Red Hook Construction, LLC v. Randall C. Bishop, Teresa C. Bishop, and Richard Putnam

CourtAlaska Supreme Court
DecidedOctober 4, 2024
DocketS18809
StatusPublished

This text of Red Hook Construction, LLC v. Randall C. Bishop, Teresa C. Bishop, and Richard Putnam (Red Hook Construction, LLC v. Randall C. Bishop, Teresa C. Bishop, and Richard Putnam) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Hook Construction, LLC v. Randall C. Bishop, Teresa C. Bishop, and Richard Putnam, (Ala. 2024).

Opinion

Notice: This opinion is subject to correction before publication in the PACIFIC REPORTER. Readers are requested to bring errors to the attention of the Clerk of the Appellate Courts, 303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, email corrections@akcourts.gov.

THE SUPREME COURT OF THE STATE OF ALASKA

RED HOOK CONSTRUCTION, LLC, ) ) Supreme Court No. S-18809 Appellant, ) ) Superior Court No. 3KO-18-00306 CI v. ) ) OPINION RANDALL C. BISHOP, TERESA C. ) BISHOP, and RICHARD PUTNAM, ) No. 7726 – October 4, 2024 ) Appellees. )

Appeal from the Superior Court of the State of Alaska, Third Judicial District, Kodiak, Stephen B. Wallace, Judge.

Appearances: Peter A. Scully, Schwabe, Williamson & Wyatt, P.C., Anchorage, for Appellant. Notice of non- participation filed by Jill Wittenbrader, Law Office of Jill Wittenbrader, LLC, Kodiak, for Appellees Randall and Teresa Bishop. No appearance by Appellee Richard Putnam.

Before: Maassen, Chief Justice, and Carney, Borghesan, Henderson, and Pate, Justices.

HENDERSON, Justice.

INTRODUCTION A mother and son co-owned a lot in Kodiak that they wanted to turn into a duplex property. The son contracted with an excavation company to build a retaining wall for the project and made one $15,000 payment to the contractor by credit card. The parties later disputed the terms of the contract and sued each other for breach of contract. The superior court determined that the contractor had breached the contract and issued final judgment in favor of the mother and son. The court’s damages award assumed that the $15,000 credit card payment would be disgorged by the credit card company and the charge reversed. The contractor appealed on matters unrelated to the instant appeal, and we reversed several aspects of the superior court’s decision. More than a year after the court’s issuance of its final judgment, the mother and son moved for relief from the judgment pursuant to Alaska Civil Rule 60(b), asserting that the court was mistaken in assuming that the son would not be held responsible for the $15,000 credit card charge. The court granted relief from judgment under Rule 60(b)(1), finding that it had made a mistake about the credit card payment and adjusting its damages award accordingly. The contractor appeals, asserting the court abused its discretion in granting relief under Rule 60(b)(1) because the mother and son moved for relief more than a year after final judgment, the delay was unreasonable, and the court’s original judgment had not been mistaken. Because the mother and son waited longer than the one year permitted to seek relief under Rule 60(b)(1), we reverse the court’s grant of relief from judgment. FACTS AND PROCEEDINGS We detailed many of the underlying facts in this matter in Red Hook Construction, LLC v. Bishop.1 Here we set forth only the abbreviated facts and proceedings relevant to the issue before us. A. The Bishops’ Lawsuit For Breach of Contract And Red Hook’s First Appeal Randall Bishop and his mother Teresa Bishop co-owned a property in Kodiak that they wanted to develop. The Bishops hired Red Hook Construction, LLC to perform dirt excavation and build a retaining wall for the structure they intended to

