Reber v. Alsace Township

49 Pa. Super. 465, 1912 Pa. Super. LEXIS 353
Superior Court of Pennsylvania·Decided March 1, 1912·No. Appeal, No. 129·Published

Opinion

Opinion by

Pouter, J.,

The plaintiff was, on May 29, 1908, employed by the defendant township and engaged in shoveling gravel at a gravel bank, from which material was being taken to be used upon public roads. The operations at this gravel bank were under the direct supervision of John Lutz, the road master, who was in charge of and directing the entire [467] work upon the public roads of the township, including that at this gravel bank and the plaintiff and all other employees engaged in the work were bound to conform and did conform to his orders. It is not seriously contended by the defendant, and could not be under the evidence, that John Lutz was not a vice principal of the township and the latter is answerable for his negligence, if any there was. The plaintiff had gone to work at this gravel bank for the first time in the morning of the day upon which he was injured, and the accident occurred at about three o’clock in the afternoon. The location -was near the public road and, at the time of the accident, the bank from which the gravel was taken was about eighty-five feet in length, and in height from eleven to fifteen feet above the bottom, where the men worked. The road master had employed under him at this work seven or eight men, three of whom were “diggers” and four or five “shovelers.” The road master was himself present upon the ground all the time and personally directed the several employees as to the manner in which they should perform their duties. The formation of the bank was rather solid and it was necessary to undermine the bank, the road master testified, to a depth of at least eighteen inches, and then make a perpendicular cut in the face of the, bank, so as to deprive the material intended to be thrown down of lateral support. The manner of working which had been adopted by the road master was to have the diggers undermine the bank and do the other work necessary to cause the gravel to fall into the pit at some point in the bank where the shovelers were not working, and after a mass of gravel had thus been thrown into the pit it made what the witnesses called • “stock,” with which the shovélers loaded the wagons; and the diggers went to another part of the pit to undermine the bank at a new point. All the evidence indicated that there was no danger of a fall or slide of gravel, at any given point in this bank, unless the bank had at that point been undermined, and that there was danger of such a fall when the bank had been under[468] mined, the extent of that danger being dependent upon the depth to which the undermining had been carried. The evidence of the road master would have warranted a finding that to permit the diggers to continue their operations at any given point in the bank while the shovelers were engaged in working at the same point involved danger to the latter. The plaintiff had been working as a shoveler at what is referred to in the evidence as “the upper end” of the bank and he testified that at that end of the bank the material for loading the wagons was not obtained by undermining the bank but by simply digging it off from the face of the bank. The road master said in his testimony that the material at that end of the bank was not so solid, but did not expressly say whether the practice of undermining the bank was or was not used at that point. The plaintiff’s work having been confined to the upper part of the bank until the hour named, he and the other man working with him as a shoveler were suddenly called to the lower end of the bank by the road master, who said: “Come down quick and help to load this wagon and then we will get a little blow,” meaning a rest. The plaintiff hurried to obey this order and, there being several men already at work shoveling gravel into the wagon, he took his place at the only position open for him, between the wagon and the bank and about six or eight feet distant from the latter, and began to shovel gravel into the wagon. He had thus been engaged only a few minutes when a large mass of earth and gravel fell from the bank and injured him severely. He subsequently brought this action against the township to recover for such injuries and obtained a judgment in the court below, from which the township has taken this appeal.

The assignments of error raise only the question of the propriety of the action of the court in submitting the case to the jury and entering judgment upon the verdict. The appellant contends that the court should have withdrawn the case from the jury by affirming defendant’s fifth point, which was, “The injury which befell the plaintiff was an [469] apparent risk necessarily incident to his employment, and for such injury he cannot recover;” and the seventh point, which was, “Under all the evidence in the case the verdict must be for the defendant.” The first and second assignments of error refer to the refusal of the above points, and the third to the refusal of the court to enter judgment in favor of the defendant non obstante veredicto.

Free access — add to your briefcase to read the full text and ask questions with AI

Reber v. Alsace Township, 49 Pa. Super. 465, 1912 Pa. Super. LEXIS 353 (Pa. Ct. App. 1912).

49 Pa. Super. 465 (Reber v. Alsace Township) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lee v. Woolsey
109 Pa. 124 (Supreme Court of Pennsylvania, 1885)
Danisch v. Amer
63 A. 416 (Supreme Court of Pennsylvania, 1906)
Dougherty v. Dobson
63 A. 748 (Supreme Court of Pennsylvania, 1906)