Redgate v. Boston Redevelopment Authority

311 F. Supp. 43, 1969 U.S. Dist. LEXIS 13742
CourtDistrict Court, D. Massachusetts
DecidedOctober 27, 1969
DocketCiv. A. No. 69-1103-F
StatusPublished

This text of 311 F. Supp. 43 (Redgate v. Boston Redevelopment Authority) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redgate v. Boston Redevelopment Authority, 311 F. Supp. 43, 1969 U.S. Dist. LEXIS 13742 (D. Mass. 1969).

Opinion

ALDRICH, Circuit Judge.

This is a motion to. stay, pending a hearing and decision of a three-judge court upon the constitutionality of a state statute under which the defendant Boston Redevelopment Authority, BRA,1 [44]*44is seeking to evict the plaintiffs from houses taken by eminent domain in 1964 and in which plaintiffs have since been living without permission and without payment of rent. The case was originally addressed to a single district judge, who granted a temporary restraining order as of course on receiving the complaint and then, after two days of hearing testimony, revoked it. That same afternoon plaintiffs appealed to the Court of Appeals, and sought a stay from the Chief Judge, who commenced an immediate hearing, while the defendant, at the request of the court, stipulated to an informal stay. The hearing was continued the next day, following which the stipulation was continued, and a three-judge district court was constituted. The next day, Friday, October 24, a hearing was held by this court on the matter of the issuance of a formal stay.

The reason for this immediacy is to be found in the facts. The BRA is under contract and is endeavoring to erect a 210-unit non-profit, low rental project, costing approximately $5,000,000., sponsored by a multi-denominational group of local churches and a synagogue. The last day upon which delivery of the cleared site must be made to the contractor is Monday, November 3. If this delivery is not effected the contract, at best, must be renegotiated at, without question, substantially increased cost and delay, because of the onset of winter. Any increase whatever in cost will cause the project to exceed the federal authorization. There is no certainty that this can be enlarged even with a delay, and considerable danger that it could not be. The single judge found,

“Continuance of the restraining order would seriously endanger the start of a project providing low cost housing for over two hundred families, to the general detriment of the community * * * [and] would cause irreparable harm to the Boston Redevelopment Authority.”

We come, then, to the problem. Plaintiffs assert that the statute, which, they concede, resulted in a lawful taking of their property in 1964 (a matter the most presently conspicuous of them contested in the state court some while back) is unconstitutional because it does not provide for a hearing in connection with the requirement that they vacate the premises, but provides merely for a 30-day notice to quit.2 Plaintiffs say that had they received a hearing it could be made to appear that under certain regulations which they say are applicable they should have received 90 days’ notice, rather than 30, and would have had an opportunity to show that they had not been offered suitable housing accommodations to move into, as required by the removal plan that was an integral part of the taking.3

Plaintiffs alternatively allege that they were denied equal protection [45]*45of the laws because a Massachusetts statute, G.L. c. 239 § 9, provides that a tenant may, in the discretion of the court, obtain a stay of eviction up to six months, a right which chapter 79 does not give them. The claim that plaintiffs are tenants, when they have no lease, oral or written, have paid neither rent nor taxes for four years, and have received nothing from the owner of the premises except a prior demand that they quit delivered in 1965, stretches the meaning of tenancy to its limits. Plaintiffs have been allowed to stay merely because BRA has not needed the property. It has been moving out other occupants, some sixty in number, who have gone voluntarily, and has not previously joined issue with the present five plaintiffs, whose attitude has made it apparent that voluntariness was not for them.4

The equal protection claim, that plaintiffs were entitled to the same procedure as that afforded to tenants occupying under a lease, overlooks the fact that the Massachusetts tenancy statute expressly exempts from its terms evictions for non-payment of rent. Furthermore, all the tenancy statute provides is a discretionary extention. The urban redevelopment statute gives less absolute time, but it imposes on the authority the duty to find suitable relocation facilities. This claim is totally frivolous.

Before we reach the substantive question of the unconstitutionality of the statute because it fails to provide for a hearing, or, more exactly, the probability of eventual success which plaintiffs must establish in order to obtain a stay, we must consider, what the writer of this opinion advised counsel from the outset was an issue, the standing of these plaintiffs, in the light of their past conduct, presently to seek an injunction. This requires a further factual statement.

On August 22, 1969 BRA sent each of the plaintiffs by registered mail a notice to quit in 30 days pursuant to the terms of the statute. Plaintiffs refused to receive the letters, and they were returned, unopened. Plaintiffs’ counsel candidly concedes that this was in accordance with plaintiffs’ long established custom not to pay attention to communications from the BRA. Counsel also concedes, as he must, that plaintiffs had no knowledge whether the letters contained 30-day notices, 90-day notices, or even advice of unexceptionable opportunities to relocate. In connection with this latter subject, the evidence is undisputed that many discussions were sought to be had with plaintiffs on the subject of relocation, but plaintiffs were uniformly “uncooperative.” 5

In answer to the court’s remark on the subject of plaintiffs’ refusal to accept communications from the BRA, that evidently plaintiffs “didn’t care what the BRA might have to say,” counsel protested, but supplied no substance to support the protest.

During early September, following the refusal of the registered letters, 30-day notices in accordance with the statute [46]*46were served upon the plaintiffs in hand, or at the premises, by a constable. The notices, both the ones refused, and the ones served, stated that plaintiffs were to vacate within 30 days, and quoted the statute, n. 2, swpra, to the effect that on refusal to comply they faced eviction by force. In addition, plaintiffs were informed in writing of offers of relocation. To these, too, plaintiffs made no response.

Plaintiffs presently state, through counsel, that the rents involved in the offered facilities were too high, but even this much reply was not made until they got into court. When, in response to court questioning on the aforesaid second hearing on the stay, it was brought out that plaintiffs had as of the day before, received offers in public housing in which the rent was very small, plaintiffs replied, through counsel, that they had heard that this housing was unclean, exposed to vandalism, and had a leaky roof. Pressed further, whether any offer, including temporary hotel accommodations pending the finding of suitable permanent housing, would satisfy plaintiffs, counsel replied that his clients would rather stand on their legal rights.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 9
Massachusetts § 9

Cite This Page — Counsel Stack

Bluebook (online)
311 F. Supp. 43, 1969 U.S. Dist. LEXIS 13742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redgate-v-boston-redevelopment-authority-mad-1969.