Redlinger & Hanson Co. v. Parker

243 N.W. 792, 62 N.D. 483, 1932 N.D. LEXIS 208
CourtNorth Dakota Supreme Court
DecidedJune 30, 1932
DocketFile No. 6027.
StatusPublished
Cited by1 cases

This text of 243 N.W. 792 (Redlinger & Hanson Co. v. Parker) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redlinger & Hanson Co. v. Parker, 243 N.W. 792, 62 N.D. 483, 1932 N.D. LEXIS 208 (N.D. 1932).

Opinion

*486 Burr, J.

Under contract made with defendant to build the Leland Parker addition to his hotel in Minot and' to remodel and repair the older portion the plaintiff began’work in the-forepart of 1929. The work was to be done under the supervision of the architect employed by defendant.

The contract between th'e parties specifically provides that the “General conditions'of the contract, ’ together, with’this agreement,- Specifications and Drawings, form the Contract” between the parties,’ and these specifications and dialings are entitled “Leland Parker 'Hotel Addition, Minot, North .Dakota, Sheets oné' to fifteen of Specifications entitled General Contract' Leland Parker Hotel Addition, Minot, N. Dak. including General Conditions, pages one to eleven, Bidding" *487 Blanks, Instructions to Contractor, and Sections one to fourteen and addenda dated May 9th, 1929.”

These papers and sheets contain the provisions that “the owner without invalidating the contract may make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly.” They further provide that such work shall be executed under the contract as if these changes were included in the original contract “except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.” It is further provided that the “value of any such changes shall be determined by cost plus ten per cent” and it was máde the duty of the plaintiff to keep and present the correct amount of the net cost in such form as the architect may direct. Plaintiff was to furnish the labor and material for the building.

During the process of building the defendant made several changes and alterations in the plans, and plaintiff says these changes not only increased the cost of material but also delayed the plaintiff in its work and caused it heavy damage. It is evident however, that unless the changes increased the cost plaintiff is not entitled to extra pay, and further that if the changes reduced the cost it was possible the plaintiff would be paid less than the contract price.

The complaint is two fold. It sets forth the terms of the contract in general and then alleges changes and alterations increasing the cost in the sum of $13,865.59 and damages caused by unnecessary delays amounting to $15,566.79. The original contract price was $76,764 and plaintiff admits it received from the defendant, on or before December 21, 1929, the sum of $73,308.75. Thus the plaintiff asks judgment for the remainder of the contract price and the further sum -of $29,432.38 for increased costs and damages, or $32,887.63 in all. The complaint contains “a second cause of action” in which the claim of the plaintiff is alleged under an agreement to furnish labor and material and perform services for the defendant, and that the same were reasonably worth $106,196.38 of which no part has been paid except the sum of $73,308.75. The amount of judgment demanded therein -is $32,887.63 with costs.

The answer sets forth the contract in full and the extras and deductions to be allowed, and then in counterclaim alleges damages to the *488 defendant through delays occasioned by the plaintiff and through faulty work in construction. The defendant alleges the plaintiff is entitled to judgment in the sum of $4,922.4-4; but asks a deduction in the sum of $1,550 because of his counter-claim.

During the trial the court required the plaintiff to elect whether it would stand on the contract or demand quantum meruit relief, and permitted t-he defendant to amend his answer in order to set up his counterclaim. This action of the court is specified as error.

In submitting the case to the jury the court submitted thirty-six questions on behalf of the plaintiff. These asked the jury to find “What if anything is due the plaintiff?” followed by a statement of some proposition in dispute, such as “For addition to.fire escape,” “For any delay caused by plumber,” “For delay, if any, in approving steel details” and similar matters. The court then requested the jury to return “a verdict for the plaintiff without deducting anything which che defendant may prove in his case.”

The court further submitted to the jury on behalf of the defendant special findings asking “What if anything is due the defendant for repainting bath room walls . . . for the sale of the shed . . . for failure to complete the buildings in time . . . for damages for improper construction of roof. . . . ?” The court then said it “asked the jury to bring in a verdict in favor of the defendant if defendant has proved his claims or any of them, without regard to the amount which the jury may find due the plaintiff;” stating that “the court will later adjust the rights of all parties as may be-shown by the verdicts.”

Such action on the part of the court is specified as error on the ground that “there is no authority in law for such proceedings and that the same was not asked for or requested by either parties hereto, and it was a mere arbitrary method by the court without any legal precedent therefor and without any agreement thereto to arrive at a special verdict.”

The jury made thirty-six findings in favor of the plaintiff amounting to $15,236.33, and four in favor of the defendant amounting to $2,637.50.

The defendant thereafter moved for a judgment reducing the amount the jury allowed the plaintiff by the elimination of thirteen items *489 found for it in the special findings. The plaintiff moved for judgment “notwithstanding the verdict returned in favor of the defendant.” ■

The court made an order for judgment in the sum of $6,398.69,. arriving at this amount by taking the findings favorable to the plaintiff, amounting to $15,236.33, deducting therefrom, the sum of $2,637.50, allowed the defendant in the findings in his favor, and disallowing the thirteen findings for plaintiff challenged by the defendant, amounting to $6,200.14. Costs were allowed the plaintiff in the sum of $933.

The plaintiff appeals from this judgment and sets forth thirty-one specifications of error, many of which deal with rulings on the admission of testimony.

Appellant states that there are four general issues presented in this appeal, “excluding assignments of error on the admissibility of evidence.” First. Under the pleadings and .the evidence may the plaintiff recover on the quantum meruit basis- and was it error - on the part of the court to require the plaintiff to elect whether it would proceed on the quantum meruit basis or stand upon the contract ?' • Second. If standing on its contract may the plaintiff recover-for the thirteen items rejected by the court or any of them? Third. “Was the ’defendant entitled to damages because of the failure of the plaintiff to complete the building at the time specified, in the contract?”-. Fourth. “Was the defendant entitled to recover damages for the manner in which the roof was laid and constructed?”

It was not error for the court to require the plaintiff to elect whether it would stand upon the contract or sue upon a quantum meruit account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Shoe Co. v. Hawkinson
18 N.W.2d 761 (North Dakota Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
243 N.W. 792, 62 N.D. 483, 1932 N.D. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redlinger-hanson-co-v-parker-nd-1932.