REBUILD NORTHWEST FLORIDA INC v. FEDERAL EMERGENCY MANAGEMENT AGENCY

CourtDistrict Court, N.D. Florida
DecidedSeptember 30, 2019
Docket3:17-cv-00441
StatusUnknown

This text of REBUILD NORTHWEST FLORIDA INC v. FEDERAL EMERGENCY MANAGEMENT AGENCY (REBUILD NORTHWEST FLORIDA INC v. FEDERAL EMERGENCY MANAGEMENT AGENCY) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
REBUILD NORTHWEST FLORIDA INC v. FEDERAL EMERGENCY MANAGEMENT AGENCY, (N.D. Fla. 2019).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF FLORIDA PENSACOLA DIVISION

REBUILD NORTHWEST FLORIDA, INC.,

Plaintiff,

v. CASE NO. 3:17cv441-MCR/HTC

FEDERAL EMERGENCY MANAGEMENT AGENCY, BROCK LONG, Administrator of Federal Emergency Management Agency; FLORIDA DIVISION OF EMERGENCY MANAGEMENT,

Defendants. / ORDER The Federal Emergency Management Agency (“FEMA”) previously obligated hazard mitigation grant funds to assist the State of Florida in amounts initially totaling over $400 million after four major hurricanes impacted the State in 2004 and 2005. Plaintiff Rebuild Northwest Florida, Inc. (“Rebuild”) was a subgrantee, approved to receive more than $7 million under the various grants for wind retrofit projects designed to make homes less vulnerable to future storms. The time for Rebuild to perform under its subgrants expired in 2016, but additional original grant money ($16,758,60,916) remained available to the State for distribution to subgrantees until 2017, when FEMA decided to deobligate those remaining funds.1 As a result, those remaining original grant funds are now unavailable to the State for distribution to future projects.

Rebuild brings suit, under the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 702-706, and the Robert T. Stafford Disaster Relief and Emergency Assistance Act (the “Stafford Act”), 42 U.S.C. §§ 5121-5208, asserting in the

Second Amended Complaint that the deobligation decision was improper agency action. Rebuild seeks declaratory relief to establish that the grant funds in the amount of $16,758,60,916 remain available to the State for distribution and, in turn, to Rebuild as a subgrantee. FEMA moves to dismiss, see Fed. R. Civ. P. 12(b)(1),

(6), challenging the Court’s subject matter jurisdiction and alternatively arguing that the complaint fails to state a claim. ECF No. 47. After careful review, the motion will be granted and the case dismissed for lack of jurisdiction.

I. Background2 In the span of a little over one year, Florida was hit by four major hurricanes: Hurricane Charley in August of 2004, Hurricanes Ivan and Jeanne in September of

1 For ease of reference, the Court is collectively referring to the federal Defendants–– FEMA and its administrator, Brock Long––under the term “FEMA.” 2 The facts are taken from the Second Amended Complaint, documents incorporated by reference that are attached to the original Complaint, and portions of the administrative record submitted by FEMA in its first motion to dismiss, ECF No. 16, and incorporated by reference in the pending motion. Documents attached to the pleadings and central to the claims are properly considered on a motion to dismiss. See SFM Holdings, Ltd. v. Banc of America Securities, LLC, 600 F.3d 1334, 1337 (11th Cir. 2010). It is also proper to consider matters outside the complaint on a Rule 12(b)(1) motion. See Lawrence v. Dunbar, 919 F.2d 1525, 1529 (11th Cir. 1990). 2004, and Hurricane Wilma in October of 2005. At the request of Florida’s Governor and pursuant to the president’s discretionary authority under the Stafford Act, 42

U.S.C. § 5170, then-President George W. Bush declared each hurricane a “major disaster” and directed FEMA to provide Florida with disaster relief under the Hazard Mitigation Grant Program (“HMGP”), 42 U.S.C. § 5170c. To carry out this

directive, FEMA and the State of Florida then executed “FEMA-State Agreements” for each hurricane, by which FEMA agreed to grant the State through the Florida Division of Emergency Management (“FDEM”) (grantee) “funds in the amount specified on the obligating document.” ECF No. 1-1 at 7. The FEMA-State

Agreements imposed “binding obligations” on both parties and subgrantees under the Stafford Act’s implementing regulations.3 ECF Nos. 1-1, 1-2, 1-3, 1-4 (Exhibits A, B, C, D); see also 44 C.F.R. §§ 206.44(a), 206.430, et seq. Relevant terms in the

agreements included the following: the grant award activities were to be “completed within the time period prescribed in FEMA regulations and on the obligating documents;” FEMA was authorized to grant extensions of the performance time; FEMA was permitted to assert remedies for noncompliance as provided under

federal regulations; and either party could terminate the agreement on seven days’ notice, e.g., ECF No. 1-1 at 9, 15, 16.

