CORSON, J.

This action was instituted by the plaintiff to recover from the defendant the amount of certain promissory notes executed by the plaintiff, expenses 'attending the defense of an action upon one of said notes, and freight paid by him on a certain theshing rig, claimed by the defendant to have been purchased by the plaintiff, but which the plaintiff refused to. accept. Verdict and judgment being in favor of the plaintiff, the defendant has appealed.

It apears from the record that the plaintiff introduced evidence tending to prove that on or about the 21st day of July, T903, the plaintiff gave an order for certain threshing rig machinery to the defendant which was not accepted by that company; that some ten days later, being advised that the first order had not been accepted, the plaintiff signed a second order, which was accepted by the defendant, and an engine and threshing rig was a few days thereafter shipped to the plaintiff at Salem, in this state; that, upon ¡the arrival of said threshing rig. at Salem, the plaintiff made a partial examination of the same, but was not allowed to unload it, and did not have an opportunity to. fully examine it as it was situated upon the cars at the station; that the general agent of the defendant refused to allow the machinery to be unloaded from the cars until the freight was paid and certain notes and chattel mortgages executed by the plaintiff in accordance with the terms of the order; that the plaintiff was induced to execute the notes and chattel mortgage upon the agreement by the agent that he would retain the notes and chattel mortgage or deposit them at a bank in Canastota until the plaintiff had had an opportunity to fully inspect and examine the machinery; and that, if the plaintiff was not satisfied that the same was such as he had ordered, the notes and chattel mortgage should be returned to him; that thereupon the plaintiff paid the freight, about $150, executed four notes aggregating about $1,850 and a chattel mortgage, and thereupon the machinery was unloaded, and, upon an examination of the same, the plaintiff determined that it did not correspond with the machinery ordered, refused to accept the same, and demanded from the agent his notes [413]*413■and chattel mortgage so executed by him; and the defendant refused to surrender them, and subsequently three of the notes were transferred by the defendant before maturity, and in the usual course of business, and that in an action upon one of the notes judgment was recovered against the plaintiff. The complaint is too lengthy to be inserted in this opinion, but alleges, in substance, the foregoing statement of facts.

The answer set up various defenses, among which was that a written order was executed by the plaintiff; that said written order contained all of the agreement and representations of the defendant in regard to the same and also contains a complete description of the machinery so ordered; that the defendant accepted the order, and immediately sold and delivered the machinery ordered to the plaintiff in all respects described in the order; that the plaintiff is now estopped from claiming that the said machinery is and was not as ordered, and is estopped from asserting that there is a breach of any warranty of said machinery, for the reason that, having taken the same into his possession, the plaintiff neglected and refused .-to attempt to make the same operate as provided in said order ; that plaintiff is estopped by his own agreement from claiming any breach of warranty, or of claiming that the machinery delivered to him by defendant is not in all respects such as plaintiff ordered, for the reason that the order contains the entire contract between plaintiff and defendant in regard to the same, and defendant alleges that he has fully complied with all and every condition of the aforesaid contract and agreement, and demands judgment that the action be dismissed.

Before the commencement of the trial, the defendant moved the court to compel the plaintiff to elect whether he would attempt to recover for breach of warranty as independent damages or whether he would rely only upon the claim for the value of the notes which were given by plaintiff to defendant and claimed to have been sold. The court ruled upon this motion that the complaint clearly shows >a suit for the recovery of the value of the amount of the notes, and thereupon overruled the objection. On the trial plaintiff offered evidence tending to prove the allegations of his complaint. The plaintiff then offered evidence tending to [414]*414prove that, at tlíe time he gave the second order, he was induced to give the same by the general agent of the defendant by -representations made to him that the defendant had a second-hand threshing rig which was -in good running order, the engine not having been used more than io days and never used for threshing but only in the yards of the defendant. This evidence was objected to by the defendant on the ground that it tended to- vary and contradict the terms of a written instrument, and that no such contract had been 'alleged in the complaint. Thereupon the plaintiff moved the court for leave to amend his complaint by alleging therein “that the defendant by its general agent falsely and fraudulently represented to plaintiff that the company had an engine and separator that was practically new and -the engine had never been used for threshing purposes; that the engine had been set up in the shops and run for a period of io days, but was designated as a second-hand engine; that the general agent explained to plaintiff that the engine had never been used for threshing purposes, and all of these representations were falsely and fraudulently made; that the engine and machinery described to- the plaintiff at the time by the general agent were not such as was afterwards shipped in compliance^ with the order, and that the plaintiff at the time understood by the use of the word “secondhand” as explained to him, one that had been simply run in the shops and not for threshing. This amendment was objected to, but was allowed by the court, and 'the defendant excepted, and it now insists that the court erred in permitting the plaintiff to amend his complaint in the manner above specified on the trial. This motion was clearly within the sound judicial discretion of the trial court, and, as no motion was made for a continuance or affidavit filed as provided by section 150 of the Revised Code of Civil Procedure, the court committed no error in allowing the amendment.

Upon the complaint being amended, the court admitted evidence as to the agreement and representations made by defendant’s agent prior to the execution of the contract. The appellant contends that the admission of this evidence was error, as tending to vary and contradict .the terms of the written order;, but this contention is clearly untenable, for the reason that by the written or[415]*415der no particular description' of the engine to be furnished to the plaintiff was given, -the only description being “one Port Huron traction engine, twenty horse power, traction rating, simple compound:” The object and purpose of the evidence was to show that' the plaintiff had been induced by the defendant through its general agent to order the machinery specified in the written contract by fraudulently and falsely representing to him that the company would furnish him an engine that had only been used for a period of io days and was in good working order. In other words, the object of the evidence was to show that the contract executed by the plaintiff was fraudulently obtained from him, and for that reason never in fact became his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tesch v. Tesch
399 N.W.2d 880 (South Dakota Supreme Court, 1987)
DuPratt v. BLACK HILLS LAND AND ABSTRACT COMPANY
140 N.W.2d 386 (South Dakota Supreme Court, 1966)
First Trust Co. v. Commonwealth Co.
98 F.2d 27 (Eighth Circuit, 1938)
Ganley Brothers, Inc. v. Butler Brothers Bldg. Co.
212 N.W. 602 (Supreme Court of Minnesota, 1927)
National Cash Register Co. v. Midway City Creamery Co.
191 N.W. 762 (North Dakota Supreme Court, 1922)
Lehman v. Smith
168 N.W. 857 (South Dakota Supreme Court, 1918)
Kurtz v. Paulson
157 N.W. 305 (North Dakota Supreme Court, 1916)
General Electric Co. v. O'Connell
136 N.W. 404 (Supreme Court of Minnesota, 1912)
A. A. Cooper Wagon & Buggy Co. v. Stedronsky Bros.
123 N.W. 846 (South Dakota Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
118 N.W. 697, 22 S.D. 410, 1908 S.D. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rectenbaugh-v-northwestern-port-huron-co-sd-1908.