Rea v. SIMMONS & SIMMONS CONSTRUCTION CO.

275 S.W.2d 747, 1955 Tex. App. LEXIS 2457
CourtCourt of Appeals of Texas
DecidedFebruary 2, 1955
Docket12775
StatusPublished
Cited by7 cases

This text of 275 S.W.2d 747 (Rea v. SIMMONS & SIMMONS CONSTRUCTION CO.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rea v. SIMMONS & SIMMONS CONSTRUCTION CO., 275 S.W.2d 747, 1955 Tex. App. LEXIS 2457 (Tex. Ct. App. 1955).

Opinion

W. O. MURRAY, Chief Justice.

This suit was instituted by Simmons & Simmons Construction Company, Inc., against W. L. Rea, d/b/a W. L. Rea Construction Company, seeking to recover damages for the breach of an unsigned written contract, whereby plaintiff agreed to do outside electrical work at Foster Air Force Base, Victoria, Texas. Plaintiff was the subcontractor, and defendant the general contractor.

The trial was to a jury, and judgment in the sum of $6,870.16 in favor of plaintiff was based upon the answers of the jury to the issues submitted. W. L. Rea, doing business as W. L. Rea Construction Company, has prosecuted this appeal.

The written contract sued upon was signed by appellee but not signed by appellant, and the question here presented is whether the contract, under all the circumstances, was binding upon appellant so as to hold him liable for damages for a breach thereof.

The jury found~in answer to Special Issue No. 1, that both Jack Jones, general manager of appellee, and W. C. Bon-villain, general manager of appellant, in.r tendqd that thg,written contract.would become binding: on both parties on July 22, 1952, whether or jot, actually signed by both parties.

On July 22, 1952, these two agents met for the purpose of negotiating the contract herein sued upon. After much discussion, Bonvillain had his secretary type up the contract here involved and gave several copies of it to Jones. At this point the statement of facts shows the following:

“Q. What did Mr. Bonvillain do with those written terms after they had been reduced to writing? A. He gave them to me.
“Q. What did he tell you when he gave them to you ? A. He told me to take them, they were in several copies, take them with me, and obtain a bond, have the contract signed, the documents signed, on behalf of our organization, place with it the bonds so obtained, and return it to the W. L. Rea Construction Company for signature.”

This testimony, given by the general manager of appellee, when considered *749 with other evidence, conclusively establishes that it was the intention of the parties that the contract should be in writing and signed by both parties thereto. The contract is set out in full in the statement of facts. It is a formal and complete contract and occupies six pages of the statement of facts.

The preamble to the contract reads as follows:

“This agreement made the twenty second day of July in the year Nineteen Hundred and fifty two, by and between Simmons & Simmons Construction Company, Inc., hereinafter called the Contractor, and W. L. Rea, an in-dividué doing business as W. L. Rea Construction Company, hereinafter called the Owner, witnesseth, that the Contractor and the Owner for the considerations hereinafter named agree as follows

Following this preamble is Article 1, relating to “Scope of the Work,” Article 2 relates to the “time of Completion,” Article 3 relates to “The Contract Sum,” Article 4 relates to “Progress Payments,” Article 5 relates to “Acceptance and final Payment,” Article 6 relates to “The Contract Documents,” and reads as follows:

“The General Conditions of the Contract, the Specifications and the Drawings, together with this Agreement, form the Contract, and they are as fully a part of the Contract as if hereto attached or herein repeated. The following is an enumeration of the Specifications and Drawings:
“All Drawings applicable to the Electrical Distribution System as listed in Contract No. DA-41-243-Eng-1545, Specifications and Addenda one through five.
“In Witness Whereof the parties hereto have executed this Agreement, the day and year first above written.
“W. L. Rea Construction Company
By_
W. L. Rea, Owner
“Acknowledgement:
“Subscribed to and sworn before me this-day-, 1952.
“Simmons & Simmons Construction Co. Inc.
By Jack D. Jones
Jack D. Jones, Sec.-Treas.
“Acknowledgement:
“Subscribed to and sworn before me this 26 day of July, 1952.
“Frances McWilliams
Notary Public
“(Seal: Notary Public County of Travis, Texas)”

This contract shows on its face that it was intended that it should be executed by both parties signing it in the spaces provided for such signatures.

It is undisputed that appellee was to furnish a performance bond in the sum of $27,000.

*750 Jack Jones took these several copies of the written contract with him to Austin. Four days thereafter, on July 26, 1952, he signed the instruments and swore to them before a Notary Public. On the same date he procured a performance bond in the proper amount.

In reply to a question as to what he did with the copies of the contract and the bond, Jack Jones answered as follows:

“I placed it with the required number of copies. I believe there were two or three copies of the document Mr. Bonvillain had given me, signed that document on behalf of Simmons & Simmons Construction Company, placed them in an envelope and mailed them to W. L. Rea Construction Company.”

Three days later Jones received a letter from appellant stating, among other things, that it would be impossible for appellant to enter into the contract.

This evidence, either given by Jack Jones, appellee’s general manager, or supplied by documents introduced by appellee, conclusively proves that the parties intended to enter into a written contract to be signed by each of them. Appellee signed the contract but it was never signed by appellant.

In Vol. 1, Williston on Contracts, § 28a, p. 67, this statement is made: “It is the undoubted rule that where the contract contemplates the execution of it by signing either party has the right to insist upon the condition, and mere acts of performance upon the part of one who has not signed will not validate the contract.”

With reference to part performance by one party, the same section has this to say: “ * * * Acts of performance by one party, unless they have been received as such by the other, cannot be evidence that the latter either had previously made an agreement on definite terms, or that he had subsequently assented to a contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carol M. Kam v. Carl David Adams
Court of Appeals of Texas, 2022
Wetzel v. Sullivan, King & Sabom, P.C.
745 S.W.2d 78 (Court of Appeals of Texas, 1988)
Harrell v. Bakhaus
315 S.W.2d 685 (Court of Appeals of Texas, 1958)
SECURITY FINANCE COMPANY v. Kone
307 S.W.2d 163 (Court of Appeals of Texas, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
275 S.W.2d 747, 1955 Tex. App. LEXIS 2457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rea-v-simmons-simmons-construction-co-texapp-1955.