Record Steel & Construction, Inc. v. Martel Construction, Inc.

923 P.2d 995, 129 Idaho 288, 1996 Ida. App. LEXIS 90
CourtIdaho Court of Appeals
DecidedJuly 17, 1996
Docket21936
StatusPublished
Cited by6 cases

This text of 923 P.2d 995 (Record Steel & Construction, Inc. v. Martel Construction, Inc.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Record Steel & Construction, Inc. v. Martel Construction, Inc., 923 P.2d 995, 129 Idaho 288, 1996 Ida. App. LEXIS 90 (Idaho Ct. App. 1996).

Opinion

LANSING, Judge.

Record Steel & Construction, Inc. brought this action against Martel Construction, Inc. for breach of contract. The complaint was dismissed by the magistrate court, and the involuntary dismissal was affirmed by the district court acting in its appellate capacity. *290 Record Steel now appeals from that decision. Record Steel also challenges the amount of attorney fees awarded to Martel by both the trial court and the district court.

I.

FACTS AND PROCEDURAL BACKGROUND

Martel was the general contractor on a construction project. By a written contract dated July 3, 1991, Martel subcontracted with Record Steel to install foundation rebar for the project (the rebar contract). This contract specified that disputes regarding its performance would be submitted to arbitration. In November 1991, before the. work under the rebar contract was completed, the parties entered into an oral contract for Record Steel to erect structural steel at the same job site (the structural steel contract). Upon Record Steel’s completion of the structural steel work, Martel paid in full all of Record Steel’s invoices for the structural steel contract, totaling $107,512.14, but Martel subsequently found fault with the quality of Record Steel’s work. To recoup funds expended to correct the structural work, Martel withheld $4,903.97 from payment otherwise owed to Record Steel under the rebar contract. 1

Record Steel filed a complaint in the magistrate division of the district court, alleging that Martel had breached the structural steel contract by failing to make full payment thereunder. Martel filed a motion to dismiss or, alternatively, to compel arbitration, taking the position that the structural steel work fell within the written rebar contract, which provided for mandatory arbitration. This motion was resisted by Record Steel. The magistrate found that there existed two distinct contracts between the parties, a written contract for rebar, which required arbitration, and an oral structural steel contract with no arbitration term. Since the lawsuit was brought on the oral structural steel contract, the motion to compel arbitration was denied. Following the denial of its motion, Martel filed an answer denying liability and a counterclaim for the expenses it allegedly incurred in correcting and completing the structural steel work performed by Record Steel. Record Steel then moved the court for an order prohibiting Martel from introducing at the trial in this case any evidence relating to Record Steel’s performance of the rebar contract and requiring arbitration of disputes arising from the rebar contract. Martel stipulated that this motion be granted, and an order was entered accordingly.

In the subsequent arbitration proceeding on the rebar contract disputes, Record Steel sought recovery only of the amount retained by Martel due to alleged deficiencies in Record Steel’s performance of the rebar contract; Record Steel expressly declined to pursue in the arbitration proceeding any claim for the sums at issue here, which Martel had retained as compensation for Record Steel’s alleged poor or incomplete structural steel work. In the arbitration, Record Steel expressed the view that the latter retainage was not involved in the arbitration because it related to work under the structural steel contract which contained no provision for arbitration.

A court trial was scheduled in the present case, but in lieu of presentation of testimony, the parties submitted the matter to the court for decision on stipulated facts. The stipulated facts included the following: (a) that Martel had paid all amounts that were due Record Steel for work on the structural steel contract; (b) that the sum at issue in this litigation, $4,903.97, was “part of the retention monies that were held back on the written [rebar] contract”; and (c) that Martel’s refusal to pay that sum was based upon alleged expenses Martel incurred in repairing and completing allegedly deficient work performed by Record Steel under the structural steel contract. Following submission of the stipulated facts, Martel moved to dismiss Record Steel’s complaint on the ground that although the complaint alleged breach of the structural steel contract, Record Steel admitted that it had been paid in full for all work performed and materials supplied under that *291 contract. The trial court, treating Martel’s motion as one for involuntary dismissal under I.R.C.P 41(b), granted the motion and dismissed the action on the ground that Martel had fully performed its obligations under the contract upon which the action was brought. The magistrate also found Martel to be the prevailing parly and granted Martel’s request for attorney fees and costs pursuant to I.C. § 12-120(1) and (3).

Record Steel appealed to the district court, which affirmed the magistrate’s Rule 41(b) dismissal and awarded Martel attorney fees and costs on appeal. Record Steel now appeals from that decision, arguing (a) that the magistrate erred in holding that the stipulated facts precluded recovery by Record Steel; (b) that the record shows that Martel breached the implied covenant of good faith and fair dealing; (c) that principles of equitable estoppel, quasi-estoppel and waiver bar Martel from asserting that it has fully performed the structural steel contract; and (d) that the awards of attorney fees to Martel by the magistrate and the district court are excessive.

II.

ANALYSIS

A. The Alleged Breach of Contract

When reviewing an intermediate appellate decision of the district court, we examine the record independent of, but with due regard for, the district court’s decision. Shurtliff v. Northwest Pools, Inc., 120 Idaho 263, 266, 815 P.2d 461, 464 (Ct.App.1991); Matter of McNeely, 119 Idaho 182, 186, 804 P.2d 911, 915 (Ct.App.1990). An appellate court will uphold factual findings made in granting a motion for involuntary dismissal so long as the findings are not clearly erroneous; however, it will review freely any application of the law to the facts found. Staggie v. Idaho Falls Consol. Hosps., Inc., 110 Idaho 349, 351, 715 P.2d 1019, 1021 (Ct.App.1986).

In Record Steel’s complaint it is the structural steel contract, and no other, that is alleged to have been breached by Martel. The rebar contract is not referenced anywhere in the complaint. The magistrate dismissed Record Steel’s action because Record Steel stipulated that it had been paid in full on the structural steel contract, making it impossible to find a breach of that contract by Martel. The magistrate reasoned that if Martel had breached any contract between the parties, it was the separate rebar contract, and that any claim of Record Steel pertinent to that contract was not before the court but, rather, had been the subject of the arbitration proceeding. We find no error in this determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Huyett v. Idaho State University
104 P.3d 946 (Idaho Supreme Court, 2004)
Simons v. Simons
11 P.3d 20 (Idaho Supreme Court, 2000)
Crown v. State, Department of Agriculture
955 P.2d 612 (Idaho Court of Appeals, 1998)
Star Phoenix Mining Co. v. Hecla Mining Co.
939 P.2d 542 (Idaho Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
923 P.2d 995, 129 Idaho 288, 1996 Ida. App. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/record-steel-construction-inc-v-martel-construction-inc-idahoctapp-1996.