R.E. Dailey & Co. v. John Madden Co., Ltd.

1 F.3d 1242, 1993 U.S. App. LEXIS 35791, 1993 WL 288269
CourtCourt of Appeals for the First Circuit
DecidedJuly 28, 1993
Docket93-1058
StatusUnpublished
Cited by3 cases

This text of 1 F.3d 1242 (R.E. Dailey & Co. v. John Madden Co., Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.E. Dailey & Co. v. John Madden Co., Ltd., 1 F.3d 1242, 1993 U.S. App. LEXIS 35791, 1993 WL 288269 (1st Cir. 1993).

Opinion

1 F.3d 1242

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
R.E. DAILEY & COMPANY, Plaintiff-Appellant,
v.
JOHN MADDEN COMPANY, LTD.; Detroit Development Group, Ltd.;
John Madden, Jr., jointly and severally; First National
Bank of Boston; Jefferson Street Properties, Inc.,
intervenors, Defendants-Appellees.

No. 93-1058.

United States Court of Appeals, Sixth Circuit.

July 28, 1993.

Before JONES and BATCHELDER, Circuit Judges, and CELEBREZZE, Senior Circuit Judge.

PER CURIAM.

Plaintiff-Appellant R.E. Dailey & Company ("Dailey") appeals the dismissal of its claims for rescission of a Settlement Agreement and the district court's order that it release a construction lien. We affirm the decision of the district court.

* On July 27, 1987, Dailey entered into a Construction Contract with John Madden Company, Ltd. ("Madden Co."). Under the contract, for a guaranteed maximum price of $37,090,000, Dailey was to serve as general contractor relating to the construction of a twenty-eight story office tower and 636-space parking structure at 150 West Jefferson Avenue, Detroit, Michigan. The Construction Contract was amended on August 17, 1987. On August 28, 1987, Madden Co. assigned the Construction Contract to the Detroit Development Group, Ltd. ("DDG").

After construction began, disputes between the parties arose. Dailey, Madden Co. and DDG tried to settle these disputes by entering into a Settlement Agreement on October 28, 1989. Paragraph Two of the Settlement Agreement "converted [the Construction Contract] from a guaranteed maximum price contract to a lump sum contract in the amount of $50,000,000." J.A. at 54. Paragraph Three of the Settlement Agreement detailed how the payment of this lump-sum price was to be accomplished. First, on October 31, 1989, Madden Co. was to pay $4,096,344.48 to Dailey by wire transfer to bring the total amount paid as of October 31, 1989 to Dailey by Madden Co. and DDG up to $45,000,000. There is no dispute that this event actually occurred. The First National Bank of Boston (the "Bank") apparently advanced this money and concomitantly increased the loan amount owed by DDG.1 Second,

[i]n payment for that portion of the Lump Sum Price which is in excess of $45,000,000, Dailey agrees to accept and does hereby accept a 33 percent limited partnership interest in DDG (the "Partnership Interest").... [T]he Madden [Co.] shall raise the sum of at least $94,000,000 for the benefit of DDG, by means of a mortgage or mortgages, the sale of interests in the Project or in DDG, entry into a joint venture, or otherwise, which sum shall be applied to pay costs of the Project and shall not be available for distribution to the partners[.] ... DDG may incur indebtedness in the amount of up to $94,000,000 to pay costs of the Project, and such indebtedness may be secured by a mortgage or mortgages on the Project in such amount....

Id. at 55-56 (Settlement Agreement, p 3(b)). On July 27, 1990, DDG and the Bank amended their Construction Loan Agreement to increase the principal amount of the construction loan from $89,000,000 to $94,500,000. See id. at 144-45 (Second Amendment to Construction Loan Agreement at 1-2).

Also as part of the Settlement Agreement, Dailey agreed that it would not file a construction lien on the property in question:

7. No Liens. Dailey will pay all costs and expenses in connection with the completion of the the [sic] Project including payment of all subcontractors and material suppliers performing work in connection with the Project. Dailey will not file nor permit to be filed any construction lien against the Project based on work performed or to be performed by Dailey or any subcontractor of Dailey hereunder or under the Construction Contract.... In the event a lien is so filed, Dailey will secure its release, by payment or securing an adequate bond, within twenty (20) days after the date Dailey is notified of the recorded filing.

Id. at 57.

Dailey claims that, following execution of the Settlement Agreement, it spent at least $5,000,000 completing the construction project, but has "never received any payment for the balance of its services by way of a partnership interest in DDG or otherwise." J.A. at 288 (Plaintiff's Brief in Opposition to Defendants' Motion for Summary Judgment, for Release of Lien and for Sanctions at 4).

On February 1, 1991, the Bank published a Notice of Foreclosure Sale as a result of failures to repay the construction loan. The foreclosure sale took place in March 1991. Jefferson Street Properties, Inc. ("JSP"), a wholly owned subsidiary of the Bank, purchased the property in question.

On April 15, 1991, Dailey filed a construction lien against the relevant property in the amount of $4,909,472.84. JSP obtained a bond to secure payment of the alleged obligation underlying Dailey's construction lien, which enabled JSP to sell the property to a third party.

On May 7, 1991, Dailey filed its Complaint against Madden Co., DDG, and John Madden, Jr. (a general and controlling partner in Madden Co. and DDG), jointly and severally (together, "Madden"), in the United States District Court for the Eastern District of Michigan. In the first two counts of the Complaint, Dailey sought rescission of the Settlement Agreement. In a third count, Dailey sought damages for breach of the Settlement Agreement. Dailey generally claimed that, "[u]nder the terms of the Settlement Agreement, Madden [Co.] was obligated to raise $94,000,000 for the benefit of DDG, which would have made Dailey's interest in DDG worth $5,000,000," and that "Madden has not raised the agreed upon $94,000,000 and Madden and DDG have not assigned Dailey an interest in DDG worth $5,000,000." Id. at 25 (Complaint, paragraphs 15, 19). In the first count of the Complaint, Dailey sought rescission for failure of consideration, or, "failure and inability of DDG and Madden [Co.] to perform their obligations under the Settlement Agreement." Id. at 26 (Complaint, p 23). In the second count, Dailey sought rescission for "innocent misrepresentation" Id. (Complaint at 5). Specifically, Dailey claimed that the "representations that Madden [Co.] and DDG made regarding Madden [Co.'s] ability to raise not less than $94,000,000 for the benefit of DDG were untrue[ ...; a]t the time Madden [Co.] and DDG made the representations, Madden [Co.] and/or DDG should have known that the representations were untrue[ ...;] Madden [Co.] and DDG made the representations with the intent that Dailey would act upon the representations by entering into the Settlement Agreement"; and Dailey relied on the representations to its detriment. Id. at 26-27 (Complaint, paragraphs 25-29).

On June 27, 1991, Madden filed a Motion for Summary Judgment, for Release of Lien and for Sanctions. On September 30, 1991, the district court granted the motion in part. It dismissed the claim for rescission

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1 F.3d 1242, 1993 U.S. App. LEXIS 35791, 1993 WL 288269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/re-dailey-co-v-john-madden-co-ltd-ca1-1993.