Redevelopment Agency v. Salvation Army

127 Cal. Rptr. 2d 30, 103 Cal. App. 4th 755, 2002 Daily Journal DAR 12950, 2002 Cal. Daily Op. Serv. 11137, 2002 Cal. App. LEXIS 4976
CourtCalifornia Court of Appeal
DecidedOctober 21, 2002
DocketD038835
StatusPublished
Cited by7 cases

This text of 127 Cal. Rptr. 2d 30 (Redevelopment Agency v. Salvation Army) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redevelopment Agency v. Salvation Army, 127 Cal. Rptr. 2d 30, 103 Cal. App. 4th 755, 2002 Daily Journal DAR 12950, 2002 Cal. Daily Op. Serv. 11137, 2002 Cal. App. LEXIS 4976 (Cal. Ct. App. 2002).

Opinion

Opinion

KREMER, P. J.

Defendant Salvation Army (Army) appeals the portion of a judgment after court trial favoring plaintiff Redevelopment Agency of the City of San Diego (Agency) on Agency’s cause of action for cost recovery under the Polanco Redevelopment Act (Health & Saf. Code, § 33459 et seq., Polanco Act). Army contends the court erred in concluding Agency satisfied the legal requirements for recovery of such costs. Army also contends the court should have awarded Army its litigation costs and attorney fees. We affirm the judgment.

I

Introduction

Army owned a parcel (the Property) located in an area where Agency was acquiring properties for a redevelopment project. In accord with the Polanco *758 Act, Agency gave Army notices to submit a timely proposed action plan for remediating hazardous substances on the Property. However, when Army failed to submit any plan by the statutory deadline, Agency proceeded to take actions it deemed necessary to remove hazardous substances from the Property.

Agency developed a master work plan for the redevelopment project that received the approval of the County of San Diego Department of Environmental Health (County Department), the regulatory agency overseeing the redevelopment project. After filing this lawsuit against Army for eminent domain, cost recovery under the Polanco Act and declaratory relief, Agency took possession of the Property. Later, the County Department approved a property mitigation plan submitted by Agency for remediation of the Property. After discovering lead contamination in bum ash 1 found at the Property, Agency received the County Department’s approval for an amendment to the property mitigation plan to establish a cleanup level for the lead. Agency proceeded to complete the remediation work contemplated in the amended property mitigation plan.

Meanwhile, after the parties to this lawsuit settled all claims on Agency’s cause of action for eminent domain, the court entered a final order of condemnation vesting title to the Property in Agency. When the lawsuit ultimately came on for trial, Agency’s only remaining cause of action was for recovery of costs under the Polanco Act. At trial, Agency claimed entitlement to costs it incurred in performing remediation of hazardous substances at the Property, including the excavation and removal of contaminated soil. In defending against Agency’s Polanco Act claim, Army argued Agency was not entitled to recover those costs since Agency assertedly failed to comply with procedural requirements of federal law 2 purportedly incorporated into the Polanco Act. After trial, the court awarded Agency its costs requested under the Polanco Act.

On appeal, Army contends Agency’s excavation and waste disposal costs were not recoverable under the Polanco Act since those costs were assertedly not within the scope of CERCLA but instead were incurred only to comply with state waste disposal regulations. Army also contends Agency did not demonstrate that Army was a “responsible party” subject to liability under *759 the Polanco Act. Army further contends Agency did not satisfy a condition precedent for recovery under the Polanco Act, to wit, a request that Army submit a proposed remedial action plan for the Property. Finally, Army contends it was entitled to an award of its litigation costs and attorney fees. However, since Army has not shown any prejudicial judicial error, the judgment must be upheld.

II

Factual and Procedural Background

Army owned the Property, a parcel in the East Village Redevelopment District of downtown San Diego. In the process of acquiring properties necessary for its redevelopment project, Agency took steps to ensure that acquired properties would be remediated of hazardous substances.

In March 1998 Agency retained an environmental consultant, Environmental Business Solutions, Inc. (EBS), to work with the County Department to prepare a phase I environmental site assessment of 35 blocks in the redevelopment area by researching the current and historical uses of properties to assess the likelihood that a release of hazardous substances requiring remediation had occurred there. Upon identifying a possible underground storage tank under the sidewalk adjacent to the Property as a potential pollution problem, EBS prepared an “Initial Scope of Work” to address the tank and any other possible contamination at the Property. The Initial Scope of Work included a comprehensive site reconnaissance and a phase II site assessment of the Property involving investigation of hazardous materials and wastes.

In September 1998 Agency sent Army a notice requesting that Army submit a proposed remediation action plan for the Property within the 60-day time limit established by the Polanco Act. (Health & Saf. Code, § 33459.1, subd. (b)(2).) The notice also stated Army would be held liable for the costs to remediate the Property if Army failed to submit a plan. Included with the notice was the Initial Scope of Work that identified some of the potential hazardous substances at the Property and requested that Army perform additional work. In October 1998 Agency sent Army a notice extending by an additional 30 days the time for Army to submit a proposed remediation action plan. However, Army did not respond to Agency’s notices.

Meanwhile, in October 1998, upon Agency’s request, the California Environmental Protection Agency designated the County Department as the *760 lead regulatory agency to provide oversight for the redevelopment project. (Health & Saf. Code, § 33459.1, subds. (a)(1), (d).) 3

In 1999 Agency worked with the County Department to develop a master work plan describing the assessment and remedial plan for the redevelopment project area. During the process, the master work plan was available for public comment and Agency conducted a public hearing to discuss that plan. However, Army did not submit comments or attend the hearing.

In August 1999 the County Department notified Army of an unauthorized release of hazardous substances from an underground storage tank at the Property. In September 1999 the County Department asked Army to submit a work plan describing its activities to investigate that unauthorized release.

Also in September 1999, the County Department approved Agency’s master work plan. The master work plan certified that actions consistent with its procedures and methodologies were deemed consistent with the national contingency plan. Further, in approving the master work plan, the County Department found conformance with that plan constituted compliance with the national contingency plan.

In February 2000 Agency filed this lawsuit against Army. Upon Agency’s deposit of $100 for acquisition of the Property, the court issued an order for possession of the Property, with possession to be effective on May 8, 2000.

In March 2000 Army submitted to the County Department a work plan to remove the underground storage tank and assess the surrounding area.

On May 8, 2000, Agency took possession of the Property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Modesto v. The Dow Chemical Co.
California Court of Appeal, 2018
City of Modesto v. Dow Chemical Co.
California Court of Appeal, 2018
City of Modesto v. Dow Chem. Co.
227 Cal. Rptr. 3d 764 (California Court of Appeals, 5th District, 2018)
Redevelopment Agency of San Diego v. Mesdaq
65 Cal. Rptr. 3d 372 (California Court of Appeal, 2007)
Block v. Golden Eagle Ins. Corp.
17 Cal. Rptr. 3d 13 (California Court of Appeal, 2004)
City of Modesto Redevelopment Agency v. Superior Court
13 Cal. Rptr. 3d 865 (California Court of Appeal, 2004)
Redevelopment Agency v. San Diego Gas & Electric Co.
4 Cal. Rptr. 3d 317 (California Court of Appeal, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
127 Cal. Rptr. 2d 30, 103 Cal. App. 4th 755, 2002 Daily Journal DAR 12950, 2002 Cal. Daily Op. Serv. 11137, 2002 Cal. App. LEXIS 4976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redevelopment-agency-v-salvation-army-calctapp-2002.