Reed, Wible & Brown, Inc. v. Mahogany Run Development Corp.

550 F. Supp. 1095
CourtDistrict Court, Virgin Islands
DecidedNovember 2, 1982
DocketCiv. 1982/168
StatusPublished
Cited by12 cases

This text of 550 F. Supp. 1095 (Reed, Wible & Brown, Inc. v. Mahogany Run Development Corp.) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed, Wible & Brown, Inc. v. Mahogany Run Development Corp., 550 F. Supp. 1095 (vid 1982).

Opinion

MEMORANDUM OPINION AND ORDER

O’BRIEN, District Judge.

This action for debt, declaratory relief and specific performance is before this Court on plaintiff’s motion for partial sum *1097 mary judgment and request to fix the scope of arbitration. Plaintiff and defendant Mahogany Run Development Corporation submitted memoranda, supporting affidavits and documents, and appeared before this Court for oral argument on September 22, 1982. For the reasons which follow this Court will grant plaintiff’s motion and direct the parties to submit to arbitration the issue of damages, if any, due for the late completion of the condominiums.

On December 4, 1980, defendant, Mahogany Run Development Corporation (hereinafter referred to as MRDC) entered into a construction contract with plaintiff, Reed, Wible and Brown, Inc. (hereinafter referred to as RWB) whereby RWB was to build five condominium units in Mahogany Run, a housing complex being developed by MRDC on St. Thomas. The construction was divided among several contractors and RWB was awarded the contract for sections of the project known as Phase IV-A and Phase IV-B.

The contract called for co-defendant Bank of America, which financed the project, to make “progress payments” to RWB as work on the project progressed; and to retain ten percent of total payments due RWB, to be paid out upon completion of the work. Bank of America presently holds $143,476.62, which includes both the ten percent “retainage” sum and the withheld progress payments. Bank of America asserts no claim to the funds, is merely a stakeholder in the dispute at bar, and remains willing to distribute the $143,476.62 as directed by this Court.

As the construction neared its conclusion, RWB and MRDC entered into negotiations to tie up loose ends regarding completion of the condominiums. A letter from RWB to MRDC dated January 28, 1982 was signed by both parties and set forth their understanding as to the remaining duties and rights under the construction contract. The agreement provided for: 1) MRDC’s payment of $66,000 to RWB for work previously billed to MRDC, 2) MRDC’s conveyance of plot # 142 of Mahogany Run upon final closing of Phase IV-B, and 3) payment to RWB of “retainage” and unpaid progress payments, due when the $66,000 is paid. 1 Correspondingly, the agreement provided that MRDC would draw up a “punch list” by February 7, 1982, specifying all items which remained to be completed by RWB. In a handwritten addendum, initialed by both parties, each further agreed to submit to arbitration any damages due MRDC arising from RWB’s late completion of the condominiums.

A second document entitled “Release and Waiver” was drawn up and executed by RWB on February 26, 1982. This two-page document, the source of the parties’ dispute, is a standard release form whereby RWB generally released and discharged all construction liens against the recently completed buildings. This document also contained an addendum, typed in by RWB on the bottom of page two of the release. The addendum reiterated some of the matters settled in the January 28th agreement: that MRDC will pay $66,000 (less any damages for late completion assessed by an arbitrator) to RWB on the closing of building # 322, and that MRDC will convey Plot* # 142 of Mahogany Run to Beth Meyers, as assignee of RWB, upon the final closing of Phase IV — B. The addendum further states:

Also, except for the warranties and guaranties provided for in the original contract for this release of 322 shall serve as a general release from GEC to MRDC including final punch list and from MRDC to GEC, pursuant to which each party waives, for now and forever hereinafter, any claims for any matters whatsoever arising from the construction for Phase IV-A and Phase IV-B.
Also, damages due to late completion, if any, will be assessed as per contract and in the event of disagreement as to completion date, Tom Brunt will arbitrate, and his decision will be final.

*1098 Plaintiff’s Memorandum in Support, Exhibit D.

This release was received by MRDC on February 26, 1982 whereupon it was initialed in the margin at the addendum by James Armour, President of MRDC. MRDC used the document on that same date to facilitate the closing on three condominium units in Building # 322 of Mahogany Run Condominiums.

Plaintiff, RWB, seeks partial summary judgment on the basis that the February 26, 1982 release represents the final agreement between RWB and MRDC, and seeks specific performance thereof. Defendant, MRDC counters that the February 26th document is not representative of the parties’ final agreement, that RWB has' not fully performed under the original December 14,1980 contract, and, in any event this matter should be arbitrated pursuant to an agreement in the December 4,1980 contract to arbitrate “all claims, disputes and other matters in question between the contractor and the owner arising out of, or relating to, the contract documents.” Defendant’s Motion in Opposition, Exhibit A, § 7.9.1 at 12.

DISCUSSION

Rule 56(c) of the Federal Rules of Civil Procedure considers summary judgment and provides in part:

The judgment sought shall be rendered forthwith if the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

Summary Judgment is an extreme remedy which is not to be entered unless the movant has established its right to a judgment with such clarity as to leave no room for controversy, and that the other party is not entitled to recover under any discernable circumstances. Weber v. Towner County, 565 F.2d 1001 (8th Cir.1977); See Tomalewski v. State Farm Insurance Co., 494 F.2d 882 (3d Cir.1974); Janek v. Celebrezze, 336 F.2d 828 (3d Cir.1964). In passing upon a motion for summary judgment the Court is required to review the facts in the light most favorable to the party opposing the motion. Adickes v. S.H. Kress & Co., 398 U.S. 144, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970); United States v. Diebold, Inc., 369 U.S. 654, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962).

RWB asserts that, in the January 28th letter and the February 26th release, MRDC expressly agreed to pay the $66,000 due RWB and convey plot # 142 upon the closing of Building # 322 of Mahogany Run Condominiums, and MRDC admits that Building # 322 has been closed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Insurance Exchange v. Virgin Islands Enterprises, Inc.
264 F. Supp. 2d 261 (Virgin Islands, 2003)
Hendricks v. Transportation Services of St. John, Inc.
41 V.I. 21 (Supreme Court of The Virgin Islands, 1999)
Fleming v. Frett
33 V.I. 58 (Supreme Court of The Virgin Islands, 1995)
Bussue v. Paradise Motors, Inc.
29 V.I. 181 (Virgin Islands, 1994)
Battle v. Industrious
26 V.I. 83 (Supreme Court of The Virgin Islands, 1991)
Hadley v. Gerrie
124 B.R. 679 (Virgin Islands, 1991)
Whitfield v. International Motors Corp.
24 V.I. 151 (Supreme Court of The Virgin Islands, 1989)
Dennie v. University of Pittsburgh School of Medicine
638 F. Supp. 1005 (W.D. Pennsylvania, 1986)
Abramson v. Small Business Development Agency
20 V.I. 167 (Virgin Islands, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
550 F. Supp. 1095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-wible-brown-inc-v-mahogany-run-development-corp-vid-1982.