Redden v. Glade Creek Coal & Lumber Co.

141 S.E. 639, 105 W. Va. 138, 1928 W. Va. LEXIS 28
CourtWest Virginia Supreme Court
DecidedFebruary 7, 1928
Docket6024
StatusPublished
Cited by1 cases

This text of 141 S.E. 639 (Redden v. Glade Creek Coal & Lumber Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redden v. Glade Creek Coal & Lumber Co., 141 S.E. 639, 105 W. Va. 138, 1928 W. Va. LEXIS 28 (W. Va. 1928).

Opinion

Lively, Judse:

This writ brings up for review a verdict and judgment for $1,073.32 in favor of plaintiff Redden. against Glade Creek Coal & Lumber Company (hereinafter called the Company), on a logging contract. Redden is a logging contractor, and the company manufactures lumber from timber owned by it on Glade Creek in Raleigh County. A written contract was entered into by them on September 15, 1922, by which Red *140 den agreed to fell and cut into logs the merchantable timber on the east water shed of Glade Creek from the railroad crossing near its mouth to the mouth of Polls Branch, and deliver the logs to within sixty feet of the company’s railroad at $6.00 per thousand feet, log measure, payments to be made on the 15th of each month for the timber delivered the preceding month, except 10% which was to be retained until the contract was finished. The measurement of the logs was to be made at defendant’s mill by its scaler by Doyle rule. It was provided that should Redden fail to deliver logs at a “reasonable rate” defendant company reserved the right to go upon the property and deliver the remaining timber and charge the additional expense to Redden and that he, Redden, should forfeit the retention money (the 10% retained by the company until the completion of the contract). After performance of the contract began it was agreed that the measurement of the logs should be at the place the logs were delivered along the railroad to avoid confusion with other logs at the mill cut by other persons. It seems that the railroad had not been constructed through the timber embraced in the contract at the time of the contract, but had been graded only; and that other loggers had contracts for cutting logs beyond the territory embraced in Redden’s contract (that is above the mouth of Polls Branch), which logs would be hauled out over the railroad when extended to the other •outlying territory. Glade Creek lies between mountains with precipitous sides running down to the creek. The water shed embraced in plaintiff’s contract lying on the east side and below the mouth of Polls Branch was steep, and the method of delivering the logs to within sixty feet of the railroad (which was partially constructed up the creek), was by rolling or sliding the logs down the hillside called in the woodman’s vernacular “ballhooting”. It appears that after the railroad was completed through the tract, the contract was still being carried out and this “ballhooting method” used by plaintiff caused damage to the railroad. The logs would not always stop rolling or sliding before they reached the railroad but would be projected upon it causing damage and delay. Between the 1st and 15th of May, 1923, the log road *141 was constructed through that part of the tract which was then being cut by plaintiff and the logs therefrom damaged the railroad so that it could not be used to deliver logs to the mill from territory beyond the place of injury. Defendant, claiming that it was necessary for the operation of its large mill to have the logs from the territory beyond the places of injury and obstruction in order tO' meet the demand for' logs at the mill, (which had a capacity of about 30,000 feet per day), ordered plaintiff to cease “ballhooting” the logs. Thereupon, plaintiff practically ceased his cutting. At that time he had been cutting about seven and one-half months, and had cut about one-half of the timber. In the meantime, from September, 1922, to about the middle of May, 1923, he had cut and delivered many logs, and had been advanced sums on the estimates,, defendant retaining 10%. In September, 1923, an attempt was made at settlement which failed because plaintiff insisted that he had delivered ’ more logs, and hence more feet of lumber, than defendant had given him credit for by its measurement. Defendant would not settle nor pay any further sums, and then this suit began. Plaintiff claimed that he had cut and delivered 2,692 logs and that each log would average 150 feet, making in all 403,800 feet, and that defendant had paid for 297,071 feet, which left a balance coming to him of $640.38 calculated at $6.00 per thousand. This sum, $640.38, together with 99 logs yet in the woods and not removed amounting to $89.10, and for fifteen logs which had gone beyond the railroad grade into the creek and washed away and for which he claimed $13.50, making the principal amount for which the suit is brought, not including the retention of $178.24 and the interest on the claim amounting to $202.25. Defendant, according to its testimony, had received 2,141 logs at the mill which had been sealed by its sealer in accordance with the contract and which amounted to 297,071 feet actual measurement and for which it had paid plaintiff. Thus it will be seen that 551 logs were unaccounted for and the first assignment of error is based on this controversy. The first assignment is that the verdict is excessive. It is conceded by defendant that the jury had the right, under the evidence, to find that *142 551 logs bad not been accounted for. Plaintiff said be bad. cut these logs delivered them to tbe railroad and that they bad been removed by defendant to its mill, while defendant claimed that it bad only.received 2,141 logs at tbe mill, which logs bad been measured according to tbe contract and accounted for. But it is contended by defendant that even if tbe 551 logs were actually received at tbe mill and bad not been measured, plaintiff’s estimation of. tbe amount of feet in these logs at 150 feet per log is a mere guess. It is pointed out that 2,141 logs by actual measurement amounted to 297,071 feet and that this actual measurement should be used for tbe computation of tbe average amount in each log instead of the estimated amount fixed by plaintiff at 150 feet per log. It may be that such would be tbe better method for computation if tbe jury believed the measurements made by tbe scaler were correct and that tbe logs unaccounted for were average logs with those accounted for; but it will be observed that no instruction was offered to tbe jury pointing out any rule or method of weighing tbe evidence in that regard; and we cannot say, as a matter of law, that tbe jury has misconceived or misapplied tbe principle of law contended for.

Defendant plead the general issue and filed a plea of re-coupment, which plea is to tbe effect that under tbe contract plaintiff was to cut tbe timber and deliver tbe logs at a reasonable rate and failure on bis part to deliver tbe logs at a reasonable rate entitled defendant to go upon tbe property and deliver tbe remaining timber and charge additional expense to plaintiff, and retain tbe retention money; and that plaintiff had failed to deliver tbe logs at a reasonable rate; that defendant bad thereupon gone upon tbe property and cut and delivered logs to tbe railroad at an additional expense of $2.00 per thousand feet and was entitled under tbe contract to retain tbe 10% reserve, called in tbe contract tbe retention money. Issue was joined on this plea and this issue furnishes tbe main part of tbe controversy. Tbe points of error in relation thereto are: (1) tbe giving of plaintiff’s instruction No. 1 with respect to tbe meaning of “reasonable rate” as contained in the contract; and (2) tbe rejection of evidence offered on tbe part of defendant for tbe purpose of *143 showing the meaning of the words “reasonable rate” as used in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Workman v. Clear Fork Lumber Co.
163 S.E. 14 (West Virginia Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
141 S.E. 639, 105 W. Va. 138, 1928 W. Va. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redden-v-glade-creek-coal-lumber-co-wva-1928.