Red Bridge Capital LLC v. Dos Lagos LLC

2016 UT App 162, 381 P.3d 1147, 818 Utah Adv. Rep. 54, 2016 Utah App. LEXIS 168, 2016 WL 4074021
CourtCourt of Appeals of Utah
DecidedJuly 29, 2016
Docket20141123-CA
StatusPublished
Cited by2 cases

This text of 2016 UT App 162 (Red Bridge Capital LLC v. Dos Lagos LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Bridge Capital LLC v. Dos Lagos LLC, 2016 UT App 162, 381 P.3d 1147, 818 Utah Adv. Rep. 54, 2016 Utah App. LEXIS 168, 2016 WL 4074021 (Utah Ct. App. 2016).

Opinion

Opinion

GREENWOOD, Senior Judge:

¶1 Dos Lagos LLC, Mellon Valley LLC, Roland N. Walker, and Sally Walker (collectively, Defendants) appeal the district court’s denial of their motion for satisfaction of judgment and grant of attorney fees to Red Bridge Capital LLC. We reverse and remand.

BACKGROUND

¶2 Red Bridge foreclosed on two parcels of property belonging to Mellon (the Foreclosed Parcels) and then sought a deficiency judgment against Defendants. The Foreclosed Parcels were encumbered by a communications easement. Mellon owns two additional parcels (the Strip Parcels) that lie between the two Foreclosed Parcels, and a road lies between the two Strip Parcels. Thus, the most convenient access between the Foreclosed Parcels and the road is over the Strip Parcels.

¶3 To resolve Red Bridge’s deficiency claims, the parties entered into a Settlement Agreement in which Defendants agreed to (1) pay $150,000 to Red Bridge, (2) consent to entry of a deficiency judgment in the amount of $2,000,000, (3) terminate the communications easement as to the Foreclosed Parcels, (4) grant Red Bridge an access and utility easement across the Strip Parcels with two points of entry for each of the Foreclosed Parcels to be selected by Red Bridge, (5) “cause all liens and encumbrances to be removed from the Strip Parcels,” and (6) negotiate in good faith for “a mutually acceptable development agreement” or, if a mutually acceptable agreement could not be reached, transfer title to the Strip Parcels to Red Bridge, “free and clear of any and all liens and encumbrances.” Red Bridge agreed that if “each” of these actions were completed within 180 days, it would file a satisfaction of the $2,000,000 deficiency judgment. If “any” of the actions did not occur within the allotted time, Red Bridge was entitled to collect the judgment.

*1149 ¶4 In the course of fulfilling their obligations under the Settlement Agreement, Defendants discovered that the legal descriptions of the Strip Parcels in an exhibit to the Settlement Agreement incorrectly included a tenth-acre triangle of land (the Elim Parcel) that actually belonged to Elim Valley Planning & Development LLC, which was not a party to the Settlement Agreement. Defendants arranged to have Elim execute an access and utility easement with respect to its property, but Defendants were unable to discharge a $39,000 judgment lien on the Elim Parcel.

¶5 Red Bridge asserted that the Settlement Agreement obligated Defendants to remove the judgment lien from the Elim Parcel and that they failed to comply with their obligations under the Settlement Agreement in two additional respects. First, although Defendants terminated the communications easement as to the Foreclosed Parcels, they were unable to remove it from the Strip Parcels. Second, Defendants never proposed an appropriate development agreement, the parties did not reach an agreement, and Defendants did not transfer the Strip Parcels to Red Bridge after failing to reach an agreement, It is undisputed that Defendants complied with all other obligations necessary for release of the $2,000,000 judgment.

¶6 On May 27, 2014, Defendants filed a motion in the district court seeking a determination that they were entitled to a satisfaction of judgment. They asserted that, to the extent the Settlement Agreement could be read to obligate them to remove the judgment lien from the Elim Parcel, the Settlement Agreement should be reformed due either to mutual mistake' or to unilateral mistake. In the alternative, they asserted that the Elim Parcel was not material to the Settlement Agreement and that they had therefore substantially complied with the Settlement Agreement by removing the title defects on the remaining portions of the Strip Parcels, which would provide Defendants with the required access points to the Foreclosed Parcels. They further argued that Red Bridge waived any obligation they had to remove the communications easement from the Strip Parcels when Red Bridge excluded that easement from a memo purporting to contain a list of “directives for [Defendants] to resolve the title issue in compliance with the parties[’] Settlement Agreement.” Finally, Defendants argued that they fulfilled their obligations with respect to negotiating a development agreement because they negotiated in good faith but were prevented from reaching an agreement because Red Bridge refused to accept any solution short of Mellon deeding the Strip Parcels to Red Bridge.

¶7 The district court scheduled an eviden-tiary hearing on Defendants’ motion for July 3, 2014. The parties submitted a statement of stipulated undisputed facts, along with exhibits the parties agreed should be admitted. The stipulated facts were intended to be “[i]n addition to the statements and facts contained in the exhibits which [were] offered and admitted into evidence at the hearing ... and in addition to any testimony of witnesses that [was] admitted into evidence at the [h]earing.”

¶8 Although Defendants appeared at the hearing ready to present evidence, the court indicated that it saw Defendants’ motion and Red Bridge’s response “basically as cross motions for summary judgment, on the issues.” The court gave the parties the opportunity to make opening statements and asked a number of questions but then refused to take any additional evidence. The court determined that the parol evidence rule precluded it from considering extrinsic evidence relating to Defendants’ mistake arguments and deniéd the motion for satisfaction of judgment because the motion was not “well taken oh many fronts but [was] clearly not sufficient ... either substantively and maybe procedurally.” The court did not further explain its decision.

¶9 The court subsequently issued a written order denying the motion. The order indicated that the court had “made its Findings of Fact and Conclusions of Law upon the record” at the July 3 hearing. Later, in response to a motion by Red Bridge, the district court awarded Red Bridge its attorney fees and costs. Defendants appeal.

ISSUES AND STANDARDS OF REVIEW

1110 Defendants contend that the district court erred in excluding extrinsic evi *1150 dence regarding mistake and in summarily denying their motion for satisfaction without taking evidence or articulating grounds for the denial. 2 A district court’s refusal to consider extrinsic evidence “presents a question of law that we review for correctness.” Equine Assisted Growth & Learning Ass’n v. Carolina Cas. Ins. Co., 2009 UT App 200, ¶ 5, 216 P.3d 971, aff'd, 2011 UT 49, 266 P.3d 733; see also Bennett v. Huish, 2007 UT App 19, ¶ 8, 165 P.3d 917. Essentially, the ¿strict court appears to have treated Defendants’ motion for satisfaction and Red Bridge’s response as cross-motions for summary judgment and ruled as a matter of law. “Summary judgment is proper solely in eases in which no genuine issues of material fact exist and the movant merits judgment as a matter of law.” Spencer v. Pleasant View City, 2003 UT App 379, ¶ 8, 80 P.3d 546 (citation and internal quotation marks omitted). While this is not precisely a summary judgment case, the issue presented on appeal is similar— whether the district court erred in summarily disposing of Defendants’ motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peterson v. State
2024 UT App 159 (Court of Appeals of Utah, 2024)
State v. Bruun
2019 UT App 77 (Court of Appeals of Utah, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2016 UT App 162, 381 P.3d 1147, 818 Utah Adv. Rep. 54, 2016 Utah App. LEXIS 168, 2016 WL 4074021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-bridge-capital-llc-v-dos-lagos-llc-utahctapp-2016.