Reed Bros. Stone Co., Inc. v. Pittman Const. Co.

101 S.W.2d 478, 20 Tenn. App. 552, 1936 Tenn. App. LEXIS 46
CourtCourt of Appeals of Tennessee
DecidedJune 27, 1936
StatusPublished
Cited by9 cases

This text of 101 S.W.2d 478 (Reed Bros. Stone Co., Inc. v. Pittman Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed Bros. Stone Co., Inc. v. Pittman Const. Co., 101 S.W.2d 478, 20 Tenn. App. 552, 1936 Tenn. App. LEXIS 46 (Tenn. Ct. App. 1936).

Opinion

DeWITT, J.

The Pittman Construction Company was, in 1932, the principal contractor with the United States Government for the construction of a building for the United States Veterans’ Hospital at Tuskegee, Ala. On January 14, 1932, it entered into a contract with Reed Brothers Stone Company, of Birmingham, Ala., for furnishing stone — limestone trim, cut stone and random ashlar base — in accordance with plans and specifications referred to in said contract, for the sum of $15,000. This amounted to 7,600 cubic feet of stone, so that the average price per cubic foot was $2.12.

The controversy in this cause arose over a supplementary contract between complainant and defendant, which grew out of a change in the plans for the building. Revised plans were submitted by the defendant to the complainant as the basis for bidding for furnishing the stone additionally required. The defendant had not estimated the number of cubic feet called for, but submitted this to the complainant. On February 5, 1932, the complainant submitted to the defendant its proposal by letter as follows :

“Re: Tuskegee Hospital Units. We propose to furnish the additional limestone trim and random ashlar required for this job, as per the revised plans submitted to you, complete as called for in our original contract, all for the sum of five thousand three hundred and twelve and no/100 dollars $5312.

“For your information, in figuring the setting, we estimate the increase in cube to be approximately 2500 cubic feet.

“Please let us have your extra order covering this work as soon as possible. In the meantime, we shall continue preparation of our working drawings.”

It appears without dispute that the additional stone thus called for amounted to 1,808.5 cubic feet. At the unit price of the original contract, that is, $2.12 per cubic foot, this would amount to $3,834.02; but the complainant brought this suit to establish its claim to $5,312. The defendant admits that it owed $3,834.02 and no more. The bill sought a recovery of $3,533.18 as the balance claimed after certain payments had been made. The defendant in its answer admitted that it owed the complainant $1,883.40, which sum it tendered and paid into the registry of the court.

On April 27, 1932 the defendant wrote to the complainant as follows:

*555 “We hereby accept your proposal dated February 5, 1932, covering all additional limestone, with freight allowed, to Tuskegee, Ala., as shown by revised plans and new location of above contract.

“All of the above extra work to be done for five thousand three hundred twelve dollars ($5,312.00).

“If the Veterans Administration should question the correctness of price you will be expected to furnish the evidence to show that your figures are correct.”

By a letter dated April 28, 1932, the complainant acknowledged receipt of the order, as follows:

“We acknowledge receipt of your letter dated April 27th, approving our extra claim on this job amounting to $5,312.00.

“We thank you for this additional business, and are enclosing our formal confirmation order form.”

The order form contained the following: „

“Items required: All additional limestone trim and random ashlar required for the Veterans Hospital Job, Tuskegee, Alabama, as per the revised plans submitted by you on February 1st, 1932, for the sum of $5,312.00.”

Between February 5th and April 27th, there was additional correspondence between these parties relative to the changes made by the Government, which will be hereinafter referred to.

Upon the first hearing of this cause, on the entire record, the chancellor referred the .cause to the clerk and master to report from the evidence on file on the following matters:

(a) What was the contract between the complainant and defendant covering the.extra work sued for in this cause?

(b) What sum, if any, is due and owing from the defendant to the complainant for the extra work involved in this cause?

This was a reference of the whole case to the clerk and master, but no objection was made to it and any objection is therefore treated as waived. Scales v. James, 9 Tenn. App., 306; 53 C. J., 703; 10 R. C. L., 511.

The clerk and master rendered an elaborate report. The substance of his conclusions is as follows:

1. That the contract covering the extra work was that the complainant was to furnish to the defendant all the extra stone required by the revised plans and specifications for $5,312, provided, however, that if the Veterans’ Administration should question the price, the complainant would have to furnish evidence that the price was correct; that the Government did question the price upon finding that the amount of stone required was only 1808.5 cubic feet; that the complainant did not furnish evidence that the price was correct; that the amount of stone furnished was not ascertained until after April 27, 1932, and was until after that date unknown to the defendant; that the defendant was entitled *556 to rely upon the statements of complainant as to the amount of stone required; that complainant intended for defendant to rely •upon its statements; that defendant did rely upon its statements; that under the circumstances shown, complainant is guilty of such unconscientious conduct toward defendant in this transaction that it is in court with unclean hands, and is not entitled to insist that defendant by its conduct accepted its proposal to furnish the extra 'stone at complainant’s stated price without regard to the quantity of stone to be furnished.

2.That the total amount due and owing for the extra stone was $3,834.02, being for 1808.5 cubic feet at a unit price of $2.12 as allowed by the Government; and that there was a balance due on the original and extra contracts of $2,055.20.

The question of allowance of interest or attorney’s fees was reserved to the discretion of the court.

Elaborate exceptions were taken to the report and were overruled by the master and by the chancellor.

A decree was rendered confirming the report and awarding a recovery in favor of the complainant against the defendant for $1,310.67, to be credited with the sum of $871.55 (a sum remaining in the hands of the clerk and master after a previous disbursement of $1,011.85 to a creditor of the complainant) less the costs of the cause. Prom this decree the complainant appealed and has assigned errors challenging the report of the clerk and master and the decree overruling the exceptions thereto.

Upon the theory that the reference and report involved only questions of law, or of mixed questions of law. and fact, the appellant contends that' the whole case is here reviewable de novo; and its assignments are that the chancellor erred:

1. In not holding and decreeing that the contract for the extra stone was that appellant was to furnish appellee with all the extra stone required by the revised plans for $5,312.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re White Motor Credit Corp.
11 B.R. 294 (N.D. Ohio, 1981)
Brock v. Brock
205 So. 2d 903 (Supreme Court of Alabama, 1967)
Huntington v. Lumpkin
281 S.W.2d 403 (Court of Appeals of Tennessee, 1954)
Smith v. Frazier
222 S.W.2d 367 (Tennessee Supreme Court, 1949)
Earle v. Illinois Cent. R. Co.
167 S.W.2d 15 (Court of Appeals of Tennessee, 1942)
Ingram v. Stein
126 S.W.2d 891 (Court of Appeals of Tennessee, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
101 S.W.2d 478, 20 Tenn. App. 552, 1936 Tenn. App. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-bros-stone-co-inc-v-pittman-const-co-tennctapp-1936.