1 No. S-18031, 2022 WL 10826078 (Alaska Oct. 19, 2022).

-2- 7726 build. After initially quoting one price that would be due upon completion of the project, Red Hook charged the Bishops in phases during construction. The Bishops paid cash for the initial phase, and then used a credit card to make a $15,000 partial payment for the second phase. The relationship between the parties deteriorated and they sued each other for breach of contract after Red Hook abandoned the project. The Bishops contended the parties formed a fixed-price contract and that the Bishops had suffered losses caused by Red Hook’s breach, including having to hire a second contractor to complete the project. The court conducted a four-day bench trial where the Bishops testified about the damages resulting from Red Hook’s conduct. The Bishops testified that after making the $15,000 partial payment to Red Hook on Teresa Bishop’s credit card, they later concluded that they had been asked to pay more than the contracted amount, and they contacted the credit card company to dispute the charge. Randall confirmed that though he disputed the charge, Red Hook had received payment, and while the credit card company did not require him to pay the disputed amount immediately, the $15,000 remained as an “outstanding” balance on the credit card. The superior court found that the contract was for a fixed price and that Red Hook breached the contract by abandoning the project. In its damages award the court noted that the Bishops “submitted a payment of $15,000 using a credit card” and that the Bishops testified they “subsequently contested the charge through their credit card company as their relationship with [Red Hook] further broke down.” The court did not award expectation damages arising from Red Hook’s breach; instead, it assumed “that once this order issues, [the credit card] dispute will be resolved and the $15,000.00 recovered from [Red Hook]” resulting in the Bishops paying “less than the total contract price” to complete the project. The court issued its final judgment on July 13, 2021, and it was distributed on July 19, 2021. Red Hook subsequently appealed.

-3- 7726 We affirmed the superior court’s finding that the parties had formed a fixed-price contract.2 We also noted the superior court’s assumption that the Bishops would not be held responsible by their credit card company for the $15,000 contested charge, but did not discuss the issue further because the parties were not contesting that aspect of the court’s decision.3 B. The Bishops’ Motion For Relief From Judgment Six months after we issued our opinion in the first appeal, and 21 months after the parties received notice of final judgment, the Bishops filed a motion for relief from judgment under Alaska Civil Rule 60(b). The Bishops’ motion sought compensation for their overpayment of the fixed-price contract. 4 They indicated that “the credit card company did not resolve the dispute in [their] favor[;] rather, it gave the $15,000 to Red Hook.” The Bishops contended Red Hook was “fully aware of the content and spirit of the court’s previous order regarding the credit card payment, specifically that it should be returned to the Bishops,” and that Red Hook received the funds “never informing the court or parties of the new development, and now refuses to return the funds.” Red Hook opposed the Bishops’ motion for relief from judgment on numerous grounds. Relevant to this appeal, Red Hook asserted that the court had not made a mistake, that the Bishops “were the only party who knew” whether they had

2 Id. at *6. 3 Id. at *6 n.8. We reversed other aspects of the damages award not relevant to this appeal. Id. at *10. 4 The Bishops’ motion also included a separate motion for order to show cause asserting the superior court originally ordered the refund of the $15,000, and further sought relief from judgment under Civil Rule 60(a) claiming the court had made a clerical mistake. See Alaska R. Civ. P. 60(a). The superior court denied both requests. Neither ruling is appealed, so we do not consider them further.

-4- 7726 paid the $15,000 5 and did not seek to correct the findings under Alaska Civil Rule 52(b) 6 or on appeal to us, and that the Bishops’ motion was untimely since it was filed more than one year after final judgment. The superior court granted the Bishops’ motion for relief from judgment under Civil Rule 60(b)(1) and awarded expectation damages to the Bishops based on their overpayment. Citing “the evidentiary record as a whole,” the court made several findings to support its grant of relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Link v. O'Link
632 P.2d 225 (Alaska Supreme Court, 1981)
Alaska Truck Transport, Inc. v. Berman Packing Co.
469 P.2d 697 (Alaska Supreme Court, 1970)
Farrell Ex Rel. Farrell v. Dome Laboratories
650 P.2d 380 (Alaska Supreme Court, 1982)
Vezey v. Green
171 P.3d 1125 (Alaska Supreme Court, 2007)
Sandberg v. Sandberg
322 P.3d 879 (Alaska Supreme Court, 2014)
Fernandez v. Fernandez
358 P.3d 562 (Alaska Supreme Court, 2015)
Johnson v. Johnson
394 P.3d 598 (Alaska Supreme Court, 2017)
Bravo v. Aker
435 P.3d 908 (Alaska Supreme Court, 2019)
State v. Mares
2014 WY 126 (Wyoming Supreme Court, 2014)
Nabors v. New England Mutual Life Insurance
204 F.R.D. 6 (D. Massachusetts, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Red Hook Construction, LLC v. Randall C. Bishop, Teresa C. Bishop, and Richard Putnam, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-hook-construction-llc-v-randall-c-bishop-teresa-c-bishop-and-alaska-2024.