Reed & Reed, Inc. v. Weeks Marine, Inc.

335 F. Supp. 2d 110, 2004 U.S. Dist. LEXIS 18088, 2004 WL 2029441
CourtDistrict Court, D. Maine
DecidedSeptember 2, 2004
DocketCIV.02-195-P-H
StatusPublished
Cited by1 cases

This text of 335 F. Supp. 2d 110 (Reed & Reed, Inc. v. Weeks Marine, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed & Reed, Inc. v. Weeks Marine, Inc., 335 F. Supp. 2d 110, 2004 U.S. Dist. LEXIS 18088, 2004 WL 2029441 (D. Me. 2004).

Opinion

AMENDED FINDINGS OF FACT AND CONCLUSIONS OF LAW 1

HORNBY, District Judge.

This case involves a dispute among subcontractors working on the construction of *113 Bath Iron Works’ Land-Level Transfer Facility project in 2000. The parties agree that the defendant’s barge grounded out on underwater railways located on the plaintiffs property. They disagree, however, over who was at fault and over the extent of the damages. I presided at a bench trial in this case on June 7, 8, 9, 14 and August 12. 2 After considering the evidence and the arguments advanced by the parties, I make the following findings of fact and conclusions of law.

I.Findings op Fact

(A) Background; Contractual Relationships

1. A land-level transfer facility enables shipbuilders to assemble and launch ships at land level, rather than launching them from inclined railways. Bath Iron Works (“BIW”) began constructing its land-level transfer facility on the Kennebec River in Bath, Maine, in 1998.

2. The prime construction contract for the land-level transfer facility was between BIW and Clark Builders of Maine LLC (“Clark”).

3. Clark entered into a subcontract with Atkinson Construction (“Atkinson”) for various construction services. Atkinson, in turn, subcontracted work to Callahan Brothers (“Callahan”) and the defendant, Weeks Marine, Inc. (“Weeks”).

4. The plaintiff 3 Reed & Reed, Inc. (“Reed & Reed”) is a general construction contractor, headquartered in Woolwich, Maine.

5. Reed & Reed owns a dockyard in Woolwich, Maine, on the easterly side of the Kennebec River.

6. Callahan is an affiliate of Reed & Reed. Reed & Reed and Callahan share owners, offices, and administrative staff. Reed & Reed created Callahan to pursue union work.

7. Atkinson and Callahan entered into a subcontract on August 11, 1998. Under the terms of that subcontract, Callahan agreed to manufacture eighteen concrete blocks or “grids,” approximately 400 tons each. The concrete grids were designed to rest in the Kennebec River and support the dry dock at the land-level transfer facility.

8. The subcontract provided that Callahan would deliver the concrete grids either FOB the pier at Reed & Reed’s Woolwich yard or FOB launched from marine railways at the Woolwich yard. At the time that Callahan and Atkinson entered into this subcontract, the parties had not determined how Callahan would deliver the grids.

9. Eventually, the parties decided that Callahan would launch the grids from marine railways, which had not yet been constructed.

10. On June 4, 1999, Callahan entered into a subcontract with Reed & Reed. Under the terms of this subcontract, Reed & Reed agreed to construct marine railways (“ways”) at the Woolwich yard that Callahan would use to transport the landing grids from dry land into the Kennebec River. The subcontract between Callahan and Reed & Reed did not contain any specifications for how the ways should be built.

*114 11. On August 1, 1999, Reed & Reed leased the Woolwich yard to Callahan so that Callahan could manufacture the grids at the yard and deliver the grids via the yard’s ways.

12. Reed & Reed finished building the ways in the summer of 2000. The ways are similar to railroad tracks. They consist of two concrete structures (a “north way” and a “south way”), fifty feet apart, each with an iron channel on top, running from above the high tide area on dry land into the Kennebec River. A steel carriage sits on the iron channels and runs down the length of the ways into the river. To launch each concrete grid, Callahan placed the grid on the carriage and slid the carriage down the inclined ways into the river.

13. A triangular steel stop was at the underwater end of each way. The stops were designed to hold the carriage in place when it reached the end of the ways and to prevent the grid from sliding off the end of the ways into the Kennebec River. A rubber bumper was attached to the shore side of each stop. The bumpers were designed to absorb the shock of the 400-ton grid when it hit the stop.

14. On September 21, 1998, Atkinson entered into a subcontract with Weeks. Pursuant to a change order dated January 21, 2000, Weeks agreed to pick up the eighteen grids from the end of the Wool-wich yard ways and to transport the grids across the river to the land-level transfer facility in Bath.

(B) The Ways

15. Weeks planned to pick up the grids from the end of the ways using a barge with a lifting frame on the stern (the end closest to the grid). It was therefore important for Weeks to know the as-built dimensions of the ways so that it could design a barge and lifting system that could get close enough to the grid to lift it without hitting the ways.

16. In September of 1999, Scitus Engineering, a firm working with Reed & Reed during the construction of the ways, prepared some preliminary drawings of the ways. One of these drawings showed that the distance between the outboard face of a launched grid, ready for pickup, and the end of the ways would be two feet. Thus, according to the Scitus Engineering drawing, the ways would extend two feet into the river beyond the point on the ways where the outboard face of the grid would be located when it was ready for pickup.

17. This drawing was provided to Weeks in the Spring of 2000, when Weeks began designing its barge and lifting mechanism.

18. John Karpinski, Weeks’ project manager and the person responsible for designing the procedure for lifting and transporting the grids, relied on the two-foot distance in designing Weeks’ barge and lifting system.

19. Weeks’ final plans for the barge and lifting system are dated August 17, 2000.

20. On September 5, 2000, Scitus Engineering compiled a packet of drawings entitled “Construction Details: Landing Grid Transport & Support Structure.” This signed and sealed packet contained drawings showing how Callahan would launch the grids. The packet also contained the same September, 1999, drawing, depicting the two-foot distance from the outboard face of the launched grid to the end of the ways. Weeks received this packet of drawings around September 7, 2000.

21. On August 31, 2000, Timothy Sanders, Callahan’s senior project manager, called Karpinski and (contrary to the Sci-tus Engineering drawing calling out a two-foot distance between the face of the grid *115 and the end of the way) informed him that the north way actually extended approximately seven feet further into the river than the south way.

22. When Karpinski learned that the north way was longer than the south way, he sent Philip Sheridan, Atkinson’s project engineer, an e-mail expressing concern that the length of the ways would interfere with the barge and lifting frame that he had designed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bader v. Watson
D. Massachusetts, 2024

Cite This Page — Counsel Stack

Bluebook (online)
335 F. Supp. 2d 110, 2004 U.S. Dist. LEXIS 18088, 2004 WL 2029441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-reed-inc-v-weeks-marine-inc-med-2004.