Red Roof Inns, Inc. v. Purvis

691 N.E.2d 1341, 1998 Ind. App. LEXIS 137, 1998 WL 100375
CourtIndiana Court of Appeals
DecidedMarch 9, 1998
Docket48A02-9707-CV-438
StatusPublished
Cited by18 cases

This text of 691 N.E.2d 1341 (Red Roof Inns, Inc. v. Purvis) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Roof Inns, Inc. v. Purvis, 691 N.E.2d 1341, 1998 Ind. App. LEXIS 137, 1998 WL 100375 (Ind. Ct. App. 1998).

Opinion

OPINION

KIRSCH, Judge.

Red Roof Inns, Inc. (“Red Roof Inns”), a corporation registered in Indiana, and its employee John Heim 1 (collectively “Red Roof’) bring this interlocutory appeal from the trial court’s denial of Red Roofs two motions for summary judgment on Michael S. Purvis’ claim for the negligent hiring of an independent contractor. Purvis was injured when he fell from a motel roof being repaired by his employer, Reiehart Building and Remodeling, Inc. (Reiehart), an independent contractor hired by Red Roof Inns. At issue is whether Red Roof owed a non-delegable duty to Purvis based on the performance of an act that would probably cause injury to others unless due precaution is taken.

We reverse and remand.

FACTS AND PROCEDURAL HISTORY

In November of 1992, Red Roof Inns entered into a contract with Reiehart for the re-roofing of an inn located in Richmond, Virginia. Reiehart worked exclusively for Red Roof Inns and, during 1992, had completed twenty-two projects for the corporation. The contract provides that Reiehart is responsible for compliance with “[a]ll state, local, and OSHA codes and requirements.” Record at 54.

On December 9, 1992, Purvis, who had been employed by Reiehart for approximately nine months, was assisting his immediate supervisor, Jay Reiehart, in placing a tarpaulin over exposed wood which was later to be re-shingled. The procedure involved nailing boards along the edge of the roof to hold the tarpaulin in place. No netting, harnesses or other personal protective equipment was used. Purvis alleges that, at Jay Reiehart’s command, he walked across the tarpaulin to get a board, slipped and fell some thirty feet to the ground, sustaining serious injuries.

Purvis filed suit against Red Roof Inns, Jay Reiehart, and Reiehart, the business entity. 2 Purvis also named as a defendant John Heim, Red Roof Inns’ project manager, both in his individual capacity and in his capacity as an employee of Red Roof Inns. In Count I of his complaint, Purvis claims that Red Roof supervised Reiehart’s work and failed to ensure that appropriate safety devices were in place. In Count II, he avers that Red Roof negligently hired its employee John Heim.

Red Roof filed a motion for summary judgment in response to the original complaint. In a January 8, 1997 order, the trial court granted the motion on Purvis’ claim against John Heim individually and denied the motion on the claims against Red Roof Inns and John Heim in his employed capacity. Meanwhile, Purvis had amended his complaint to aver negligence in the hiring of Reiehart, the independent contractor.

Red Roof then moved for partial summary judgment on the issue of negligent hiring. In a “Memorandum Decision” dated May 7, 1997, the trial court denied Red Roofs motion for partial summary judgment, finding that evidence and inferences from that evidence support a conclusion that Red Roof owed a duty to Purvis to select a competent contractor. 3

*1343 Red Roof filed its Petition for Certification of Appeal of Interlocutory Order and For Stay of Proceedings Pending Appeal. The trial court certified both the January 8, 1997 and May 7, 1997 orders 4 after which this court accepted jurisdiction of the appeal pursuant to Indiana Appellate Rule 4(B)(6).

