REA Construction v. Columbia Country Club

CourtCourt of Appeals of South Carolina
DecidedMarch 22, 2004
Docket2004-UP-188
StatusUnpublished

This text of REA Construction v. Columbia Country Club (REA Construction v. Columbia Country Club) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
REA Construction v. Columbia Country Club, (S.C. Ct. App. 2004).

Opinion

PREHEARING REPORT

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


REA Construction Company,        Respondent,

v.

Columbia Country Club,        Appellant.


Appeal from Richland County
Joseph M. Strickland, Master-in-Equity


Unpublished Opinion No. 2004-UP-188
Submitted November 3, 2003 – Filed March 22, 2004


AFFIRMED


Richard D. Ries and John S. Nichols, both of Columbia, for Appellant.

James Coffas and James D. Cooper, Jr., both of Columbia, for Respondent.

PER CURIAM:  In this contract case, REA Construction Company (“REA”) sued Columbia Country Club (“Country Club”) for the remaining balance due on a construction contract, plus interest and attorney’s fees.  The master-in-equity granted judgment to REA, finding Country Club owed REA a total of $135,221.55.  Country Club appeals, arguing: 1) the contract was ambiguous as to whether it was a unit price contract; 2) even assuming the contract was not ambiguous, the contract was orally modified into a fixed price contract; 3) Country Club was not bound by the portions of the contract requiring it to pay interest on past due amounts and attorney’s fees connected with the collection of past due amounts; and 4) REA breached the implied covenant of good faith and fair dealing.  We affirm.

FACTUAL/PROCEDURAL BACKGROUND

In 1998, Country Club solicited bids for a construction project that entailed resurfacing a parking lot, repairing cart paths along a golf course, and completing miscellaneous work to other areas of its business. 

Although REA faxed its proposal to Country Club in July of 1998, Country Club’s board of directors did not approve the project for more than a year. 

On August 11, 1999, Don Litchford, a member of Country Club’s board of directors, signed the “Proposal and Contract Form” (“the contract”) on behalf of Country Club.  William Rosengarten, a commercial manager for REA, signed the contract on REA’s behalf.

The contract provided prices for various units of work to be performed and listed $135,182.50 as the estimated price for the total project. The contract also contained provisions authorizing REA to collect interest on past due amounts and attorney’s fees.

After the parties signed the contract, Ray Ross, Country Club’s representative on the project, met with Tim Metz, an employee of REA, to discuss the scope of work to be completed pursuant to the contract.  

When the work on the project was finished, REA sent a final bill in the amount of $208,406.94.  Country Club made a payment to REA in the amount of $117,407.50, but refused to make additional payments. 

REA commenced this action on October 11, 2000, alleging Country Club breached the contract.  As damages, REA sought the difference between the amount of the final bill and the amount paid by Country Club, as well as interest on the outstanding balance and attorney’s fees.  Country Club answered, denying the breach of contract claim, and counterclaimed for breach of the covenant of good faith and fair dealing, negligence, and unfair trade practices pursuant to the South Carolina Unfair Trade Practices Act. [1]  

In an order dated July 25, 2002, the master found the parties entered into a valid unit price contract, and Country Club had breached that contract by refusing to pay the invoice amount.  Accordingly, REA was awarded a judgment against Country Club for $135,221.55, which consisted of the remainder of the amount billed, plus interest and attorney’s fees.  Country Club appeals.

STANDARD OF REVIEW

“An action to construe a contract is an action at law.”  Pruitt v. South Carolina Med. Malpractice Liab. Joint Underwriting Assoc., 343 S.C. 335, 339, 540 S.E.2d 843, 845 (2001).  In an action at law, the appellate court will correct any error of law, but it must affirm the master’s factual findings unless there is no evidence that reasonably supports those findings.  Sea Cabins on the Ocean IV Homeowners Ass’n v. City of N. Myrtle Beach, 337 S.C. 380, 388, 523 S.E.2d 193, 197 (Ct. App. 1999).

