Reed Stenhouse, Inc. of Missouri v. Portnoy

642 S.W.2d 947, 1982 Mo. App. LEXIS 3272
CourtMissouri Court of Appeals
DecidedNovember 16, 1982
Docket43951, 43975
StatusPublished
Cited by13 cases

This text of 642 S.W.2d 947 (Reed Stenhouse, Inc. of Missouri v. Portnoy) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed Stenhouse, Inc. of Missouri v. Portnoy, 642 S.W.2d 947, 1982 Mo. App. LEXIS 3272 (Mo. Ct. App. 1982).

Opinion

DOWD, Judge.

This is an appeal from an order of the Circuit Court of St. Louis County sustaining Reed Stenhouse, Inc.’s (hereinafter plaintiff) motion for new trial following a verdict by a jury for Paul Portnoy (hereinafter defendant) on his counterclaim for $84,-000.00 plus interest in a breach of contract suit initiated by plaintiff. 1 The jury found against plaintiff on its cause of action against the defendant. 2

*949 We affirm the action of the trial court in granting plaintiff a new trial.

The following facts were adduced at trial. Plaintiff brought an action against defendant to recover monies paid pursuant to a contract for the purchase of defendant’s insurance business. Defendant counterclaimed alleging plaintiff owed him the balance due on the contract. The jury returned a verdict for defendant and assessed damages at $84,000 plus 6% interest as stated in the contract. 3

Plaintiff contracted with defendant to purchase defendant’s book of insurance business which consisted mainly of an account with the Permaneer Corporation. Under the terms of the agreement defendant was to receive a total of $320,000.00 for the business and a covenant not to compete. 4 Plaintiff by drafting paragraph 2B of the agreement attempted to provide a mechanism for adjusting the purchase price in the event the Permaneer account was lost or reduced. This provided for funding the payment amortization out of commissions actually earned from the Permaneer account and for the reduction in payments. Defendant and plaintiff also agreed that defendant would act as a consultant for plaintiff. In addition, plaintiff entered into a separate letter agreement with the Per-maneer Corp., whereby Permaneer would give plaintiff a right of first refusal to match competitive offers from other brokerage firms. Defendant was not a party to this agreement.

The agreement between plaintiff and defendant was executed in June 1974, effective as of January 1,1974. Payment under the agreement was apportioned as follows: $220,000 to the book of business and $100,-000 payable at $20,000 annually to the covenant not to compete. Defendant received $84,000 immediately upon the execution of the contract and another $84,000 in January 1975 plus $9000 in accumulated interest. Prior to July 1975 plaintiff’s branch manager had discussed the agreement for a right of first refusal with the new Chief Executive officer of Permaneer Corporation and understood that Permaneer would recognize in principle the basics of the letter agreement between plaintiff and Permaneer. In July 1975 Fireman’s Fund, the chief carrier for the Permaneer insurance business indicated it would no longer underwrite Perma-neer and cancelled the coverage on July 8, 1975 effective August 8, 1975. Plaintiff then arranged coverage for Permaneer with the Leatherby Company. However, in August of 1975 plaintiff received notice from Leatherby that Johnson & Higgins, a competing insurance brokerage firm, would replace plaintiff as agent of record on the Permaneer account.

Plaintiff then filed suit claiming it had lost the account and that defendant should return all of the consideration paid it. By the trial date plaintiff only claimed the $84,000 consideration paid defendant in advance on January 1, 1975 because the insurance account was lost during that year.

Both plaintiff’s and defendant’s causes of action are based upon the provisions of paragraph 2B of the contract for the sale of defendant’s insurance business wherein it is provided that:

“In the event the Permaneer Corp. insurance account listed on Exhibit ‘A’ here to is lost or in the event the insurance commissions received by ICI with respect to that account decline by 30% or more, ‘the payments’ to be made by ICI to Portnoy as provided in the preceding sub-paragraph (A) hereof, shall be reduced in the same proportions as the amount of commissions lost bears to the annualized commissions income of Portnoy (and *950 Town and Country) as of the date hereof.”