3 The FEMA-State Agreement “imposes binding obligations on FEMA, States, their local governments, and private nonprofit organizations within the States in the form of conditions for assistance which are legally enforceable.” 44 C.F.R. § 206.44(a). The HMGP implementing regulations required FDEM to develop plans for administering and managing the grant funds. See 44 C.F.R. § 206.437. The relevant

FDEM “State Administrative Plans” included terms and procedures by which eligible subgrantees could apply to the State for funds to be used in approved mitigation work, subject to final approval by FEMA.4 The State Administrative

Plans (and also subsequent subgrants) were subject to a Period of Performance (“POP”) limitation that required all HMGP funds to “be disbursed, and all activities completed, not later than three years from the date of the grant award (obligations) to the State.” ECF Nos. 1-5 at 10-11; 1-6 at 11 (emphasis added). FDEM could

request extensions, provided “[t]he total POP should not exceed five years.” ECF Nos. 1-5 at 10-11; 1-6 at 11. Under these terms, which were consistent with the pertinent federal regulations, any “funds not disbursed by [FDEM] within the

approved POP [would] be deobligated and returned to FEMA.”5 ECF Nos. 1-5 at 11; 1-6 at 11. FEMA approved the State Administrative Plans in 2005 and 2006. FDEM subsequently entered into Subgrant Agreements (cost-reimbursement

4 Prior to the award of HMGP funds, a state is required to develop a State Administrative Plan, which is a “brief but substantive plan documenting the State’s process for the administration of the Hazard Mitigation Grant Program.” 44 C.F.R. § 206.437(c), (d). FEMA approved FDEM’s plans for Hurricanes Charley, Ivan, and Jeanne on January 4, 2005, and for Hurricane Wilma on May 31, 2006. ECF Nos. 1-5, 1-6 (Exhibits E, F). 5 The cited regulation, 44 C.F.R. § 13.50, which required the grantee to “immediately refund to the Federal agency any balance of unobligated (unencumbered) cash advanced that is not authorized to be retained for use on other grants,” was “removed and reserved” as of December 19, 2014. See 79 FR 75871-01, 2014 WL 7235775. agreements) with Rebuild, based on its qualifying HMGP proposals. Under the Subgrant Agreements, Rebuild’s performance deadlines, with authorized

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SFM Holdings Ltd. v. Banc of America Securities, LLC
600 F.3d 1334 (Eleventh Circuit, 2010)
McClendon v. Georgia Department of Community Health
261 F.3d 1252 (Eleventh Circuit, 2001)
Allapattah Services, Incorporated v. Exxon Corporation
362 F.3d 739 (Eleventh Circuit, 2004)
McElmurray v. CONSOLIDATED GOV'T, AUGUSTA-RICHMOND COUNTY
501 F.3d 1244 (Eleventh Circuit, 2007)
United States v. Mitchell
463 U.S. 206 (Supreme Court, 1983)
Berkovitz v. United States
486 U.S. 531 (Supreme Court, 1988)
Bowen v. Massachusetts
487 U.S. 879 (Supreme Court, 1988)
Federal Deposit Insurance v. Meyer
510 U.S. 471 (Supreme Court, 1994)
Ruhrgas Ag v. Marathon Oil Co.
526 U.S. 574 (Supreme Court, 1999)
Summers v. Earth Island Institute
555 U.S. 488 (Supreme Court, 2009)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)
Dolcie Lawrence v. Peter Dunbar, United States of America
919 F.2d 1525 (Eleventh Circuit, 1990)
Freeman v. United States
556 F.3d 326 (Fifth Circuit, 2009)
Burgos-Montes v. Municipality of Yauco
294 F. Supp. 2d 141 (D. Puerto Rico, 2003)
Rosas v. Brock
826 F.2d 1004 (Eleventh Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
REBUILD NORTHWEST FLORIDA INC v. FEDERAL EMERGENCY MANAGEMENT AGENCY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rebuild-northwest-florida-inc-v-federal-emergency-management-agency-flnd-2019.