LAW/ANALYSIS

I.          Ambiguous Contract

Country Club argues the master erred by finding the contract was not ambiguous as to whether it was a unit price contract.  We disagree.

If a contract is clear on its face and reasonably susceptible to only one interpretation, it is not ambiguous.  Padgett v. South Carolina Ins. Reserve Fund, 340 S.C. 250, 254, 531 S.E.2d 305, 307 (Ct. App. 2000).  Conversely, “[a] contract is ambiguous when the terms of the contract are reasonably susceptible of more than one interpretation.”  South Carolina Dept. of Natural Res. v. Town of McClellanville, 345 S.C. 617, 623, 550 S.E.2d 299, 302 (2001).  When the language of the contract is ambiguous, parol evidence is allowed to determine the intent of the parties.  Southern Atlantic Fin. Servs. v. Middleton, 349 S.C. 77, 81, 562 S.E.2d 482, 484-85 (Ct. App. 2002). 

The determination of whether the language of a contract is ambiguous is a question of law.  McClellanville, 345 S.C. at 623, 550 S.E.2d at 302-03.

Initially, we note, Country Club does not deny the contract is clear on its face.  The front page of the contract stated the price was “estimated” and the contract was “a unit price contract.”

Instead, Country Club argues these two terms, estimated and unit price contract, each have more than one reasonable meaning, rendering the contract ambiguous.  Specifically, Country Club argues these words in the contract could mean REA was only allowed to charge the estimated amount, and any additional work authorized by Country Club would be billed at a unit price.  The master disagreed with this argument, as do we.

The meaning proposed by Country Club for the term estimated would render the term meaningless.  Further, nothing in the contract required REA to seek Country Club’s approval to exceed the estimated total listed on the front page of the contract. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commercial Credit Corp. v. Nelson Motors, Inc.
147 S.E.2d 481 (Supreme Court of South Carolina, 1966)
Player v. Chandler
382 S.E.2d 891 (Supreme Court of South Carolina, 1989)
Adams v. GJ Creel and Sons, Inc.
465 S.E.2d 84 (Supreme Court of South Carolina, 1995)
South Carolina Department of Natural Resources v. Town of McClellanville
550 S.E.2d 299 (Supreme Court of South Carolina, 2001)
Crosby v. Protective Life Insurance
359 S.E.2d 298 (Court of Appeals of South Carolina, 1987)
Roberts v. Gaskins
486 S.E.2d 771 (Court of Appeals of South Carolina, 1997)
Regions Bank v. Schmauch
582 S.E.2d 432 (Court of Appeals of South Carolina, 2003)
Kumpf v. United Telephone Co. of the Carolinas, Inc.
429 S.E.2d 869 (Court of Appeals of South Carolina, 1993)
Southern Atlantic Financial Services, Inc. v. Middleton
562 S.E.2d 482 (Court of Appeals of South Carolina, 2002)
Pruitt v. South Carolina Medical Malpractice Liability Joint Underwriting Ass'n
540 S.E.2d 843 (Supreme Court of South Carolina, 2001)
Munoz v. Green Tree Financial Corp.
542 S.E.2d 360 (Supreme Court of South Carolina, 2001)
Black v. Hodge
410 S.E.2d 595 (Court of Appeals of South Carolina, 1991)
Padgett v. South Carolina Insurance Reserve Fund
531 S.E.2d 305 (Court of Appeals of South Carolina, 2000)
Pee Dee Nursing Home, Inc. v. Florence General Hospital
419 S.E.2d 834 (Court of Appeals of South Carolina, 1992)
Sea Cabins on the Ocean IV Homeowners Ass'n v. City of North Myrtle Beach
523 S.E.2d 193 (Court of Appeals of South Carolina, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
REA Construction v. Columbia Country Club, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rea-construction-v-columbia-country-club-scctapp-2004.