floodplain determination and ordinance adopted by the DNR has the same effect as if adopted by the city, and the city must enforce the ordinance as its own. Sec. 87.30(l)(b). Anything placed on or maintained within the floodplain in violation of the ordinance is a public nuisance, and violators risk a fine of $50 for each day during which a violation exists. Sec. 87.30(2).

*668 The complaint alleges that the plaintiffs own lots in an industrial plat near the LaCrosse River. Reel Enterprises purchased the entire tract before 1980, retained some lots within it and conveyed others to Swanson Heavy Moving, Harold Swanson, Jr., and to persons not parties to this action. When Reel Enterprises bought the property, it was subject to a city floodplain zoning ordinance applicable to the La Crosse River and approved by DNR. That ordinance permitted the plaintiffs to develop the property as a commercial industrial park, and they obtained city permits to put fill materials and buildings on it.

On July 22, 1981 the DNR advised the city that DNR’s study of the La Crosse River floodplain indicated a need for the city to revise its ordinance. The city hired a consultant to make an independent study of the floodplain, and the DNR agreed not to adopt an ordinance for the city under sec. 87.30, Stats., until that study had been completed. In April 1982, the city revised its ordinance in accordance with the conclusions of its independent study.

In May 1982, the DNR disapproved the city’s revised ordinance and gave notice the next month that it would begin proceedings under sec. 87.30, Stats., to adopt a floodplain zoning ordinance for the city. That summer the DNR filed a series of lis pendens which effectively precluded the plaintiffs from developing or selling their properties.

The city brought an action to review DNR’s disapproval of the revised ordinance. On March 21, 1983 the circuit court reversed DNR’s decision disapproving the ordinance. DNR appealed, and the court of appeals reversed the decision of the circuit court and upheld DNR’s original disapproval of the ordi *669 nance. City of La Crosse v. DNR, 120 Wis. 2d 168, 353 N.W.2d 68 (Ct. App. 1984).

In April 1982 the city applied to DNR for a sanitary sewer extension in the plat. In May 1982 DNR disapproved the application because the extension would be within a floodway. The city and all but one of the plaintiffs brought a circuit court action challenging DNR’s decision, and on March 21, 1983 the court reversed DNR’s denial of the extension permit. 3

The complaint alleges that in the summer of 1982 the DNR refused to permit further deposits of fill materials on the property. The reason for the denial is not alleged, nor do plaintiffs allege they sought judicial relief.

In the fall of 1984 the DNR held a public hearing in La Crosse with respect to its imposition of a floodplain zoning ordinance on the city under sec. 87.30, Stats. In early 1985 the city brought an action to stay any further proceedings before the DNR. That action was dismissed.

The complaint continues that the DNR’s studies of the La Crosse River floodplain put all or much of plaintiffs’ properties within the floodway, and that the DNR intends to impose a floodplain zoning ordinance *670 on the city, putting all or most of plaintiffs’ property within the "floodway” designation. The ordinance and floodway designation will render the plaintiffs’ properties useless for all reasonable purposes.

The complaint further alleges that since at least July 22, 1981, plaintiffs properties have been "occupied and taken” by the city and DNR without just compensation. The "occupancy and taking” will continue as to all or a material part of their properties, depending on where DNR places its floodway line.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stelpflug v. Town Board, Town of Waukesha
2000 WI 81 (Wisconsin Supreme Court, 2000)
Eberle v. Dane County Board of Adjustment
595 N.W.2d 730 (Wisconsin Supreme Court, 1999)
State Ex Rel. Epping v. City of Neillsville Common Council
581 N.W.2d 548 (Court of Appeals of Wisconsin, 1998)
Zealy v. City of Waukesha
548 N.W.2d 528 (Wisconsin Supreme Court, 1996)
Zealy v. City of Waukesha
534 N.W.2d 917 (Court of Appeals of Wisconsin, 1995)
State Ex Rel. Madison Landfills, Inc. v. Dane County
515 N.W.2d 322 (Court of Appeals of Wisconsin, 1994)
Busse v. Dane County Regional Planning Commission
511 N.W.2d 356 (Court of Appeals of Wisconsin, 1993)
Old Tuckaway Associates Ltd. Partnership v. City of Greenfield
509 N.W.2d 323 (Court of Appeals of Wisconsin, 1993)
Busse v. City of Madison
503 N.W.2d 340 (Court of Appeals of Wisconsin, 1993)
J.J.G. v. L.J.
441 N.W.2d 273 (Court of Appeals of Wisconsin, 1989)
In Re Paternity of JLH
441 N.W.2d 273 (Court of Appeals of Wisconsin, 1989)

Cite This Page — Counsel Stack

Bluebook (online)