DISCUSSION AND DECISION

Standard of Review

The purpose of summary judgment is to end litigation about which there can be no factual dispute and which may be determined as a matter of law. Sizemore v. Arnold, 647 N.E.2d 697, 698 (Ind.Ct.App.1995). When reviewing a decision on a summary judgment motion, this court applies the same standard as does the trial court. Wickey v. Sparks, 642 N.E.2d 262, 265 (Ind.Ct.App.1994), trans. denied (1995). Thus, we are not bound by the findings and conclusions entered by the trial court when ruling on a motion for summary judgment as we base our decision upon the Trial Rule 56(C) materials properly presented to the trial court. Campbell v. Spade, 617 N.E.2d 580, 582-83 (Ind.Ct.App.1993). Summary judgment shall be granted if the designated evidentiary matter demonstrates that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. Ind.Trial Rule 56(C); Wickey, 642 N.E.2d at 265. In determining whether summary judgment is appropriate, all facts and reasonable inferences must be construed against the moving party. Wickey, 642 N.E.2d at 265.

Purvis’ claim against Red Roof sounds in negligence. Thé tort of negligence consists of the following elements: 1) a duty owed to the plaintiff by the defendant; 2) a breach of that duty by the defendant; and 3) injury to the plaintiff proximately caused by that breach. Id. The defendant may obtain summary judgment in a negligence action by demonstrating that the undisputed material facts negate at least one element of the plaintiffs claim. Ramon v. Glenroy Constr. Co., 609 N.E.2d 1123, 1128 (Ind.CtApp.1993), trans. denied.

Negligent Hiring of an Independent Contractor

Purvis argues that Red Roof is liable because it hired Reiehart, the independent contractor, knowing that Reiehart failed to use safety equipment while performing roofing work. Red Roof counters that it does not owe Purvis a duty. The question of whether the law recognizes such an obligation is a legal one for the court. Id.

Our supreme court recently considered the question of duty in the context of the tort, negligent hiring of an independent contractor, as defined in Section 411 of the Restatement (Second) of Torts (“Restatement”). 5 Bagley v. Insight Communications, Co., L.P., 658 N.E.2d 584, 587 (Ind.1995). The court reiterated the general, rule that a principal is not liable for the negligence of an *1344 independent contractor and then recognized the following five exceptions to the general rule of nonliability:

“(1) where the contract requires the performance of intrinsically dangerous work;
(2) where the principal is by law or contract charged with performing the specific duty;
(3) where the act will create a nuisance;
(4) where the act to be performed will probably cause injury to others unless due precaution is taken; and
(5) where the act to be performed is illegal.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swan Lake Holdings, LLC v. Hiles
888 N.E.2d 265 (Indiana Court of Appeals, 2008)
Daisy v. Roach
811 N.E.2d 862 (Indiana Court of Appeals, 2004)
Merrill v. Knauf Fiber Glass GmbH
771 N.E.2d 1258 (Indiana Court of Appeals, 2002)
Kahrs v. Conley
729 N.E.2d 191 (Indiana Court of Appeals, 2000)
Carie v. PSI Energy, Inc.
715 N.E.2d 853 (Indiana Supreme Court, 1999)
McDaniel v. Business Investment Group, Ltd.
709 N.E.2d 17 (Indiana Court of Appeals, 1999)
Ryobi Die Casting v. Montgomery
705 N.E.2d 227 (Indiana Court of Appeals, 1999)
LeBrun v. Conner
702 N.E.2d 754 (Indiana Court of Appeals, 1998)
Johnson v. AAA Chicago Motor Club Insurance
699 N.E.2d 1182 (Indiana Court of Appeals, 1998)
Wabash Grain, Inc. v. Smith
700 N.E.2d 234 (Indiana Court of Appeals, 1998)
Birrell v. Indiana Auto Sales & Repair
698 N.E.2d 6 (Indiana Court of Appeals, 1998)
Carie v. PSI Energy, Inc.
694 N.E.2d 729 (Indiana Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
691 N.E.2d 1341, 1998 Ind. App. LEXIS 137, 1998 WL 100375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-roof-inns-inc-v-purvis-indctapp-1998.