The decisive issue in this case as to the plaintiff was whether the word “payments” as found in paragraph 2B indicated the defendant must return monies already paid for the year 1975 or that only future payments would cease upon the loss of the Permaneer account.

Defendant’s description of his own counterclaim is that ICI did not lose the Perma-neer account in 1975, because it made no effort to keep the account or to enforce the right of first refusal agreement, but rather willingly allowed the account to be transferred because Permaneer was no longer a long term business prospect.

The order of the trial court granting the plaijitiff a new trial was based upon ground # 2 of plaintiff’s motion for new trial and stated “Plaintiff’s Motion for New Trial sustained on ground that error was committed in submitting Inst. 6.” Instruction 6 is defendant’s verdict directing instruction for his counterclaim. As the trial court failed to set forth any detailed reasons for its finding we look to plaintiff’s motion for new trial where the following grounds appear as follows:

“A) The Permaneer account was, as a matter of law, lost to plaintiff in 1975 and it was therefore error to submit such issue to the jury.
B) Said instruction failed to hypothesize and to submit to the jury as an issue of fact defendant’s proposed construction of the language previously held ambiguous by the court.
C) Said instruction was based on MAI 26.02 and is to be used in a contract action only where breach is the sole issue to be determined by the jury and the issue of breach was not the sole issue to be decided by the jury in this case, and
D) Said instruction failed to submit to the jury as an issue of fact the disputed and essential element of substantial performance.”
Instruction No. 6 as requested by defendant reads as follows:
“INSTRUCTION NO. 6
Your verdict must be for defendant on defendant’s counterclaim if you believe:
First, the Permaneer business was not lost to ICI and the commissions received by ICI from the Permaneer account did not decline 30% or more within the meaning of the agreement during 1975; thus leaving a balance due on the contract for Permaneer and other business and,
Second, plaintiff failed to pay to defendant the balance due, and
Third, defendant was thereby damaged.
Source, MAI 26.02 modified by defendant.”

In reviewing a trial court’s order for a new trial, the appellate court must indulge every reasonable inference favorable to the trial court’s ruling and may not reverse unless there has been a clear abuse of discretion in granting the motion. Pihsou Hsu v. Mound City Yellow Cab Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dallas v. American General Life & Accident Insurance
709 F.3d 734 (Eighth Circuit, 2013)
Pointe Development, LLC v. Enterprise Bank & Trust
316 S.W.3d 543 (Missouri Court of Appeals, 2010)
Jablonski v. Barton Mutual Insurance Co.
291 S.W.3d 345 (Missouri Court of Appeals, 2009)
McMillan v. First State Bank of Joplin
935 S.W.2d 329 (Missouri Court of Appeals, 1996)
Boatmen's Bank of Mid-Missouri v. Crossroads West Shopping Center, Ltd.
907 S.W.2d 800 (Missouri Court of Appeals, 1995)
James O'Brien & Associates, Inc. v. American Sportsman Travel, Inc.
819 S.W.2d 62 (Missouri Court of Appeals, 1991)
Penberthy v. Nancy Transportation, Inc.
804 S.W.2d 404 (Missouri Court of Appeals, 1991)
Hildebrand v. Ballard
767 S.W.2d 62 (Missouri Court of Appeals, 1989)
Schlemer v. Connell Agencies of Kimberling City, Inc.
741 S.W.2d 307 (Missouri Court of Appeals, 1987)
Seuf, Inc. v. Bartlett
665 S.W.2d 31 (Missouri Court of Appeals, 1984)
Buder v. Martin
657 S.W.2d 667 (Missouri Court of Appeals, 1983)
Harris v. Washington
654 S.W.2d 303 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
642 S.W.2d 947, 1982 Mo. App. LEXIS 3272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-stenhouse-inc-of-missouri-v-portnoy-moctapp-1982.