Redwood Fibre Products Co. v. Miller Manufacturing Co.

143 P.2d 389, 61 Cal. App. 2d 505, 1943 Cal. App. LEXIS 679
CourtCalifornia Court of Appeal
DecidedNovember 29, 1943
DocketCiv. 12408
StatusPublished
Cited by9 cases

This text of 143 P.2d 389 (Redwood Fibre Products Co. v. Miller Manufacturing Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redwood Fibre Products Co. v. Miller Manufacturing Co., 143 P.2d 389, 61 Cal. App. 2d 505, 1943 Cal. App. LEXIS 679 (Cal. Ct. App. 1943).

Opinion

KNIGHT, J.

Plaintiff appeals from an order dissolving an attachment levied on a small bank deposit and the undisclosed contents of a safe deposit box.

The writ was issued in an action to recover several sums of money, aggregating $8,782.80, claimed to be due plaintiff on account of the alleged breach of a contract of warranty involving the manufacture and sale by defendants of two *507 mills or machines designed to grind and shred redwood bark. Under the terms of the contract as pleaded defendants expressly agreed that in the event of a breach of the warranty they would repay to plaintiff the cost of the mills, and one of the sums sought to be recovered, to wit, $1,339, represents such cost. The other sums represent items of damage plaintiff claims to have sustained as the result of the alleged breach. The motion to dissolve the attachment was made and granted upon the sole ground that it appeared from the complaint that the action “is one in tort for damages and not on contract,” and therefore does not fall within the scope of that part of subdivision 1 of section 537 of the Code of Civil Procedure which provides that a plaintiff may have the property of the defendant attached “1. In an action upon a contract, express or implied, for the direct payment of money. . . .” The single issue to be determined by the appeal is therefore whether the construction so placed by the trial court upon the cause of action pleaded is sustained by the allegations of the complaint; and in considering and determining that issue it must be presumed that such allegations are true.

The essential facts alleged are as follows: For some time prior to March 5, 1941, plaintiff had been preparing to engage in the business of grinding and shredding redwood bark into bark wool, which it intended to place upon the market and sell for insulation purposes; but in order to do so profitably it was necessary to have two mills built which would be capable of turning out a minimum of 30 tons of bark wool each week. The defendant company operated a manufacturing plant in Modesto where it built grinding mills and machines of different types, and on March 5, 1941, as the result of negotiations between the officers of the two companies, which extended over a period of about three weeks, the defendant “assured and warranted to plaintiff,” so the complaint alleges, “that said defendant could and would build and manufacture two mills for the plaintiff, which would be in all respects fit and proper and suitable for the aforesaid purposes, and would do the aforesaid work satisfactorily and in the required volume, to-wit, that said mills would produce a minimum of at least one car, or 15 tons per week of the finished product, per machine, or a total of 30 tons per week, for a total price for the two machines of Fourteen Hundred ($1400.00) Dollars, plus sales tax; and *508 the said defendant then and there offered to plaintiff to hnild and manufacture said two mills within thirty days and deliver them to plaintiff’s plant at Santa Cruz, California, for said price; and then and there said defendant assured and warranted to plaintiff that if said mills would not do the aforesaid work satisfactorily, that defendant would make them do the work satisfactorily, without any expense, in this connection, to plaintiff, or that in the event said machines should not do the aforesaid work satisfactorily, that the cost of the said mills would be paid by said defendant to plaintiff.” (Italics ours.)

Continuing, the complaint alleges “that on or about the 7th day of March, 1941, the said offer and warranty was confirmed by defendant to plaintiff in writing. That on or about March 10, 1941, the plaintiff transmitted to defendant a written acceptance of the said offer and warranty and accompanied same with a down payment, or deposit of $300.00, as agreed”; that “on or about April 23, 1941, the said mills were delivered by defendant to plaintiff’s plant and coincident therewith, plaintiff paid to defendant the balance in full of the purchase price of said mills with sales tax.”

The complaint then goes on to allege that the mills were installed under the supervision of defendant’s mechanics and factory superintendent, and were set in operation about May 9, 1941, but that they “were never able to do the said required work”; that from May 9, 1941, up to October 1, 1941, defendant’s employees were “continually experimenting and tinkering with said mills” in an endeavor to make them do the required work, and that during that period defendant assured plaintiff that it would make them do the work and “would remedy all defects and deficiencies in said mills at its own expense”; “that on or about August 15, 1941, one of said mills became a complete wreck through its improper construction and unfitness for the required purpose, and said defendant offered to fix same at its own expense if it was returned to said defendant’s factory at Modesto, but after same was so returned by plaintiff, and on or about September 18, 1941, said defendant notified plaintiff that said mill would not be returned,at all except upon the condition that plaintiff pay an additional sum of $185.00 for repairing said mill, upon receipt of the mill; which demand was in express violation of said defendant’s aforesaid assurances and warranty. That on or about September 20, 1941, plaintiff *509 notified said defendant that said machines would not and could not do the aforesaid required work, and that said demanded charge for repairing said wrecked mill was improper and in violation of the aforesaid assurances and warranty, and that if said demanded charge was not withdrawn that plaintiff would return both mills. That said charge was never withdrawn. That on October 1, 1941, on account of the total inability of the said machines to do the aforesaid required work, and on account of the aforesaid failure and refusal of the said defendant to make any further repairs or changes in said machines without charging the plaintiff therefor, and on account of the aforesaid refusal and failure of said defendant to return the mill in its possession except upon condition of plaintiff’s paying the demanded charge for repairing said machine, to wit, on account of the aforesaid breaches of defendant’s assurances and warranty, plaintiff was forced to abandon any further attempts to make said machines do the required work, and any further expenses in trying to make them work, and was forced to purchase other machinery to do the aforesaid required work, and so notified said defendant on said date of October 1, 1941. . . . That neither of the said mills was able to do the required work at all under the normal conditions of the business as known to the defendant, for more than an average continuous run of one-half hour at a time, before a major breakdown would occur, nor for more than a maximum continuous period of operation of four hours, on one occasion, on which occasion that mill completely wrecked itself. That the said mills were not constructed properly by defendant to do the required work. That the said machinery was never able to grind or shred the redwood bark as required, or as warranted, or properly or suitably, nor were they ever able to turn out the produce satisfactorily, or in any volume. That the total finished product turned out by said machines within the entire period from May 9, 1941, to October 1, 1941, was and is negligible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landry v. Marshall
243 Cal. App. 2d 170 (California Court of Appeal, 1966)
Walker v. Phillips
205 Cal. App. 2d 26 (California Court of Appeal, 1962)
Rapoport v. Hoberg
198 Cal. App. 2d 478 (California Court of Appeal, 1961)
E. I. Noxon Construction Co. v. Wallace Process Piping Co.
191 Cal. App. 2d 651 (California Court of Appeal, 1961)
Bringas v. Sullivan
273 P.2d 336 (California Court of Appeal, 1954)
B. J. Carney & Co. v. Murphy
195 P.2d 339 (Idaho Supreme Court, 1948)
Eaton v. Queen
177 P.2d 997 (California Court of Appeal, 1947)
Yosemite Growers Co-op Ass'n v. Case-Swayne Co.
167 P.2d 541 (California Court of Appeal, 1946)
Peterson v. Sherman
157 P.2d 863 (California Court of Appeal, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
143 P.2d 389, 61 Cal. App. 2d 505, 1943 Cal. App. LEXIS 679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redwood-fibre-products-co-v-miller-manufacturing-co-calctapp-1943.